EPID:L-2018-LLO-0003, Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost Estimate (Approved, Closed) |
|
MONTHYEARML18333A2402018-12-17017 December 2018 Application for Order Approving Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC (Owner) and Holtec Decommissioning International, LLC (Operator) Project stage: Other ML18337A1372018-12-17017 December 2018 Request for Withholding Info from Public Disclosure - 11/12/18 Affidavit Executed by A. Rosenlieb, Entergy and 11/14/18 Affidavit Executed by A. Ryan, Holtec International Enclosure 1P, Equity Purchase and Sale Agreement (L-2018-LLO-0003) Project stage: Other ML18333A0092018-12-19019 December 2018 Acceptance Review Letter, Application for Order for Direct and Indirect Transfers of Control of Licenses, Conforming License Amendment, and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) Project stage: Acceptance Review ML18337A4182019-01-0202 January 2019 FRN, Notice of Application for Order for Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC and Holtec Decommissioning International, LLC Project stage: Other ML18337A4302019-01-0202 January 2019 Letter, Notice of Application for Order for Direct and Indirect Transfer of Renewed Facility Operating License and Conforming License Amendment to Holtec Pilgrim, LLC and Holtec Decommissioning International, LLC Project stage: Other ML19017A1622019-01-15015 January 2019, 30 January 2019 Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost Estimate Project stage: Request ML19017A1732019-01-30030 January 2019 Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost Estimate Project stage: Meeting ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc Project stage: RAI ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order Project stage: Draft Other ML19198A2832019-08-13013 August 2019 Notification of Significant Licensing Action - Proposed Issuance of Order Approving a License Transfer Application for Which a Hearing Has Been Requested Project stage: Approval ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application Project stage: Acceptance Review ML19170A1012019-08-22022 August 2019 Letter, Order Approving Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator Project stage: Other ML19170A2652019-08-22022 August 2019 Enclosure 1, Order Approving Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator (L-2018-LLO-0003) Project stage: Other ML19170A2502019-08-22022 August 2019 Enclosure 3, Safety Evaluation for Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator (L-2018-LLO-0003) Project stage: Approval ML19170A1472019-08-22022 August 2019 Order, Safety Evaluation, and Draft Conforming Amendment for Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator (L-2018-LLO-0003) Project stage: Request ML19170A1492019-08-22022 August 2019 Enclosure 2, Draft Conforming Amendment for Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator (L-2018-LLO-0003) Project stage: Draft Other ML19170A2572019-08-22022 August 2019 Federal Register Notice, Order Approving Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator (L-2018-LLO-0003) Project stage: Other ML19234A3612019-08-22022 August 2019 Attachment 1 - License Transfer Cover Letter Project stage: Other ML19235A0502019-08-27027 August 2019 Issuance of Amendment No. 249 Order Approving Direct Transfer of Renewed Facility Operating License and ISFSI General License and Conforming Amendment Project stage: Approval ML19267A0102019-09-30030 September 2019 Correction of Error in Docket Number Associated with Issuance of Amendment No. 249 Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Project stage: Approval 2019-07-26
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML22335A2802022-11-0404 November 2022 11-4-2022 Email Transmitting Draft Questions Pertaining to Pilgrim ISFSI Exemption Request ML22270A0422022-09-26026 September 2022 Acknowledgement Email for Holtec'S Request for Reporting Exemption with Regards to the Pilgrim ISFSI Annual Radioactive Effluent Release Report (Docket No. 05000293) ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22007A2602021-12-0606 December 2021 E-mail from P. O'Brien, Holtec, to A. Snyder, NRC, on Pilgrim Effluent Discharge ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness ML21266A2512021-09-23023 September 2021 Consultation with Commonwealth of Massachusetts Regarding Proposed Amendment Application