MONTHYEARNG-20-0090, Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center2020-10-12012 October 2020 Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center Project stage: Request NG-20-0083, Registration of Independent Spent Fuel Installation Storage Casks2020-10-12012 October 2020 Registration of Independent Spent Fuel Installation Storage Casks Project stage: Request L-21-008, License Amendment Request to Approve Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation Only Emergency Plan2021-02-18018 February 2021 License Amendment Request to Approve Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Request ML21069A3312021-03-15015 March 2021 Acceptance of Requested Licensing Action Re Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Acceptance Review L-21-057, Supplemental Information to Update - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan2021-05-20020 May 2021 Supplemental Information to Update - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan Project stage: Supplement ML21158A1232021-06-24024 June 2021 License Amendment No. 46, Revised License Termination Plan Project stage: Request ML21158A1262021-06-24024 June 2021 Letter - Humboldt Bay Power Plant Unit 3 - Issuance of Amendment No. 46 Re License Termination Plan Project stage: Approval NG-21-0010, License Amendment Request (TSCR-192): Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2021-06-28028 June 2021 License Amendment Request (TSCR-192): Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme Project stage: Request ML21158A1132021-06-28028 June 2021 License Amendment Application - Revision of the License Termination Plan - May 3, 2021 Request for Additional Information Response Clarification Call Project stage: RAI ML21161A1072021-07-0909 July 2021 Request for Additional Information Regarding Pilgrim License Amendment Request ISFSI Only Emergency Plan Project stage: RAI L-21-090, Response to Request for Additional Information (Rai), License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan2021-07-29029 July 2021 Response to Request for Additional Information (Rai), License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan Project stage: Response to RAI ML21223A2422021-08-16016 August 2021 Enclosure - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: RAI ML21223A2392021-08-16016 August 2021 Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Request ML21223A2412021-08-16016 August 2021 Letter to A. Sterdis, HDI, from A. Snyder, NRC - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: RAI ML21238A2752021-08-26026 August 2021 Clarification Call Regarding RAI License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: RAI L-21-098, Response to Request for Additional Information (RAI) - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan2021-09-0707 September 2021 Response to Request for Additional Information (RAI) - License Amendment Request to Approve the Pilgrim Nuclear Power Station Independent Fuel Storage Installation Only Emergency Plan Project stage: Response to RAI ML21257A3822021-09-15015 September 2021 Summary of Clarification Cal with Holtec Decommissioning International, Llc. Regarding Second Follow-On Emergency Preparedness Request for Additional Information Project stage: RAI ML21257A3792021-09-15015 September 2021 Clarification Call 2 Re Request for Additional Information Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan Project stage: Request ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl Project stage: RAI ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness Project stage: Request ML21265A3032021-10-21021 October 2021 Enclosure 2 - Pilgrim ISFSI Only SER Input Final Project stage: Other ML21251A1622021-10-21021 October 2021 Ioep Amendment No. 257 Project stage: Request ML21251A1732021-10-21021 October 2021 Enclosure 1 - Pilgrim Amendment No. 257 ISFSI Only Emergency Plan Project stage: Other ML21251A1722021-10-21021 October 2021 Issuance of Amendment No. 257 ISFSI Only Emergency Plan Cover Letter Project stage: Approval ML21335A0712021-12-0101 December 2021 Request for Additional Information - Duane Arnold Energy Center ISFSI Only Emergency Plan Project stage: RAI ML21335A0702021-12-0101 December 2021 Cover Letter to B. Coffey from K. Conway - Duane Arnold Energy Center RAI Re License Amendment Request for ISFSI Only Emergency Plan Project stage: RAI ML21335A0662021-12-0101 December 2021 Request for RAI License Amendment Request ISFSI Only EP Project stage: Request ML22357A1002023-03-31031 March 2023 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments Standard Emergency Plan and Consolidated Emergency Operations Facility Project stage: Approval 2021-06-24
