ML102590086: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML102590086
| number = ML102590086
| issue date = 10/15/2010
| issue date = 10/15/2010
| title = 5/25/10 Summary of Telephone Conference Call Held Between Usnrc and Entergy Nuclear Operations, Inc. Concerning the Annual Update Associated with the Pilgrim Nuclear Power Station License Renewal Application
| title = 5/25/10 Summary of Telephone Conference Call Held Between USNRC and Entergy Nuclear Operations, Inc. Concerning the Annual Update Associated with the Pilgrim Nuclear Power Station License Renewal Application
| author name = Regner L M
| author name = Regner L
| author affiliation = NRC/NRR/DLR/RPB2
| author affiliation = NRC/NRR/DLR/RPB2
| addressee name =  
| addressee name =  
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555"()001 October 15, 2010 LICENSEE:        Entergy Nuclear Operations, Inc.
FACILITY:        Pilgrim Nuclear Power Station
 
==SUBJECT:==
 
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON MAY 25,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE ANNUAL UPDATE ASSOCIATED WITH THE PILGRIM NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Entergy Nuclear Operations, Inc. (the applicant) held a telephone conference call on May 25, 2010, to discuss and clarify the staff's draft request for additional information (RAI) concerning the Pilgrim Nuclear Power Station, license renewal application. The draft RAI was associated with a letter submitted by the applicant dated December 28, 2009, in accordance with Title 10 of the Code of Federal Regulations, Part 54.21 (b). The telephone conference call was useful in clarifying the intent of the staff's draft RAJ. provides a listing of the participants and Enclosure 2 includes the draft RAI discussed with the applicant, including a brief description on the status of the item.
The applicant had an opportunity to comment on thi summary.
Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-293
 
==Enclosures:==
 
As stated cc w/encls: Distribution via Listserv
 
TELEPHONE CONFERENCE CALL PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS MAY 25,2010 PARTICIPANTS        AFFILIATIONS Lisa Regner        U.S. Nuclear Regulatory Commission (NRC)
Steve Jones        NRC Fred Mogolesko      Entergy Nuclear Operations, Inc. (Entergy)
Steve Bethay        Entergy Joe Lynch          Entergy Dave Heard          Entergy Paul Smith          Entergy Rich Pardee        Entergy Dave Lach          Entergy Dave King          Entergy ENCLOSURE 1
 
DRAFT REQUESTS FOR ADDITIONAL INFORMATION PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION MAY 25,2010 The U.S. Nuclear Regulatory Commission (the staff) and representatives of Entergy Nuclear Operation, Inc. (the applicant) held a telephone conference call on May 25, 2010, to discuss and clarify the following draft request for additional information (RAI) concerning the Pilgrim Nuclear Power Station (PNPS) license renewal application (LRA).
 
==Background:==
 
Item 5 of the PNPS Annual Update, submitted by letter dated December 28, 2009, deletes the "fogger housing" component type from the LRA Table 2.3.3-4, "Emergency Diesel Generator System Components Subject to Aging Management Review;" and LRA Table 3.3.2-4, "Emergency Diesel Generator System Summary of Aging Management Evaluation." LRA Table 2.3.3-4 identified the intended function of the "fogger housing" as a pressure boundary.
LRA Table 3.3.2-4 identified the fogger housing material as "copper alloy>15% Zn" with an internal environment of untreated air and external environment of indoor air. This material/environment combination is different than the material/environment combination for other emergency diesel generator (EDG) components.
Section 2.3.3.4 of the LRA includes the following discussion:
The EDG system has the following intended function for 10 CFR 54.4(a)(1):
* Provide power to essential AC busses during a loss of offsite power.
The air start and turbo air assist systems support the startup and operation of the emergency diesel generators. Each EDG engine is started by high pressure air, which powers the air motors to crank the engine and start combustion.
Issue:
LRA Drawing M219 showed a component identified as a "Motor Oil Fogger" in the piping supporting delivery of pressurized air from the EDG air receivers to 1 of the 2 sets of air motors relied on to start the "A" EDG and to both sets of air motors relied on to start the "B" EDG.
Thus, the staff concluded that "fogger housing" described a unique component type whose integrity would be necessary for accomplishment of the EDG intended function for 10 CFR 54.4(a)(1).
Request:
Expain: 1) how the "fogger housing" is no longer required to support the EDG intended function, and 2) how the pressure boundary function is being achieved.
Discussion:
The applicant explained that question is clear. The applicant will submit a supplement to the December 28,2009, Annual Update addressing the staff's question.
ENCLOSURE 2
 