for Emergency Plan and Emergency Action Levels ML21266A2772021-09-23023 September 2021 HDI Clarification of Exemption Requested from 10 CFR 20, Appendix G, Section Iii.E ML21267A0012021-09-23023 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E Acceptance Review ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl ML21211A5912021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21211A5162021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Physical Security Plan ML21200A2352021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21200A1522021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim Isfi Only Physical Security Plan ML21176A1842021-06-25025 June 2021 Email from HDI Regarding Pilgrim Nuclear Power Station Training ML21180A0582021-06-17017 June 2021 Email from Region I Regarding Pilgrim Nuclear Power Station Inspection - EA-13-132 ML21097A0402021-04-0606 April 2021 E-Mail Consult with Commonwealth of Mass Re - Amendment Application - Physical Security Plan for the Pilgrim Nuclear Power Station L-20-092, Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B,2020-12-10010 December 2020 Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B, L-20-096, Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 20102020-12-10010 December 2020 Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 2010 ML20328A2982020-11-16016 November 2020 Response from Commonwealth of Massachusetts on No Significant Hazard for Pilgrim ISFSI Amendment to Address ISFSI II Dated November 16, 2020 ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20163A6802020-06-11011 June 2020 Confirmation of the Scope of the Requested Regulatory Relief for Pilgrim Security Qualifications ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML20269A3542020-03-0505 March 2020 CFR 26.717 Reports 2019 Transmittal Email ML19336A0302019-11-27027 November 2019 OEDO-15-00479 - Re 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding ML19336A0332019-11-26026 November 2019 OEDO-15-00479 - E-mail to Petitioner - 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding (CAC No. MF6460; EPID L-2015-CRS-0002)- Issuance of Final Director'S Decision ML19331A1952019-11-21021 November 2019 NRR E-mail Capture - (External_Sender) Pilgrim Nuclear Power Station - Commonwealth Consultation Response - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan ML19331A1642019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1792019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Emergency Planning Exemption CY-19-007, LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station2019-11-0404 November 2019 LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station ML19275H1962019-09-24024 September 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Consult with Commonwealth - Amendment Regarding Permanently Defueled Technical Specifications (PDTS) ML19239A0372019-08-26026 August 2019 E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License Transfer ML19239A0262019-08-23023 August 2019 LTR-19-0330 Janet Azarovitz, E-mail a Plea for More Time and Reasonable Discussion Including the Citizens of the Commonwealth in the Sale of the Pilgrim Nuclear Power Station ML19234A2072019-08-20020 August 2019 LTR-19-0328 Lawrence Delafield, President, Six Ponds Improv Assoc., Plymouth, Ma, Ltr Requests NRC to Postpone Consideration of Transferring the Licenses for the Pilgrim Nuclear Power Until the NRC Has Answered Concerns by Pilgrim Watch, Se ML19232A4032019-08-20020 August 2019 LTR-19-0322 Diane Turco, Director, Cape Downwinders, Massachusetts, Letter/E-mail Requests Suspension of the Pilgrim License Transfer from Entergy to Holtec Until the Adjudicatory Hearing Is Held and Raised Contentions Are Resolved ML19308A9942019-08-19019 August 2019 Entergy Nuclear Operations, Inc. Confirmatory Order Rescission Supplemental Information ML19226A3912019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Decommissioning Trust Fund Exemption (Holtec) ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application ML19226A1212019-08-13013 August 2019 OEDO-15-00479-2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Status (CAC No. MF6460; EPID L-2015-CRS-0002) ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19176A3452019-06-25025 June 2019 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Information (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002) ML19154A0652019-06-0303 