{{Adams
| number = ML20195D210
| issue date = 06/17/1988
| title = Forwards Insp Repts 50-456/88-15 & 50-457/88-16 on 880420-21 & Notice of Violation & Proposed Imposition of Civil Penalty.W/O Encl
| author name = Davis A
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
| addressee name = Reed C
| addressee affiliation = COMMONWEALTH EDISON CO.
| docket = 05000456, 05000457
| license number =
| contact person =
| document report number = NUDOCS 8806230072
| document type = CORRESPONDENCE-LETTERS, NRC TO UTILITY, OUTGOING CORRESPONDENCE
| page count = 4
}}
See also: [[see also::IR 05000456/1988015]]
 
=Text=
{{#Wiki_filter:'-  o'                                                                                    bC0
,
                                                        h    a  u
                                                      JUN 171998
          Docket Nos. 50-456; 50-457
          License Nos. NPF-72; NPF-75
          EA 88-125
          Commonwealth Edison Company
          ATTN:  Mr. Cordell Reed
                  Senior Vice President
          Post Office Box 767
          Chicago, IL 60690
          Gentlemen:
          SUBJECT:  NOTICE OF VIOLATION AND PROPOSED IMPOSITION OF CIVIL PENALTY
                      (NRC INSPECTION REPORT NOS. 50-456/88015(DRSS); 50-457/88016(DRSS))
          This refers to the inspection conducted on April 20-21, 1988, of activities at
          Braidwood Nuclear Power Station, Units 1 and 2, authorized by NRC Operating
          Licenses No. NPF-72 and No. NPF-75.        On April 19, 1988, your staff identified
          an unprotected vital area barrier opening, as described in the subject
          Inspection Reports sent to you by letter dated May 2, 1988. An enforcement
          conference was held on May 19, 1988 between Mr. T. J. Maiman and members of
          your staff and Mr. B. S. Mallett and members of my staff during which the
          violation, its root cause and your corrective actions were discussed. The
          enforcement conference attendees are listed in Enclosure 2 to this letter.
          In violation of your Security Plan, an opening has existed in a vital area
          barrier since initial licensing of the plant.          Upon discovery by your staff,            ;
          it was posted with a guard as a compensatory measure and reported to the NRC
          in accordance with 10 CFR 73.71. On April 23, 1988, the opening was modified                    i
          to reduce the penetration size.        This opening had not been adequately evaluated            '
          during previous vital area barrier walkdowns.                                                    l
          To emphasize the need to ensure the integrity of all vital area boundaries, I
          have been authorized, after consultation with the Director, Office of
          Enforcement, and the Deputy Executive Director for Regional Operations, to
          issue the enclosed Notice of Violation and Proposed Imposition of Civil Penalty
          in the amount of Fifty Thousand Dollars ($50,000) for the violation describ d
          in the enclosed Notice. In accordance with the "General Statement of Policy
          and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1988'
          (Enforcement Policy), the violat' ion described in the enclosed Notice has beon
          categorized at a Severity Level III.          The escalation and mitigation factors in
          the Enforcement Policy were considered as were the unique characteristics of
          this security area, and no adjustment has been decmed appropriate.                    fp  lk
                                                                                                    I
                                                                                                        \
          CERTIFIED MAIL
                                                                          Enclosure containS
          RETURN RECEIPT REQUESTED
                                                                          SAFEGUARDS INFORMATI
                                                                          Upon scparation this
                                                                          paga is Decontrollo
    8806230072 880617
    PDR    ADOCK 05000456          1- O!I A      ) Y IY
                                                              CO)V hI]
                                        -  -
    Q                    DCD        *  '-""''''" -
                                  ,
 
