{{Adams
| number = ML20207L621
| issue date = 01/08/1987
| title = Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-267/85-28 & 50-267/85-32
| author name = Gagliardo J
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
| addressee name = Williams R
| addressee affiliation = PUBLIC SERVICE CO. OF COLORADO
| docket = 05000267
| license number =
| contact person =
| document report number = NUDOCS 8701120274
| title reference date = 12-04-1986
| document type = CORRESPONDENCE-LETTERS, NRC TO UTILITY, OUTGOING CORRESPONDENCE
| page count = 1
}}
See also: [[see also::IR 05000267/1985028]]
 
=Text=
{{#Wiki_filter:7
?, .y
      . . , .
                                                  JAN    8 1987
                                          .
              In Reply Refer To: _      _
                                                                  *
              Docket:    50-267/85-28 & 85-32
              Public~ Service Company of Colorado
              ATTN:  Robert 0. Williams, Jr.
                      Vice President, Nuclear Operations
              P. O. Box 840
              Denver, Colorado    80201-0840
                                                                                                    l
              Dear Sir:
              Thank you for your letter of December 4,1986, by which you informed us of the
              new completion dite for the Security Equipment Reliability Program.
              If there are additional delays or any change to the March 31, 1987, completion
              date, please advise us as soon as possible.
                                                          ORIGINAL SIGNED BY:
                                                          J. E. Gagliardo, Chief
                                                          Reactor Projects Branch
              cc:
              J. W. Gahm, Manager, Nuclear
                Production Division
              Fort St. Vrain Nuclear Station
              16805 WCR 19
              Platteville, Colorado    80651
              L. Singleton, Manager, Quality
                Assurance Division
              (same address)
              Colorado Radiation Control Program Director
              Colorado Public Utilities Commission
              bec to DM8 (IE04)
              bec distrib. by RIV:
              RP8                                  DRSP
              Resident Inspector                    R. D. Martin, RA
              Section Chief (RPB/A)                RSB
              Section Chief (RSB/ES)                R&SPB
              MIS System                            RSTS Operator
              RIV File                              Inspector
              Section Chief                        W. L. F,i her
              R. L. Bangart                              '
              RIV:EP SPS    C:EP&  P,S    C:R&SP    :R 8 A C:RPB }
              ABEarne D                            JPJaudon JEGagli      o
              l/5/84        LAYandey
                              l/5'/89        WlLFisher/(, /87;/q i /-)
                                                                    /q /86
                  8701120274 870108                                                          0
                  PDR  ADOCK 05000267                                                          1
                  G                  PDR                                                      )(!
                                                                                                  3
 
          -
  ,  ,s
        h Public Service ~                                                  %TA_
              16805 WCR 19 1/2, Platteville, Colorado 80651
                                                                      December 4, 1986
                                                                      Fort St. Vrain
                                                                      Unit No. 1
                                                                      P-86640
                                                                        f-              ._ _
                                                                                              _i
              Regional Administrator                                      . ,4
              Region IV                                                ,L
              U. S. Nuclear Regulatory Commission
              611 Ryan Plaza Drive, Suite 1000                          j)i ') DEC l l1986 - .
    .        Arlington, Texas 76011                                    LLJ
              Attention: Mr. J. E. Gagliardo, Chief
                          Reactor Projects Branch
                                            Docket No. 50-267
                                            SUBJECT:    Security Equipment
                                                        Reliability
                                            REFERENCE: PSC Letter, Williams to
                                                        Director Office of Inspection
                                                        and Enforcement Dated
                                                        August 5,1986(P-86471).
              Dear Mr. Gagliardo:
              In response to a Notice of Violation resulting from I&E Inspections
              85-28 and 85-32 (Reference 1), PSC advised the NRC that we would
              develop a program to determine root causes and trend security system
              equipment inoperability. PSC originally projected this project to be
                                                          '
              complete by October 1, 1986.
              PSC has started collecting the data necessary to determine the causes
              and to establish a trend analysis program.      However, in order to
              implement    a  truly effective program, PSC believes additional
              enhancements are needed. Therefore, PSC proposes a revision to the
              target    date  for complete implementation of this program to
              March 31, 1987. This will provide PSC sufficient time to develop and
              implement an effective security system equipment monitoring program.
              Should you have any questions, please contact Mr. M. H. Holmes
              (303) 480-6960 for further information.
                                                                                                  *
9kMis
 