October 15,2010 LICENSEE:      Entergy Nuclear Operations, Inc.
FACILITY:      Pilgrim Nuclear Power Station
 
==SUBJECT:==
 
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON MAY 25, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE ANNUAL UPDATE ASSOCIATED WITH THE PILGRIM NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Entergy Nuclear Operations, Inc. (the applicant) held a telephone conference call on May 25, 2010, to discuss and clarify the staff's draft request for additional information (RAI) concerning the Pilgrim Nuclear Power Station, license renewal application. The draft RAI was associated with a letter submitted by the applicant dated December 28,2009, in accordance with Title 10 of the Code of Federal Regulations, Part 54.21 (b). The telephone conference call was useful in clarifying the intent of the staff's draft RAI. provides a listing of the participants and Enclosure 2 includes the draft RAI discussed with the applicant, including a brief description on the status of the item.
The applicant had an opportunity to comment on this summary.
IRA!
Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-293
 
==Enclosures:==
 
As stated cc w/encls: Distribution via Listserv DISTRIBUTION:
See next page ADAMS Accession No ML102590086 OFFICE      PM:RPB2:DLR            LA:RPOB:DLR            BC:RPB2:DLR          PM:RPB2:DLR NAME        LRegner                YEdmonds                DWrona              LRegner I DATE      110104/10                9/22/10                10/15/10            10/15/10 OFFICIAL RECORD COpy
 
Memorandum to Entergy Nuclear Operations, Inc. from L. Regner dated October 15, 2010
 
==SUBJECT:==
 
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON MAY 25,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE ANNUAL UPDATE ASSOCIATED WITH THE PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARDCOPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxbes Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource JRobinson JDozier RAuluck LRegner JKim SUttal,OGC DJackson, RI MSchneider, RI NSheehan, RI}}

Latest revision as of 14:11, 13 November 2019

5/25/10 Summary of Telephone Conference Call Held Between USNRC and Entergy Nuclear Operations, Inc. Concerning the Annual Update Associated with the Pilgrim Nuclear Power Station License Renewal Application
ML102590086
Person / Time
Site: Pilgrim
Issue date: 10/15/2010
From: Lisa Regner
License Renewal Projects Branch 2
To:
Regner L M, NRR/DLR, 415-1906
References
Download: ML102590086 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555"()001 October 15, 2010 LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Pilgrim Nuclear Power Station

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MAY 25,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE ANNUAL UPDATE ASSOCIATED WITH THE PILGRIM NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Entergy Nuclear Operations, Inc. (the applicant) held a telephone conference call on May 25, 2010, to discuss and clarify the staff's draft request for additional information (RAI) concerning the Pilgrim Nuclear Power Station, license renewal application. The draft RAI was associated with a letter submitted by the applicant dated December 28, 2009, in accordance with Title 10 of the Code of Federal Regulations, Part 54.21 (b). The telephone conference call was useful in clarifying the intent of the staff's draft RAJ. provides a listing of the participants and Enclosure 2 includes the draft RAI discussed with the applicant, including a brief description on the status of the item.

The applicant had an opportunity to comment on thi summary.

Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-293

Enclosures:

As stated cc w/encls: Distribution via Listserv

TELEPHONE CONFERENCE CALL PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS MAY 25,2010 PARTICIPANTS AFFILIATIONS Lisa Regner U.S. Nuclear Regulatory Commission (NRC)

Steve Jones NRC Fred Mogolesko Entergy Nuclear Operations, Inc. (Entergy)

Steve Bethay Entergy Joe Lynch Entergy Dave Heard Entergy Paul Smith Entergy Rich Pardee Entergy Dave Lach Entergy Dave King Entergy ENCLOSURE 1

DRAFT REQUESTS FOR ADDITIONAL INFORMATION PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION MAY 25,2010 The U.S. Nuclear Regulatory Commission (the staff) and representatives of Entergy Nuclear Operation, Inc. (the applicant) held a telephone conference call on May 25, 2010, to discuss and clarify the following draft request for additional information (RAI) concerning the Pilgrim Nuclear Power Station (PNPS) license renewal application (LRA).

Background:

Item 5 of the PNPS Annual Update, submitted by letter dated December 28, 2009, deletes the "fogger housing" component type from the LRA Table 2.3.3-4, "Emergency Diesel Generator System Components Subject to Aging Management Review;" and LRA Table 3.3.2-4, "Emergency Diesel Generator System Summary of Aging Management Evaluation." LRA Table 2.3.3-4 identified the intended function of the "fogger housing" as a pressure boundary.

LRA Table 3.3.2-4 identified the fogger housing material as "copper alloy>15% Zn" with an internal environment of untreated air and external environment of indoor air. This material/environment combination is different than the material/environment combination for other emergency diesel generator (EDG) components.

Section 2.3.3.4 of the LRA includes the following discussion:

The EDG system has the following intended function for 10 CFR 54.4(a)(1):

  • Provide power to essential AC busses during a loss of offsite power.

The air start and turbo air assist systems support the startup and operation of the emergency diesel generators. Each EDG engine is started by high pressure air, which powers the air motors to crank the engine and start combustion.

Issue:

LRA Drawing M219 showed a component identified as a "Motor Oil Fogger" in the piping supporting delivery of pressurized air from the EDG air receivers to 1 of the 2 sets of air motors relied on to start the "A" EDG and to both sets of air motors relied on to start the "B" EDG.

Thus, the staff concluded that "fogger housing" described a unique component type whose integrity would be necessary for accomplishment of the EDG intended function for 10 CFR 54.4(a)(1).

Request:

Expain: 1) how the "fogger housing" is no longer required to support the EDG intended function, and 2) how the pressure boundary function is being achieved.

Discussion:

The applicant explained that question is clear. The applicant will submit a supplement to the December 28,2009, Annual Update addressing the staff's question.

ENCLOSURE 2

October 15,2010 LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: Pilgrim Nuclear Power Station

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MAY 25, 2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE ANNUAL UPDATE ASSOCIATED WITH THE PILGRIM NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (the staff) and representatives of Entergy Nuclear Operations, Inc. (the applicant) held a telephone conference call on May 25, 2010, to discuss and clarify the staff's draft request for additional information (RAI) concerning the Pilgrim Nuclear Power Station, license renewal application. The draft RAI was associated with a letter submitted by the applicant dated December 28,2009, in accordance with Title 10 of the Code of Federal Regulations, Part 54.21 (b). The telephone conference call was useful in clarifying the intent of the staff's draft RAI. provides a listing of the participants and Enclosure 2 includes the draft RAI discussed with the applicant, including a brief description on the status of the item.

The applicant had an opportunity to comment on this summary.

IRA!

Lisa M. Regner, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-293

Enclosures:

As stated cc w/encls: Distribution via Listserv DISTRIBUTION:

See next page ADAMS Accession No ML102590086 OFFICE PM:RPB2:DLR LA:RPOB:DLR BC:RPB2:DLR PM:RPB2:DLR NAME LRegner YEdmonds DWrona LRegner I DATE 110104/10 9/22/10 10/15/10 10/15/10 OFFICIAL RECORD COpy

Memorandum to Entergy Nuclear Operations, Inc. from L. Regner dated October 15, 2010

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MAY 25,2010, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING THE ANNUAL UPDATE ASSOCIATED WITH THE PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARDCOPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxbes Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource JRobinson JDozier RAuluck LRegner JKim SUttal,OGC DJackson, RI MSchneider, RI NSheehan, RI