  ,                                                                                                      l
'
'
                                              h                      Q
    Comonwealth Edison Company                  2                          jut 1 17 1988
                                                                                                          l
    You are required to respond to this letter and should follow the instructions
    specified in the enclosed Notice when preparing your response. In your
    response, you should document the specific actions taken and any additional
    actions you plan to prevent recurrence. After reviewing your response to this
    Notice, including your proposed corrective actions and the results of future
    inspections, the NRC will determine whether further NRC enforcement action is
    necessary to ensure compliance with NRC regulatory requirements.
    Areas discussed in this Notice concern subject matter which is exempt from
    disclosure according to 10 CFR 73.21(c)(2). Consequently, the enclosures to
    this letter will not be placed in the NRC Public Document Room. Your response
    to the violation identified in the enclosed Notice should be submitted in
    accordance with 10 CFR 73.27
    The responses directed by this letter and the enclosed Notice are not subject
    to the clearance procedures of the Office of Maragement and Budget, as
    required by the Paperwork Reduction Act of 1980, Pub. L. , No. 96-511.
                                                Sincerely,
                                                    Original signed by
                                                  Z. Bert Davia
                                                A. Bert Davis
                                                Regional Administrator
    Enclosures:
    1.  Notice of Violation
            and Proposed In' position
            of Civil Penalty
    2.  Enforcement Conference                                                                          i
            Attendees
    3.  Inspection Reports
            No. 50-456/88015(DRSS);
            No. 50-457/88016(DRSS)                                                                        l
    (UNCLASSIFIED SAFEGUARDS INFORMATION)                                                                '
                                                                                                          l
    See Attached Distribution
                                                                                '
    p      on/jlr                                C"      n
                                                                      @U          Glioli 3
                                                  RIIb lhi*
                                                                                                          ,
    OEca ru                py                                        ED0 pm ru
                                /
            man            P  3e/ello            D vis              T#
                                  f'2                                            Enclosure Contains
      bfidhl                (M                  L4
                                                                                  SAFEGUARDS lilFORMATION
                              GAI!PIIADDO 15 ' '~ ^      ' " 8 6 Tl              Upon Separation This    j
                              -      -musuu las        V.tnu1sr                  Page is Decontrolled
 
  ,
        '
    ' '
.,                                  qypWtmii 0N
          Commonwealth Edison Company            3
                                                          JUN i 7 gg
          Distribution
          cc w/ enclosures:
          T. J. Maiman, Vice President,
              PWR Operations
          H. Bliss, Nuclear
              Licensing Manager
          M. Wallace, Manager of Projects
          M. Lohmann, Project Construction
              and Startup Superintendent
          W. Vahle, Construction
              Superintendent
          R. E. Querio, Station Manager
          P. L. Darnes, Regulatory
              Assurance Supervisor
          J. Lieberman, OE
          NRR/DRIS/SGB
          NRR/DRIS/S1B
          NRR/DLPQ/PEB
          Enforcement Coordinators
              RI, RII, RIV, RV
          cc w/ enclosures,
              w/o UNCLASSIFIED SAFEGUARDS
              INFORMATION:
          DCD/DCB (RIDS)
          Licensing Fee Management Branch
          Resident Inspector, RIII
              Braidwood
          Resident Inspector, RIII
          Byron
          D. W. Cassel, Jr., Esq.
          Richard Hubbard
          J. W. McCaffrey, Chief, Public
              Utilities Division
          H. S. Taylor, Quality Assurance
              Division
          E. Chan, OGC
          G. Berry, 0GC
          Stephen P. Sands, NRR
          The Honorable A. Dixon Callihan, ASLB
          The Honorable Richard F. Cole, ASLB
          The Honorable Ivan W. Smith, ASLB
          The Honorable Gary J. Edles, ASLAP
          Tha Honorable Dr. W. Reed Johnson, ASLAP
          The Honor Ole Christine N. Kohl, ASLAP
          SECY
          CA
          OGPA
          J. M. Taylor, DEDR0
          L. Chandler, OGC
          RAO:RIII                                EncTosure contains
          PAO:RIII                                SAFEGUARDS INFORMATION
          SLO:RIII                                Upon separation this
          M. Stabulak, RIII                        page is Decontrolled
 