June 2019 NRR E-mail Capture - Pilgrim - Permanent Cessation of Power Operations ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements ML19123A0332019-05-0101 May 2019 NRR E-mail Capture - Logbook Entry: 05/01/2019 Endangered Species Report Regarding a Confirmed Sighting of North Atlantic Right Whale(S) (Balaena Glacialis) ML19122A4912019-04-29029 April 2019 NRR E-mail Capture - Logbook Entry: 04/29/2019 Regarding the Confirmed Sighting of Ten North Atlantic Right Whales (Balaena Glacialis) ML19108A2372019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 50.54(w)(1) - On-Site Property Damage Insurance ML19108A2362019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance 2022-09-26
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML21223A2422021-08-16016 August 2021 Enclosure - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan ML21161A1072021-07-0909 July 2021 Request for Additional Information Regarding Pilgrim License Amendment Request ISFSI Only Emergency Plan ML21013A5232021-01-15015 January 2021 Request for Additional Information Regarding the Request to Change the Physical Security Plan - Alternative Measures ML20297A2382020-10-22022 October 2020 Fleet DQAP RAIs - Enclosure ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20142A2422020-05-26026 May 2020 Acceptance of Requested Licensing Action Physical Security Plan Revision and License Amendment Request to Incorporate Additional Independent Spent Fuel Storage Installation with Requests for Additional Information ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19086A3492019-03-21021 March 2019 NRR E-mail Capture - Pilgrim Power Station - Request for Additional Information Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment (EPID: L-2018-LL0-0003) ML19036A6512019-02-0404 February 2019 NRR E-mail Capture - RAI - Pilgrim EP Exemption ML18320A1292018-11-16016 November 2018 NRR E-mail Capture - Request for Additional Information (RAI) - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML18323A1192018-11-15015 November 2018 CAL 5 Document Request #2 ML18317A2202018-11-11011 November 2018 NRR E-mail Capture - (External_Sender) Questions and Comments Regarding Pilgrim EP Exemption RAI, October 16, 2018 ML18317A2192018-11-0808 November 2018 NRR E-mail Capture - (External_Sender) RAI EP 11.06.18-Question ML18310A0212018-11-0606 November 2018 NRR E-mail Capture - RAI - Pilgrim EP Exemption ML18289A4072018-10-16016 October 2018 NRR E-mail Capture - RAIs - Pilgrim EP Exemption ML18285A8182018-10-12012 October 2018 NRR E-mail Capture - for Your Action: RAIs - Pilgrim - LAR - EP and EAL Scheme to Address Permanently Defueled Condition ML18124A1392018-05-0404 May 2018 NRR E-mail Capture - RAI - Pilgrim ERO Staffing License Amendment Request ML18094B0922018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to B. S. Ford RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59) ML18005A5422018-01-0505 January 2018 NRR E-mail Capture - Second Round of RAI for DAEC Fifth Inservice Inspection Interval Program Plan, Relief Request RR-03 - EPID: L-2017-LLR-0110 ML16347A0042016-12-0909 December 2016 NRR E-mail Capture - Pilgrim: Request for Additional Information for Relief Requests on Volumetric Exam Requirements, PNPS-ISI-001, 002 and 003 ML16013A0642016-01-13013 January 2016 NRR E-mail Capture - Request for Additional Information Entergy CNRO-2015-00023 - Revision to Entergy Quality Assurance Program Manual (Fleet Submittal CAC Nos. MF7086-MF7097) ML15341A1662015-12-0707 December 2015 NRR E-mail Capture - Entergy Fleet RR-EN-15-1, Request for Additional Information (CACs MF6341-MF6349) ML15211A6612015-07-30030 July 2015 Licensed Operator Positive Fitness-For-Duty-Test ML15051A0322015-02-25025 February 2015 Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request ML14342A0942014-12-17017 December 2014 Request for Additional Information Regarding Relief Request PRR-24, Nozzle-to-Vessel Welds and Nozzle Inner Radii Examinations ML14042A0432014-02-18018 February 2014 Request for Additional Information Regarding Safety Limits to Resolve Pressure Regulator Fail-Open Transient License Amendment Request ML13333A9102013-12-0505 December 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool ins ML13323B4702013-11-25025 November 2013 Request for Additional Information Regarding Relief Request PRR-22 ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13179A4622013-07-0505 July 2013 Entergy Nuclear Operations, Inc., Decommissioning Funding Status Report Request for Additional Information Regarding the Decommissioning Funding Status Report ML13182A4252013-07-0101 July 2013 Request for Additional Information E-mail from R.Guzman to W.Lobo PR-03 and PR-05 Fifth Ten-Year Inservice Testing (IST) Program ML13165A2762013-06-20020 June 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) ML12278A3862012-10-0404 October 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2, and 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford, Request for Additional Information, Round 2, Amendment Request to Revise QA Program Manual and Staff Qualification TSs ML1209604492012-04-0505 April 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Request for Additional Information, Revise Quality Assurance Program Manual and Staff Qualification Technical Specificat ML1208601472012-03-26026 March 2012 Request for Additional Information - Pilgrim Nuclear Power Station Revision to Condensate Storage Tank Low Level Trip Setpoint ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML12056A0502012-03-12012 March 2012 Enclosure 4 - Recommendation 2.3: Flooding ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic ML1132502282011-11-22022 November 2011 Request for Additional Information, Relief Request No. PRR-21 ML1132202342011-11-21021 November 2011 Request for Additional Information 60-Day Response to Bulletin 2011-01, Mitigating Strategies, ML1114402342011-05-25025 May 2011 Request for Additional Information to Support the Review of 2011 Decommissioning Funding Status Report ML1108202082011-04-11011 April 2011 Summary of Telephone Conference Call Held on March 23, 2011, Between the USNRC and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1106101872011-03-0303 March 2011 Request for Additional Information to Support the Review of Pilgrim Nuclear Power Station Cyber Security Plan (Id: 2.10.034) ML1105403302011-02-15015 February 2011 Response to Request for Additional Information (Rai), Dated January 5, 2011 on the Cyber Security Plan ML1100900272011-01-10010 January 2011 Request for Additional Information Revision to TS for Setpoint and Setpoint Tolerance Increase for Safety Relief Valves and Spring Safety Valves, and Related Changes (ME3543) ML1034105062011-01-0707 January 2011 December 1, 2010, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application 2021-08-16
[Table view] |
Text
NRR-DRMAPEm Resource From: Wall, Scott Sent: Friday, July 26, 2019 2:33 PM To: Couture III, Philip Cc: Halter, Mandy; Miner, Peter; Manrique, Ricardo
Subject:
Final RAI - Pilgrim License Transfer and Holtec DTF Exemption Requests (EPID: L-2018-LL0-0003 and L-2018-LLE-0020)
Dear Mr. Couture,
By application dated November 16, 2018 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML18320A031), as supplemented by letters dated November 16, 2018, and April 17, 2019 (ADAMS Accession Nos. ML18320A040 and ML19109A177, respectively), Entergy Nuclear Operations, Inc.
(ENOI), on behalf of itself and Entergy Nuclear Generation Company (ENGC) (to be known as Holtec Pilgrim, LLC), Holtec International (Holtec), and Holtec Decommissioning International, LLC (HDI), (hereinafter referred to as Applicants), requested that the U.S. Nuclear Regulatory Commission (NRC) consent to the following actions:
(1) the indirect transfer of control of the Renewed Facility Operating License No. DPR-35 for the Pilgrim Nuclear Power Station (Pilgrim), as well as the general license for the Pilgrim Independent Spent Fuel Storage Installation (ISFSI), to Holtec, and (2) the direct transfer of ENOIs operating authority to HDI.
The Applicants also requested that the NRC approve a conforming administrative amendment to the facility licenses, to reflect the proposed direct transfer of the licenses from ENOI to HDI and the planned name change for ENGC, from ENGC to Holtec Pilgrim, LLC (Holtec Pilgrim).
Additionally, in Enclosure 2 of the license transfer application dated November 16, 2018, HDI requested exemption from 10 CFR 50.82(a)(8)(i)(A). The exemption from 10 CFR 50.82(a)(8)(i)(A) would permit HDI to make withdrawals from the Pilgrim Decommissioning Trust Fund (DTF) for spent fuel management and site restoration activities in accordance with the site-specific Pilgrim Decommissioning Cost Estimate (DCE).