_
,
  .  p .  .o
  -    ..
              P-86640    -2-                    December 4, 1986
                            Sincerely,
                            J.W. Gahm
                            Manager, Nuclear Production
                            Fort St. Vrain Nuclear
                              Generating Station
              JWG:DCG/mit
    .
                      %
}}

Latest revision as of 15:39, 19 December 2021

Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-267/85-28 & 50-267/85-32
ML20207L621
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 01/08/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Robert Williams
PUBLIC SERVICE CO. OF COLORADO
References
NUDOCS 8701120274
Download: ML20207L621 (1)


See also: IR 05000267/1985028

Text

7

?, .y

. . , .

JAN 8 1987

.

In Reply Refer To: _ _

Docket: 50-267/85-28 & 85-32

Public~ Service Company of Colorado

ATTN: Robert 0. Williams, Jr.

Vice President, Nuclear Operations

P. O. Box 840

Denver, Colorado 80201-0840

l

Dear Sir:

Thank you for your letter of December 4,1986, by which you informed us of the

new completion dite for the Security Equipment Reliability Program.

If there are additional delays or any change to the March 31, 1987, completion

date, please advise us as soon as possible.

ORIGINAL SIGNED BY:

J. E. Gagliardo, Chief

Reactor Projects Branch

cc:

J. W. Gahm, Manager, Nuclear

Production Division

Fort St. Vrain Nuclear Station

16805 WCR 19

Platteville, Colorado 80651

L. Singleton, Manager, Quality

Assurance Division

(same address)

Colorado Radiation Control Program Director

Colorado Public Utilities Commission

bec to DM8 (IE04)

bec distrib. by RIV:

RP8 DRSP

Resident Inspector R. D. Martin, RA

Section Chief (RPB/A) RSB

Section Chief (RSB/ES) R&SPB

MIS System RSTS Operator

RIV File Inspector

Section Chief W. L. F,i her

R. L. Bangart '

RIV:EP SPS C:EP& P,S C:R&SP :R 8 A C:RPB }

ABEarne D JPJaudon JEGagli o

l/5/84 LAYandey

l/5'/89 WlLFisher/(, /87;/q i /-)

/q /86

8701120274 870108 0

PDR ADOCK 05000267 1

G PDR )(!

3

-

, ,s

h Public Service ~ %TA_

16805 WCR 19 1/2, Platteville, Colorado 80651

December 4, 1986

Fort St. Vrain

Unit No. 1

P-86640

f- ._ _

_i

Regional Administrator . ,4

Region IV ,L

U. S. Nuclear Regulatory Commission

611 Ryan Plaza Drive, Suite 1000 j)i ') DEC l l1986 - .

. Arlington, Texas 76011 LLJ

Attention: Mr. J. E. Gagliardo, Chief

Reactor Projects Branch

Docket No. 50-267

SUBJECT: Security Equipment

Reliability

REFERENCE: PSC Letter, Williams to

Director Office of Inspection

and Enforcement Dated

August 5,1986(P-86471).

Dear Mr. Gagliardo:

In response to a Notice of Violation resulting from I&E Inspections

85-28 and 85-32 (Reference 1), PSC advised the NRC that we would

develop a program to determine root causes and trend security system

equipment inoperability. PSC originally projected this project to be

'

complete by October 1, 1986.

PSC has started collecting the data necessary to determine the causes

and to establish a trend analysis program. However, in order to

implement a truly effective program, PSC believes additional

enhancements are needed. Therefore, PSC proposes a revision to the

target date for complete implementation of this program to

March 31, 1987. This will provide PSC sufficient time to develop and

implement an effective security system equipment monitoring program.

Should you have any questions, please contact Mr. M. H. Holmes

(303) 480-6960 for further information.

9kMis

_

,

. p . .o

- ..

P-86640 -2- December 4, 1986

Sincerely,

J.W. Gahm

Manager, Nuclear Production

Fort St. Vrain Nuclear

Generating Station

JWG:DCG/mit

.

%