Commonwealth Edison Company 1400 Opus Place -

nownen orove. it. 605t5-s701 10 CFR 50.4 10 CFR 50.54(q) 10 CFR 50 Appendix E October 18,1999 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455 Dresden Nuclear Power Station, Units 1,2 and 3 Facility Operating License Nos. DPR-2, DPR-19 and DPR-25 NRC Docket Nos. 50-10. 50-237 and 50-249 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. STN 50-373 and STN 50-374 Quad Cities Nuclear Power Station, Units 1 and 2 Facility Operating License Nes. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265 Zion Nuclear Pv.ver Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-3_04_

Subject:

Submittal of Changes to Emergency Plan and implementing Procedures in accordance with 10 CFR 50.54(q) and 10 CFR 50, Appendix E,Section V

References:

(4 NRC letter, " Request for Approval of Defueled Station Emergency Plan and Exemption from Certain Requirements of 10 CFR 50.47, ' Emergency Plans'- Zion Nuclear Power j

g Station, Unit Nos.1 and 2," dated August 31,1999 9910220131 991018 PDR ADOCK 05000010 F

PM A Unicom Company

=

~

l October 18,1999 U.S. Nuclear Regulatory Commission

-1 Page 2 (2)

Commonwealth Edison (Comed) Company letter,

" Certification of Permanent Cessation of Operations,"

dated February 13,1998 (3)

Comed letter, " Certification of Permanent Fuel Removal,"

dated March 9,1998

. In the Reference 1 letter, the NRC wproved the Zion Nuclear Power Station (ZNPS) Defueled Station Emergency Plan (DSEP). As part of the DSEP implementation process, we made several changes to Corporate Emergency Plan Implementing Procedures (CEPIPs). In addition, administrative changes modifying a procedure number reference were made to the DSEP. In accordance with 10 CFR 50.54(q) and 10 CFR 50, Appendix E,Section V,

}

" Implementing Procedures," we are reporting the above changes to the NRC.

These changes were made on September 17,1999. This submittalis required to be submitted within 30 days (i.e., by October 17,1999). However, October 17, 1999, falls on a Sunday. Therefore, in accordance with 10 CFR 50.4(d), this submittal is due by the next Federal working day which is October 18,1999., ZNPS DSEP Revision 0," contains the ZNPS DSEP reflecting the administrative changes. Attachment 2, " Implementing Procedures," contains the revised CEPIPs. Changes are indicated in the attached documents by revision bars. Also, CEPIPs 1002-01, " Engineering Drawing Change Approval and Distribution for Emergency Preparedness," and 2021-06, " Highland Park JPIC Activation," have baen deleted due to no longer being necessary.

The ZNPS Emergency Plan Implementing Procedures, although revised to implement the DSEP, are not included with this submittal.10 CFR 50, Appendix E,Section V specifically states that only licensees who are authorized to operate a nuclear power facility shall submit any changes to implementing procedures. We no longer possess licenses authorizing operation of ZNPS because of the certifications (i.e., References 2 and 3) docketed pursuant to

' 10 CFR 50.82.10 CFR 50.82(a)(2) specifically states that a 10 CFR 50 license no longer authorizes operation upon docketing of the certifications. Therefore, 10 CFR 50, Appendix E,Section V is no longer applicable to ZNPS.

We have evaluated the changes to the plan in accordance with 10 CFR 50.54(q).

We concluded the changes do not decrease the effectiveness of the plan and the plan, as changed, continues to meet the standards of 10 CFR 50.47(b) and the requirements of 10 CFR 50, Appendix E that remain in effect following the NRC approval contained in the Reference 1 letter.

d

7 October 18,1999 U.S. Nuclear Regulatory Commission Page 3

' If you have any questions about this letter, please contact Mr. P. R. Simpson at (630) 663-7971.

Respectfully,

~

e 4

R. M. K<ich Vice President - Regulatory Services Attachments cc:

Regional Administrator'- NRC Region Ill (two copies)

NRC Senior Resident inspector-Braidwood Station NRC Senior Resident inspector - Byron Station NRC Senior Resident inspector-Dresden Nuclear Power Station NRC Senior Resident inspector-LaSalle County Station

'NRC Senior Resident inspector-Quad 0: ties Nuclear Power Station ir J

i ZNPS DSEP Revision 0 1

1