UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 April 2, 2015 MEETING

SUMMARY

LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.

FACILITY: PILGRIM NUCLEAR POWER STATION

SUBJECT:

SUMMARY

OF PUBLIC MEETING On March 18, 2015, at 6:30 pm, the U. S. Nuclear Regulatory Commission (NRC) conducted a formal meeting at the Radisson Hotel Plymouth Harbor in Plymouth, MA. The NRC conducted a formal meeting and a question and answer portion to discuss its assessment of the safety performance at Pilgrim Nuclear Power Station for 2014 and held a regulatory performance meeting to discuss the results of the Inspection Procedure 95002 supplemental inspection which was documented in a report issued on January 26, 2015.

A notice of the public meeting was issued on March 4, 2015, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML15062A087.

ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The NRC presented fact sheets, reading material, and was available to discuss its assessment of the safety performance of Pilgrim Nuclear Power Station for the period of January 1 through December 31, 2014, as documented in our letter dated March 4, 2015 (ADAMS Accession No. ML15057A041). The NRC fact sheets and reading material included background on the Reactor Oversight Process. Additional information relative to the NRC's Annual Assessment Process and the safety performance of Pilgrim Nuclear Power Station can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, local officials, State officials, and members of the media attended the public meeting and were offered the opportunity to question the NRC regarding Pilgrim Nuclear Power Stations performance and the role of the agency in ensuring safe plant operations.

/RA/

Raymond R. McKinley, Chief Projects Branch 5 Division of Reactor Projects

Enclosures:

1. PowerPoint Presentation (ML15084A053)
2. Attendee List (ML15084A045)

ML15057A041). The NRC fact sheets and reading material included background on the Reactor Oversight Process. Additional information relative to the NRC's Annual Assessment Process and the safety performance of Pilgrim Nuclear Power Station can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, local officials, State officials, and members of the media attended the public meeting and were offered the opportunity to question the NRC regarding Pilgrim Nuclear Power Stations performance and the role of the agency in ensuring safe plant operations.

/RA/

Raymond R. McKinley, Chief Projects Branch 5 Division of Reactor Projects

Enclosures:

1. PowerPoint Presentation (ML15084A053)
2. Attendee List (ML15084A045)

Distribution: (via email)

R. McKinley, DRP E. Miller, DRP, SRI S. Shaffer, DRP B. Scrabeck, DRP, RI J. DeBoer, DRP RidsNRRPMPilgrim Resource E. Carfang, DRP, SRI DOC NAME: G:\DRP\BRANCH5\Annual Assessment Meetings\2014 EOC\Meeting Summaries\Annual Assessment Meeting Summary Pilgrim.docx ADAMS Accession No. ML15092A793 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME JDeBoer/SWS for RMcKinley/RRM DATE 3/25/15 4/2/15