7
o
.
.
,
.
September 17,1999
l
Mr. Oliver D. Kingsley
President, Nuclear Generation Group
Commonwealth Edison Company
ATTN: Regulatory Services
Executive Towers West lll
1400 Opus Place, Suite 500
Downers Grove, IL 60515
SUBJECT:
NRC INSPECTION REPORT 50-456/99013(DRS); 50-457/99013(DRS)
Dear Mr. Kingsley:
,
On August 24,1999, the NRC completed an AE engineering follow-up inspection at your
Braidwood Units 1 and 2 reactor facilities. The enclosed report presents the results of that
inspection.
The inspection focused on your corrective actions and activities to address the technical
- 3
concerns identified by the AE inspection team during the design inspection completed on
April 24,1998. The team identified weaknesses in timeliness of corrective actions, test
program and procedures, and evaluation of generic communications.
Overall, our inspection results indicated that your corrective actions were effective in addressing
the concerns identified by the team and steps were taken to prevent recurrence of the noted
problems.
Based on the results of this inspection, the NRC has determined that three violations of
NRC requirements occurred. These violations are being treated as Non-Cited Violations
(NCV's) consistent with Appendix C of the Enforcement Policy. These NCVs are described
in the subject inspection report. If you contest either the severity level or the violation itself,
you should provide a response within 30 days of the date of this inspection report, with the
basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control
Desk, Washington DC 20555-0001, with copies to the Regional Administrator, Region Ill,
and the Director, Office of Enforcement, United States Nuclear Regulatory Commission,
Washington, DC 20555-0001.
'
9909240048 990917
ADOCK 05000456
G
'
'
O. Kingsley
-2-
In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter, its
enclosure, and your response, if you choose to provide one, will be placed in the NRC Public
Document Room.
Sincerely,
Original'/s/ Ronald N. Gardner
Ronald N. Gardner, Chief
Electrical Engineering Branch
Docket Nos. 50-456; 50-457
Enclosure:
Inspection Report 50-456/99013(DRS); 50-457/99013(DRS)
cc w/ encl:
D. Helwig, Senior Vice President, Nuclear Services
C. Crane, Senior Vice President, Nuclear Operations
H. Stanley, Vice President, Nuclear Operations
R. Krich, Vice President, Regulatory Services
DCD - Licensing
T. Tulon, Site Vice President
K. Schwartz, Station Manager
T. Simpkin, Regulatory Assurance Supervisor
M. Aguilar, Assistant Attomey General
State Liaison Officer
Chairman, Illinois Commerce Commission
/
'
Distribution:
COT (E-Mail)
RPC (E-Mail)
GFD (Project Mgr.) (E-Mail)
J. Caldwell, Rlli w/enci
B. Clayton, Rlli w/enct
SRI Braidwood w/enci
DRP w/ enc!
DRS w/er.cl
Rlli PRR w!encI
PUBLIC IE-01 w/enci
Docket File w/enci
,
GREENS
.-i54
IEO (E-Mail)
_
',' O '
{
DOCDESK (E-Mail)
DOCUMENT NAME: G:\\DRS\\ BRA 99013.WPD
To receive a copy of this doeurnent, Indicate in the box: "C's Cooy wthout attactmeVenclosure T e Copy wth attachment / enclosure
- N" a No copy _
OFFICE
Rlli-
E Rlli
)
6
Rlli
ltJ
NAME-
ZFalevits:sd N6z MJordarff%
RGardner b/
DATE
08//4/99
- 0$//6 /99 1
08h1/99
OFFICIAL RECORD COPY