      .
%
          *
  . .  ,
                                                                                    l
                                                ENCLOSURE 2
                                                                                    l
                                                                                    l
                                    ENFORCEMENT CONFERENCE ATTENDEES              I
                                                                                    l
            Commonwealth Edison Company
            T. J. Maiman, Vice President, PWR Operations                            l
            K. L. Graesser, General Manager, PWR Operations                        1
            R. E. Querio, Station Manager                                          !
            B. M. Saunders, Nuclear Security Administrator
            F. D. Willaford, Station Security Administrator
            H. E. Bliss, Nuclear Licensing Manager
                                                                                    l
            P. Laird, Director, Corporate Security                                  -
            F. G. Lentine, PWR Licensing Supervisor
            P. L. Barnes, Regulatory Assurance Supervisor
            D. E. O'Brein, Services Superintendent                                  ;
            S. Trubatch, Attorney                                                  l
            U.S. Nuclear Regulatory Commission
            B. S. Hallett, Chief, Materials and Safeguards Branch
            L. J. Norrhom, Project Director, Office of Nuclear Reactor Regulation
            J. R. Creed, Chief, Safeguards Section
            J. R. Knicely, Security Inspector
            C. D. Anderson, Enforcement Specialist
            R. M. Lerch, Reactor Engineer
                                                                                  .
                                                                                    l
                                                                                    l
}}

Latest revision as of 19:55, 16 December 2020

Forwards Insp Repts 50-456/88-15 & 50-457/88-16 on 880420-21 & Notice of Violation & Proposed Imposition of Civil Penalty.W/O Encl
ML20195D210
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 06/17/1988
From: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
References
NUDOCS 8806230072
Download: ML20195D210 (4)


See also: IR 05000456/1988015

Text

'- o' bC0

,

h a u

JUN 171998

Docket Nos. 50-456; 50-457

License Nos. NPF-72; NPF-75

EA 88-125

Commonwealth Edison Company

ATTN: Mr. Cordell Reed

Senior Vice President

Post Office Box 767

Chicago, IL 60690

Gentlemen:

SUBJECT: NOTICE OF VIOLATION AND PROPOSED IMPOSITION OF CIVIL PENALTY

(NRC INSPECTION REPORT NOS. 50-456/88015(DRSS); 50-457/88016(DRSS))

This refers to the inspection conducted on April 20-21, 1988, of activities at

Braidwood Nuclear Power Station, Units 1 and 2, authorized by NRC Operating

Licenses No. NPF-72 and No. NPF-75. On April 19, 1988, your staff identified

an unprotected vital area barrier opening, as described in the subject

Inspection Reports sent to you by letter dated May 2, 1988. An enforcement

conference was held on May 19, 1988 between Mr. T. J. Maiman and members of

your staff and Mr. B. S. Mallett and members of my staff during which the

violation, its root cause and your corrective actions were discussed. The

enforcement conference attendees are listed in Enclosure 2 to this letter.

In violation of your Security Plan, an opening has existed in a vital area

barrier since initial licensing of the plant. Upon discovery by your staff,  ;

it was posted with a guard as a compensatory measure and reported to the NRC

in accordance with 10 CFR 73.71. On April 23, 1988, the opening was modified i

to reduce the penetration size. This opening had not been adequately evaluated '

during previous vital area barrier walkdowns. l

To emphasize the need to ensure the integrity of all vital area boundaries, I

have been authorized, after consultation with the Director, Office of

Enforcement, and the Deputy Executive Director for Regional Operations, to

issue the enclosed Notice of Violation and Proposed Imposition of Civil Penalty

in the amount of Fifty Thousand Dollars ($50,000) for the violation describ d

in the enclosed Notice. In accordance with the "General Statement of Policy

and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1988'

(Enforcement Policy), the violat' ion described in the enclosed Notice has beon

categorized at a Severity Level III. The escalation and mitigation factors in

the Enforcement Policy were considered as were the unique characteristics of

this security area, and no adjustment has been decmed appropriate. fp lk

I

\

CERTIFIED MAIL

Enclosure containS

RETURN RECEIPT REQUESTED

SAFEGUARDS INFORMATI

Upon scparation this

paga is Decontrollo

8806230072 880617

PDR ADOCK 05000456 1- O!I A ) Y IY

CO)V hI]

- -

Q DCD * '-""'" -

,

, l

'

'

h Q

Comonwealth Edison Company 2 jut 1 17 1988

l

You are required to respond to this letter and should follow the instructions

specified in the enclosed Notice when preparing your response. In your

response, you should document the specific actions taken and any additional

actions you plan to prevent recurrence. After reviewing your response to this

Notice, including your proposed corrective actions and the results of future

inspections, the NRC will determine whether further NRC enforcement action is

necessary to ensure compliance with NRC regulatory requirements.