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24241A1512024-09-18018 September 2024 License Termination Plan Readiness Assessment Site Visit Summary - June 2024 ML21257A3822021-09-15015 September 2021 Summary of Clarification Cal with Holtec Decommissioning International, Llc. Regarding Second Follow-On Emergency Preparedness Request for Additional Information ML21238A2752021-08-26026 August 2021 Clarification Call Regarding RAI License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan ML21075A3152021-03-17017 March 2021 March 11,2021 Pilgrim Request for Additional Information Response Clarifiction Meeting - Proposed Physical Security Plan ML21035A2312021-02-18018 February 2021 Physical Security Plan - RAI Clarification Meeting ML21035A1712021-02-18018 February 2021 Physical Security Plan - ISFSI Only Meeting Summary ML20045D1082020-02-19019 February 2020 January 31, 2020 Meeting Summary Pre-Amendment Meeting Proposed Changes to Pilgrim ISFSI Physical Security Plan ML19274B6662019-11-13013 November 2019 Summary of Public Meeting Near the Pilgrim Nuclear Power Station Regarding the Establishment and Operation of Community Advisory Boards ML19121A2172019-04-30030 April 2019 Annual Assessment Meeting for Pilgrim Nuclear Power Station - Meeting Summary ML19017A1732019-01-30030 January 2019 Summary of 1/15/2019 Public Meeting Regarding Pilgrim Nuclear Power Station Post-Shutdown Decommissioning Activities Report, Which Includes the Site-Specific Decommissioning Cost Estimate ML18275A3952018-10-12012 October 2018 9/25/2018 Summary of Pre-submittal Meeting with Entergy Nuclear and Holtec International to Discuss Potential License Transfer Application for Pilgrim Nuclear Power Plant ML18130A1592018-05-0909 May 2018 Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17101A3992017-04-13013 April 2017 Statement of Congressman Keating - NRC Annual Assessment Meeting for PNPS - March 21, 2017 ML17103A4132017-04-13013 April 2017 3/21/2017 - Annual Assessment/95003 Inspection Exit Summary Meeting for Pilgrim Nuclear Power Station ML17059C9192017-02-28028 February 2017 1/31/2017 - Summary of Category 3 Public Meeting - Preliminary Findings and Status of 95003 Inspection at Pilgrim ML16116A0052016-04-22022 April 2016 4/13/2016 - Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station ML15306A0122015-11-0505 November 2015 Summary of October 20, 2015, Teleconference with Entergy Nuclear Operations to Discuss Proposed Changes to Emergency Response Organization Training for Pilgrim Nuclear Power Station ML15092A7932015-04-0202 April 2015 Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station on 3/18/15 ML14136A3502014-05-14014 May 2014 Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station on 5/1/2014 (W/Nrc Presentation Slides) ML14086A2912014-04-22022 April 2014 Summary of Telephone Conference Regarding the Verbal Authorization of Relief Request PRR-25, Revision 1 ML13109A4362013-04-19019 April 2013 4/2/2013 - Pilgrim - Annual Assessment Meeting Summary ML12101A3742012-04-10010 April 2012 Summary of Meeting with Pilgrim Nuclear Power Station 2011 Annual Assessment ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors ML1118105332011-06-30030 June 2011 Summary of Annual Assessment Public Meeting with Entergy Nuclear Operation, Inc ML1117906392011-06-28028 June 2011 Summary of Meeting with Entergy Operations Inc ML11166A1342011-06-22022 June 2011 Meeting Summary with the Beyond Nuclear Petitioners Regarding Their 2.206 Petition to Suspend Operating Licenses (Ols) of General Electric (GE) Boiling Water Reactors (Bwrs) Mark I (Bwrs) ML1110401712011-04-27027 April 2011 04/5/2011 Summary of Preapplication Meeting with Entergy Operations, Inc. to Discuss Fleetwide Submittal for Proposed Technical Specification and Quality Assurance Program Manual Changes Related to Unit Staff Qualification Requirements ML1109700342011-04-19019 April 2011 Summary of Tele Conf Call Held on 4/6/11, Between the USNRC and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1108206892011-04-19019 April 2011 February 24, 2011, Summary of Telephone Conference Call Held Between NRC and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1108202082011-04-11011 April 2011 Summary of Telephone Conference Call Held on March 23, 2011, Between the USNRC and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1100404192011-02-15015 February 2011 Summary of Telephone Conference Call Held on December 6, 2010, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operating, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application (Tac No. MC9669) ML1034105062011-01-0707 January 2011 December 1, 2010, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1025900772010-10-15015 October 2010 Summary of Telephone Conference Call Held on 6/2/10 Btw the USNRC and Entergy Nuclear Operations, Inc. Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1025900862010-10-15015 October 2010 5/25/10 Summary of Telephone Conference Call Held Between USNRC and Entergy Nuclear Operations, Inc. Concerning the Annual Update Associated with the Pilgrim Nuclear Power Station License Renewal Application ML1012603632010-05-0606 May 2010 Summary of Annual Assessment Open House Public Meeting Discussed Nrc'S Assessment of Safety Performance of Pilgrim for Cy 2009 ML1011100082010-04-21021 April 2010 Summary of Public Meeting to Discuss the Results of Entergy Nuclear Plant Safety Culture Workplace Survey ML0909702992009-04-13013 April 2009 Annual Assessment Meeting Summary, Slides, Sign-in Sheet, Misc Documents, for 3/26/09 Meeting ML0809202432008-04-0101 April 2008 Summary of March 28, 2008, Annual Assessment Meeting with Entergy Nuclear Operations, Inc ML0724302642007-09-0707 September 2007 08/30/2007 Summary of Telephone Conference Call Between the U.S. NRC and Entergy Nuclear Operations, Inc., to Discuss and