The U.S. Nuclear Regulatory Commission staff has reviewed the submittals and determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). During a telephone call on July 26, 2019, the Entergy staff indicated that a response to the RAI would be provided within 10 days.
If you have questions, please contact me at 301-415-2855 or via e-mail at Scott.Wall@nrc.gov.
Scott P. Wall, LSS BB, BSP Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 301.415.2855 Scott.Wall@nrc.gov Docket Nos. 50-293 and 72-1044
Enclosure:
Request for Additional Information 1
cc: Listserv RAI-PFPB-1 REQUEST FOR ADDITIONAL INFORMATION DIRECT AND INDIRECT TRANSFER OF LICENSE AND CONFORMING LICENSE AMENDMENT AND REQUEST FOR EXEMPTION FROM 10 CFR 50.82(a)(8)(i)(A)
ENTERGY NUCLEAR OPERATIONS, INC.
PILGRIM NUCLEAR POWER STATION DOCKET NOS. 50-293 AND 72-1044 By application dated November 16, 2018 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML18320A031), as supplemented by letters dated November 16, 2018, and April 17, 2019 (ADAMS Accession Nos. ML18320A040 and ML19109A177, respectively), Entergy Nuclear Operations, Inc.
(ENOI), on behalf of itself and Entergy Nuclear Generation Company (ENGC) (to be known as Holtec Pilgrim, LLC), Holtec International (Holtec), and Holtec Decommissioning International, LLC (HDI), (hereinafter referred to as Applicants), requested that the U.S. Nuclear Regulatory Commission (NRC) consent to the following actions:
(1) the indirect transfer of control of the Renewed Facility Operating License No. DPR-35 for the Pilgrim Nuclear Power Station (Pilgrim), as well as the general license for the Pilgrim Independent Spent Fuel Storage Installation (ISFSI), to Holtec, and (2) the direct transfer of ENOIs operating authority to HDI.
The Applicants also requested that the NRC approve a conforming administrative amendment to the facility licenses, to reflect the proposed direct transfer of the licenses from ENOI to HDI and the planned name change for ENGC, from ENGC to Holtec Pilgrim, LLC (Holtec Pilgrim).
In support of its license transfer application, HDI submitted a Notification of Revised Post-Shutdown Decommissioning Activities Report and Revised Site-Specific Decommissioning Cost Estimate for Pilgrim Nuclear Power Station (revised PSDAR) on November 16, 2018 (ADAMS Accession No. ML18320A040), to notify the NRC of changes to accelerate the schedule for the prompt decommissioning (i.e., DECON) of Pilgrim and unrestricted release of all portions of the site (excluding the ISFSI) within 8 years after the license transfer. On December 17, 2018 (ADAMS Accession No. ML18333A240), the NRC notified ENOI that the staff is treating the revised PSDAR submittal, dated November 16, 2018, as a supplement to the Pilgrim license transfer application, also dated November 16, 2018, until such time as the NRC makes a regulatory decision on the Pilgrim license transfer application. The NRC staff is reviewing the revised PSDAR only to determine whether Holtec Pilgrim and HDI are financially and technically qualified to hold the license for Pilgrim and the general license for the Pilgrim ISFSI, as described in the application, and to engage in the proposed maintenance and decommissioning activities associated with the Pilgrim site.
Additionally, in Enclosure 2 of the license transfer application dated November 16, 2018, HDI requested an exemption from 10 CFR 50.82(a)(8)(i)(A). The exemption from 10 CFR 50.82(a)(8)(i)(A) would permit HDI to make withdrawals from the Pilgrim Decommissioning Trust Fund (DTF) for spent fuel management and site 2
restoration activities in accordance with the site-specific Pilgrim Decommissioning Cost Estimate (DCE),
included with the revised PSDAR.
The U.S. Nuclear Regulatory Commission staff reviewed the submittal and determined that the following additional information is needed to complete its review.