Areas discussed in this Notice concern subject matter which is exempt from

disclosure according to 10 CFR 73.21(c)(2). Consequently, the enclosures to

this letter will not be placed in the NRC Public Document Room. Your response

to the violation identified in the enclosed Notice should be submitted in

accordance with 10 CFR 73.27

The responses directed by this letter and the enclosed Notice are not subject

to the clearance procedures of the Office of Maragement and Budget, as

required by the Paperwork Reduction Act of 1980, Pub. L. , No.96-511.

Sincerely,

Original signed by

Z. Bert Davia

A. Bert Davis

Regional Administrator

Enclosures:

1. Notice of Violation

and Proposed In' position

of Civil Penalty

2. Enforcement Conference i

Attendees

3. Inspection Reports

No. 50-456/88015(DRSS);

No. 50-457/88016(DRSS) l

(UNCLASSIFIED SAFEGUARDS INFORMATION) '

l

See Attached Distribution

'

p on/jlr C" n

@U Glioli 3

RIIb lhi*

,

OEca ru py ED0 pm ru

/

man P 3e/ello D vis T#

f'2 Enclosure Contains

bfidhl (M L4

SAFEGUARDS lilFORMATION

GAI!PIIADDO 15 ' '~ ^ ' " 8 6 Tl Upon Separation This j

- -musuu las V.tnu1sr Page is Decontrolled

,

'

' '

., qypWtmii 0N

Commonwealth Edison Company 3

JUN i 7 gg

Distribution

cc w/ enclosures:

T. J. Maiman, Vice President,

PWR Operations

H. Bliss, Nuclear

Licensing Manager

M. Wallace, Manager of Projects

M. Lohmann, Project Construction

and Startup Superintendent

W. Vahle, Construction

Superintendent

R. E. Querio, Station Manager

P. L. Darnes, Regulatory

Assurance Supervisor

J. Lieberman, OE

NRR/DRIS/SGB

NRR/DRIS/S1B

NRR/DLPQ/PEB

Enforcement Coordinators

RI, RII, RIV, RV

cc w/ enclosures,

w/o UNCLASSIFIED SAFEGUARDS

INFORMATION:

DCD/DCB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Braidwood

Resident Inspector, RIII

Byron

D. W. Cassel, Jr., Esq.

Richard Hubbard

J. W. McCaffrey, Chief, Public

Utilities Division

H. S. Taylor, Quality Assurance

Division

E. Chan, OGC

G. Berry, 0GC

Stephen P. Sands, NRR

The Honorable A. Dixon Callihan, ASLB

The Honorable Richard F. Cole, ASLB

The Honorable Ivan W. Smith, ASLB

The Honorable Gary J. Edles, ASLAP

Tha Honorable Dr. W. Reed Johnson, ASLAP

The Honor Ole Christine N. Kohl, ASLAP

SECY

CA

OGPA

J. M. Taylor, DEDR0

L. Chandler, OGC

RAO:RIII EncTosure contains

PAO:RIII SAFEGUARDS INFORMATION

SLO:RIII Upon separation this

M. Stabulak, RIII page is Decontrolled

.

%

. . ,

l

ENCLOSURE 2

l

l

ENFORCEMENT CONFERENCE ATTENDEES I

l

Commonwealth Edison Company

T. J. Maiman, Vice President, PWR Operations l

K. L. Graesser, General Manager, PWR Operations 1

R. E. Querio, Station Manager  !

B. M. Saunders, Nuclear Security Administrator

F. D. Willaford, Station Security Administrator

H. E. Bliss, Nuclear Licensing Manager

l

P. Laird, Director, Corporate Security -

F. G. Lentine, PWR Licensing Supervisor

P. L. Barnes, Regulatory Assurance Supervisor

D. E. O'Brein, Services Superintendent  ;

S. Trubatch, Attorney l

U.S. Nuclear Regulatory Commission

B. S. Hallett, Chief, Materials and Safeguards Branch

L. J. Norrhom, Project Director, Office of Nuclear Reactor Regulation

J. R. Creed, Chief, Safeguards Section

J. R. Knicely, Security Inspector

C. D. Anderson, Enforcement Specialist

R. M. Lerch, Reactor Engineer

.

l