Clarify Commitment No. 47 Pertaining to the Pilgrim Nuclear Power Station License Renewal Application ML0713701422007-05-18018 May 2007 Summary of Annual Assessment Meeting with Entergy Nuclear Operations, Inc., Regarding the Nrc'S Assessment of the Safety Performance of Pilgrim Nuclear for the Calendar Year 2006 ML0710300932007-05-0101 May 2007 03/14-15/2007 Summary of Conference Calls with Entergy Nuclear Operations Inc., Pilgrim License Renewal Application, Pilgrim Request for Additional Information B.1.16.1, and Neutron Fluence ML0710300532007-04-27027 April 2007 Summary of Conference Calls on April 2, 2007, with Entergy Nuclear Operations, Inc., Regarding the Pilgrim License Renewal Application ML0710300482007-03-19019 March 2007 E-mail: (PD) Meeting Summary - March 14 & 15 2007 - from Perry Buckberg to Doug Ellis 3/19/07 7:05am ML0706005672007-03-15015 March 2007 Summary of the License Renewal Telephone Conference Call and Meeting Held Between the U.S. Nuclear Regulatory Commission Staff and the Nuclear Energy Institute License Renewal Task Force ML0710302212007-03-0707 March 2007 E-MAIL: (PD) Updated - Week of 2/26 Conference Call Record from Perry Buckberg to Doug Ellis 3/7/07 6:36am ML0705402052007-03-0101 March 2007 01/24/2007 Summary of Meeting with Pilgrim on the Draft Supplemental Environmental Impact Statement Regarding Pilgrim License Renewal Review ML0635400102007-01-18018 January 2007 12/18/2006 Summary of Conference Call with Entergy Nucelar Operations, Inc., Regarding the Pilgrim License Renewal Application 2024-09-18
[Table view] |
Text
September 14, 2021 LICENSEE: Holtec Decommissioning International, LLC FACILITY: Pilgrim Nuclear Power Station
SUBJECT:
SUMMARY
OF SEPTEMBER 14, 2021, CLARIFICATION CALL WITH HOLTEC DECOMMISSIONING INTERNATIONAL, LLC, REGARDING SECOND FOLLOW-ON EMERGENCY PREPAREDNESS REQUEST FOR ADDITIONAL INFORMATION (EPID: L-2021-LLA-0021)
At the request of the licensee, Holtec Decommissioning International, LLC (HDI), the U.S. Nuclear Regulatory Commission (NRC) had a clarification call with HDI on September 14, 2021. The purpose of the meeting was a clarification teleconference to ensure the licensee understands the second follow-on Request for Additional Information (RAI) questions that were provided on September 8, 2021 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML21257A383) for the Pilgrim Nuclear Power Station (Pilgrim) Independent Spent Fuel Storage Installation Emergency Preparedness application review.
The meeting began with opening remarks by the NRC staff, followed by introductions of the attendees. A list of attendees is provided in the Table below:
NRC HDI Amy Snyder, NMSS Andrea Sterdis Keith Miller, NSIR David Noyes Michael Norris, NSIR Mary Gatlick NRC acknowledged HDIs the quick turn around on the RAI response (ADAMS Accession No. ML21250A345) and thanked HDI for providing a complete clean version of the Emergency Preparedness Plan (EP) plan, but because the NRC staff found inconsistencies in the RAI response and the resubmitted EP Plan, the NRC requested that the licensee resolve these inconsistencies. HDI said that it appreciates the clarification call and the NRC quick response in evaluating its RAIs and the opportunity for another clarification call. HDI commented that it is still on track to complete its spent fuel transfer campaign in November 2021 and will continue to expediate its responses to the NRC on this licensing proceeding. HDI said that it overlooked a few things regarding document version control and will address it through its corrective action program.
Each RAI question was reviewed to ensure that the licensee understood the questions. HDI confirmed that the Fire Department is a 24/7 fire department and is the agreed upon touch point for contacting the Town of Plymouth. Also, HDI confirmed that it introduced an error on Emergency Action Level (EAL) Chart by submitting the wrong EAL basis version. HDI stated that there were also additional changes to the document that were made between RAI 1 and
RAI 2 documents, but they were consistent with the changes made in the RAI 1 response. HDI noted that the words Within the owner-controlled area will be added to RAI 2 response. HDI said that it plans to send a clean version of the EALs for the NRC to review with its response.
Also, HDI noted that it will delete the two definitions in its EP plan as indicated in its supplemental submittal.
HDI estimates that its RAI responses will be submitted to the NRC within approximately one week. The NRC summarized the remainder of the review process schedule and determined that the review is likely to remain on track for an end of October 2021 completion given the wiliness of HDI to submit its response in an expediated manner.
At this meeting, the NRC staff made no regulatory decisions about the merits of the HDI proposed RAI responses.
Please direct any inquiries to me at (301) 415-6822 or Amy.Snyder@nrc.gov.
Sincerely, Signed by Snyder, Amy on 09/14/21 Amy M. Snyder, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards Docket Nos. 50-293 and 72-1044
ML21257A379; ML21257A382 OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NMSS/DUWP/RDB NAME ASnyder AS BWatson BW ASnyder AS DATE Sep 14, 2021 Sep 14, 2021 Sep 14, 2021