RAI-PFPB-01 Applicable Regulation and Guidance In Title 10 of the Code of Federal Regulations (10 CFR) Part 50.75, Reporting and recordkeeping for decommissioning planning, the NRC establishes requirements for indicating to the NRC how a licensee will provide reasonable assurance that funds will be available for the decommissioning process. In addition, 10 CFR 50.75(b) requires that each power reactor applicant for an operating license submit a decommissioning report, as required by 10 CFR 50.33(k).
In 10 CFR 50.75(b)(1), the NRC states, in part, that:
For an applicant for an operating license under part 50, the report must contain a certification that financial assurance for decommissioning will be provided in an amount which may be more, but not less, than the amount stated in the table in paragraph (c)(1) of this section In 10 CFR 50.75(b)(3), the NRC indicates that the amount determined by 10 CFR 50.75(c) must be covered one or more of the methods described in Section 50.75(e).
Further, 10 CFR 50.75(b)(4) states, in part:
The amount stated in the applicant's certification may be based on a cost estimate for decommissioning the facility.
In 10 CFR 50.75(c), the NRC provides the method acceptable to the agency for determining the minimum amount required to demonstrate reasonable assurance of funds for decommissioning by reactor type and power level; with adjustment factor.
In 10 CFR 50.75(e), the NRC includes the methods acceptable to the agency for providing decommissioning financial assurance.
Finally, 10 CFR 50.75(h) provides additional requirements on the management of decommissioning trust funds (DTFs).
10 CFR 50.33(f) states, in part:
Except for an electric utility applicant for a license to operate a utilization facility of the type described in § 50.21(b) or § 50.22, [each application shall state] information sufficient to demonstrate to the Commission the financial qualification of the applicant to carry out, in accordance with regulations in this chapter, the activities for which the permit or license is sought.
The definition of decommission in 10 CFR 50.2 reads as follows:
to remove a facility or site safely from service and reduce residual radioactivity to a level that permits (1) Release of the property for unrestricted use and termination of the license; or (2) Release of the property under restricted conditions and termination of the license.
The regulation in 10 CFR 50.82(a)(8)(i)(A) restricts the use of DTF withdrawals to expenses for legitimate decommissioning activities consistent with the definition of decommissioning in 10 CFR 50.2. This definition in 10 CFR 50.2 does not include activities associated with spent fuel management and site restoration activities.
3
Regulatory Guide (RG) 1.202, Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors (ADAMS Accession No. ML050230008), states, in part, that:
[T]o meet the requirements of 10 CFR 50.75(c), a power reactor licensee may submit a certification based on a site-specific cost estimate, which may be more (but not less) than the amount specified in 10 CFR 50.75(b)(1).
In addition, RG 1.202, states:
a site-specific estimate may be submitted, at the discretion of the licensee, when a funding level differs from that calculated in the formula in 10 CFR 50.75(c). The site-specific cost estimate must clearly identify and provide the basis for the funding level if it differs from the formula.
Further RG 1.202, indicates that the licensee should provide a comparison of the estimated decommissioning cost with the minimum financial assurance funding requirement of 10 CFR 50.75(c).
RG 1.159, Assuring the Availability of Funds for Decommissioning Nuclear Reactors (ADAMS Accession No. ML112160012), states, in part, that:
At its discretion, a power reactor licensee may submit a certification based either on the formulas provided in 10 CFR 50.75(c)(1) and (2) or, when a higher funding level is desired, on a site-specific cost estimate that is equal to or greater than that calculated in the formulas in 10 CFR 50.75(c)(1) and (2). A site-specific cost estimate may include non-NRC-required costs, but such costs should be identified. If such a combined submittal is used, licensees should ensure that the NRC-required cost estimate for decommissioning costs, as defined in 10 CFR 50.2, is equal to or greater than the amount stated in the formulas in 10 CFR 50.75(c)(1) and (2). For certification amounts below the amount stated in the formulas in 10 CFR 50.75(c)(1) and (2),
licensees must submit an exemption request.
The NRC staff also applied guidance in NUREG-1577, Revision 1, Standard Review Plan on Power Reactor Licensee Financial Qualifications and Decommissioning Funding Assurance, issued February 1999 (ADAMS Accession No. ML013330264), to evaluate the financial qualifications of applicants to carry out the activities for which the permit or license is sought.
NUREG-1713, Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors, issued December 2004 (ADAMS Accession No. ML043510113), to evaluate decommissioning cost estimates provided by power reactor licensees. NUREG-1713, states in part, that:
The [NRC] reviewer should compare the [site-specific DCE] with the minimum decommissioning financial assurance requirement amount derived per the algorithm discussed in [10 CFR 50.75(c)]. If the [site-specific DCE] is less than the amount derived from the algorithm in 10 CFR 50.75(c) and adequate justification is not provided, [the NRC] will inform the licensee in writing of additional information needed to resolve the deficiency.
Issue By letter dated March 28, 2019 (ADAMS Accession No. ML19087A318), ENOI submitted its annual report on the status of decommissioning funding for Pilgrim. The report states that the minimum amount (December 2018 dollars) required to demonstrate reasonable assurance of funds for decommissioning, as required by 10 CFR 50.75(c), is $633,267,558.
The HDI analysis in the November 16, 2018, revised PSDAR, projects the total radiological decommissioning cost of Pilgrim to be approximately $592,553,000 in 2018 dollars. The request for exemption from 10 CFR 50.82(a)(8)(i)(A) relies on the estimated costs for radiological decommissioning, including ISFSI decommissioning costs, as well as for spent fuel management and site restoration provided in the revised PSDAR.
4
Request for Additional Information
- 1. As identified in the NRC regulations and guidance documents described above, the estimated radiological decommissioning costs, consistent with the definition in 10 CFR 50.2, may be more, but not less, than the amount specified in 10 CFR 50.75(c).
In the November 16, 2018, license transfer application, the Applicants state the following:
The required [DTF] value at closing exceeds the minimum financial assurance required by 10 CFR 50.75(b) and the site-specific estimate of the radiological decommissioning cost, providing sufficient confidence that decommissioning can be achieved without the need for additional financial assurance. Further, a cash-flow analysis based on the site-specific estimate demonstrates that the funds in the [DTF] at closing will be sufficient to fund all radiological decommissioning costs, spent fuel management costs, and site restoration costs through the expected license termination date, and thus demonstrates Holtec Pilgrims financial qualifications.
However, there is no comparison in the application between the estimated radiological decommissioning costs of $592,553,000 and the 10 CFR 50.75(c) minimum amount of $633,267,558, as reported by ENOI in its March 28, 2019, decommissioning funding status report.
Based on the requirements and guidance cited above, please justify using a total radiological decommissioning cost estimate value, consistent with the definition in 10 CFR 50.2, that is less than the minimum amount calculated using 10 CFR 50.75(c) in support of the license transfer application and the exemption request.
- 2. Using the 10 CFR 50.75(c) minimum amount for radiological decommissioning costs, please provide an updated, revised decommissioning cash flow analysis to support the license transfer application and exemption request.
5
Hearing Identifier: NRR_DRMA Email Number: 144 Mail Envelope Properties (BN6PR09MB14270246B66FD71A76D6517692C00)
Subject:
Final RAI - Pilgrim License Transfer and Holtec DTF Exemption Requests (EPID:
L-2018-LL0-0003 and L-2018-LLE-0020)
Sent Date: 7/26/2019 2:33:02 PM Received Date: 7/26/2019 2:33:00 PM From: Wall, Scott Created By: Scott.Wall@nrc.gov Recipients:
"Halter, Mandy" <mhalter@entergy.com>
Tracking Status: None "Miner, Peter" <pminer@entergy.com>
Tracking Status: None "Manrique, Ricardo" <rmanriq@entergy.com>
Tracking Status: None "Couture III, Philip " <pcoutur@entergy.com>
Tracking Status: None Post Office: BN6PR09MB1427.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 14519 7/26/2019 2:33:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: