Letter Sequence RAI |
---|
TAC:ME7774, (Approved, Closed) TAC:ME7775, (Approved, Closed) TAC:ME7776, (Approved, Closed) TAC:ME7777, (Approved, Closed) TAC:ME7778, (Approved, Closed) TAC:ME7779, (Approved, Closed) TAC:ME7780, (Approved, Closed) TAC:ME7781, (Approved, Closed) TAC:ME7782, (Approved, Closed) TAC:ME7783, (Approved, Closed) TAC:ME7784, (Approved, Closed) TAC:ME7785, (Approved, Closed) TAC:ME7786, (Approved, Closed) |
|
MONTHYEARCNRO-2011-00006, Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications2011-12-13013 December 2011 Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Technical Specifications Regarding Staff Qualifications Project stage: Request ML1202607432012-01-26026 January 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2, and 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Acceptance Review Email, Amendment to Revise Quality Assurance Program Manual and Staff Qualification Technical Speci Project stage: Acceptance Review ML1209604492012-04-0505 April 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Request for Additional Information, Revise Quality Assurance Program Manual and Staff Qualification Technical Specificat Project stage: RAI ML1209604232012-04-0505 April 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Email, Request for Additional Information, Revise Quality Assurance Program Manual and Staff Qualification Technical Spe Project stage: RAI CNRO-2012-00004, Request for Additional Information Regarding Changes to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Plant Technical Specifications Regarding Staff Qualifications2012-05-21021 May 2012 Request for Additional Information Regarding Changes to the Entergy Quality Assurance Program Manual (QAPM) and Associated Plant Plant Technical Specifications Regarding Staff Qualifications Project stage: Request ML12278A3862012-10-0404 October 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2, and 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford, Request for Additional Information, Round 2, Amendment Request to Revise QA Program Manual and Staff Qualification TSs Project stage: RAI CNRO-2012-00009, Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications2012-11-20020 November 2012 Entergy Responses to Request for Additional Information Regarding Changes to the Quality Assurance Program Manual & Associated Plant Technical Specifications Re Staff Qualifications Project stage: Response to RAI ML13025A3212013-03-14014 March 2013 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Correction FRN, Biweekly Notice of Issuance of Amendments Published on 1/22/13, Revise QA Program Manual and Staff Quali Project stage: Approval ML13025A3062013-03-14014 March 2013 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Correction to Amendments Issued on 12/28/12, Revise QA Program Manual and Staff Qualification Technical Specifications Project stage: Other ML13101A0942013-04-12012 April 2013 Correction to Amendment No. 249 Regarding Change to the Entergy QAPM and Associated Technical Specifications Regarding Staff Qualifications Project stage: Other ML13122A0662013-05-0808 May 2013 Correction to Amendment No. 193 Related to Entergy Fleet Amendment Issued 12/28/12 to Revise QA Program Manual and Staff Qualification Technical Specifications Project stage: Other 2012-04-05
[Table View] |
ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Request for Additional Information, Revise Quality Assurance Program Manual and Staff Qualification Technical SpecificatML120960449 |
Person / Time |
---|
Site: |
Palisades, Indian Point, Grand Gulf, Pilgrim, Arkansas Nuclear, River Bend, Vermont Yankee, Big Rock Point, FitzPatrick |
---|
Issue date: |
04/05/2012 |
---|
From: |
Kalyanam K Plant Licensing Branch IV |
---|
To: |
Ford B Entergy Operations |
---|
Kalyanam N, NRR/DORL/LPL4, 415-1480 |
Shared Package |
---|
ML120960412 |
List: |
---|
References |
---|
TAC ME7774, TAC ME7775, TAC ME7776, TAC ME7777, TAC ME7778, TAC ME7779, TAC ME7780, TAC ME7781, TAC ME7782, TAC ME7783, TAC ME7784, TAC ME7785, TAC ME7786 |
Download: ML120960449 (3) |
|
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24024A1372024-01-24024 January 2024 NRR E-mail Capture - Final Snsb RAI Regarding FitzPatrick Amendment to Modify Safety Relief Valves Setpoint Lower Tolerance ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information ML23354A2602023-12-21021 December 2023 Reference Simulator Inspection Request for Information ML23348A1222023-12-14014 December 2023 NRR E-mail Capture - Grand Gulf, River Bend, and Waterford, Unit 3 - 2nd Round of Official RAIs for RR EN-RR-22-001, Use ASME Code Case N-752, Risk Informed Categorization for Class 2 and 3 Systems ML23311A4322023-11-0909 November 2023 Notification of NRC Supplemental Inspection (95001) and Request for Information ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23195A0692023-07-24024 July 2023 2023 River Bend Station Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ML23171B0442023-06-23023 June 2023 Enclosure - Indian Point Energy Center - Request for Additional Information for Independent Spent Fuel Storage Installation Facility-Only Emergency Plan License Amendment ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23116A1462023-04-26026 April 2023 NRR E-mail Capture - Entergy Fleet (Grand Gulf and River Bend) - Final RAI for Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23081A4602023-03-22022 March 2023 RFI River Bend CETI 2023012 Drr ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23059A0742023-02-27027 February 2023 Information Request, Security IR 2023402 ML23055A1542023-02-24024 February 2023 Attachment: Request for Additional Information on the Palisades PSDAR ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML23004A0422023-01-0404 January 2023 License Renewal Phase 1 Request for Information ML22354A0812022-12-20020 December 2022 Inservice Inspection Request for Information ML22353A6122022-12-19019 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22321A0102022-11-17017 November 2022 Notification of Conduct of a Fire Protection Team Inspection ML22292A2582022-10-31031 October 2022 PDEP-EAL Amendment RAI ML22292A2402022-10-21021 October 2022 RAIs for Master Dtf Agreement on IP1 IP2 10 18 2022 ML22271A8572022-10-0303 October 2022 Notification of Commercial Grade Dedication Inspection (05000416/2023011) and Request for Information ML22235A1082022-08-19019 August 2022 RBS Emergency Preparedness (EP) Exercise Inspection October 2022 RFI ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22180A0612022-06-29029 June 2022 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000458/2022010) and Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2672022-05-0404 May 2022 Request for Additional Information for James A. FitzPatrick Nuclear Power Plant TSTF-505 ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22110A1172022-04-19019 April 2022 (GG) 2022 Emergency Preparedness (EP) Program Inspection RFI Sdh 041922 ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22102A2482022-04-14014 April 2022 Request for Additional Information Regarding License Amendment Request for Permanently Defueled Technical Specifications ML22103A2442022-04-13013 April 2022 Attachment - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center ML22104A0352022-04-13013 April 2022 Request for Additional Information Related to Exemption Request from Emergency Planning Holtec Decommissioning International, LLC Indian Point Energy Center ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML22006A0452022-01-0505 January 2022 PSDAR RAIs Final ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21274A4172021-10-0505 October 2021 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information Inspection Report 05000255/2021004 ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information 2024-01-24
[Table view] |
Text
REQUEST FOR ADDITIONAL INFORMATION REGARDING THE ENTERGY QUALITY ASSURANCE PROGRAM MANUAL (QAPM) AND ASSOCIATED PLANT TECHNICAL SPECIFICATIONS REGARDING STAFF QUALIFICATIONS, REVISION 22 Regulatory Commitments - Table 1.
1.0.1 Entergys QAPM, Revison 21, Table 1, Regulatory Commitments states that Entergy is committed to Regulatory Guide 1.8, Revision 1, dated 1975. The QAPM, Revision 21, Clarification/Exception section states, Qualification requirements for personnel, other than Licensed Operators covered under 10 CFR 55, shall meet ANSI/ANS 3.1 1978 except for positions where an exception to either ANSI/ANS 3.1-1978 or N18.1 -1971 is stated in the applicable units Technical Specifications. If an exception exists for a given position, the applicable units Technical Specification qualification requirements shall apply. The proposed revision to the QAPM will delete the above statement and replace it with:
Entergy is committed to Sections 1 - 4 of ANSI/ANS 3.1-1978 with following clarifications and exceptions.
Qualification requirements for personnel shall meet ANSI/ANS 3.1-1978 except the following:
- a. The radiation protection manager shall meet or exceed the qualifications of Regulatory Guide 1.8, Revision 2, 1987.
- b. Managers required to hold an SRO license are specified in the applicable unit's Technical Specifications.
- c. Licensed Operators shall be qualified in accordance with the requirements of 10 CFR 55.
The proposed QAPM revision will remove the referenced N18.1 -1971 Standard that Regulatory Guide 1.8 endorses. Please provide clarification of what revision of Regulatory Guide 1.8 Entergy will be committed to when the Regulatory Guide 1.8, Revision 1, which endorsed Standard N18.1-1971, is removed.
1.0.2 Entergys current QAPM states in part:
Individuals filling positions who met the previous commitment at the time of implementation of this commitment can be considered to meet any more restrictive aspects of the requirements of this commitment for that position without further review and documentation.
Entergys proposed revision to the QAPM adds the proposed insert:
Individuals who do not possess the formal education and minimum experience requirements for the manager responsible for quality assurance should not be eliminated automatically when other factors provide sufficient demonstration of their abilities. These other factors are evaluated on a case-by-case basis and approved and documented by senior management.
The current statement in the QAPM and the proposed insert are in conflict with each other.
Please provide clarification on how Entergy plans to evaluate individuals on a case-by-case basis for acceptability if the current statement is not removed.
1.0.3 Entergys proposed revision to the QAPM will state:
Entergy is committed to Sections 1 - 4 of ANSI/ANS 3.1-1978 with following clarifications and exceptions.
Qualification requirements for personnel shall meet ANSI/ANS 3.1-1978 except the following:
- a. The radiation protection manager shall meet or exceed the qualifications of Regulatory Guide 1.8, Revision 2, 1987.
- b. Managers required to hold an SRO license are specified in the applicable unit's Technical Specifications.
- c. Licensed Operators shall be qualified in accordance with the requirements of 10 CFR 55.
Entergys proposed revisions to the affected plants TS states, Each member of the unit staff shall meet or exceed the minimum qualifications of ANSI/ANS 3.1-1978 for comparable positions with exceptions specified in the Entergy QAPM. Please provide clarification on the extent of use of ANSI/ANS 3.1-1978.
1.0.4 Entergy QAPM, Table 1, Regulatory Commitments, page 21 commits to Regulatory Guide 1.8, Revision 1, dated September 1975. The Clarification/Exception of this section does not clearly state the affected sections of the standard requiring the clarification or exception. Please provide clarification by identifying the clarifications and exceptions taken from Regulatory Commitments as in other sections of Table 1.
1.0.5 10 CFR 50.54(a)(4) states in part that, Changes to the quality assurance program description that do reduce the commitments must be submitted to the Nuclear Regulatory Commission (NRC) and receive NRC approval prior to implementation. The regulation also states, the submittal of a change to quality assurance program description must include all pages affected by that change and must be accompanied by a forwarding letter identifying the change, the reason for the change, and the basis for concluding that the revised program incorporating the change continues to satisfy the criteria of appendix B of this part and the Safety Analysis Report quality assurance program description commitments previously accepted by the NRC (the letter need not provide the basis for changes that correct spelling, punctuation, or editorial items). The use of ANSI/ANS 3.1-1978 is not approved by the NRC for Fitzpatrick, Palisades, Pilgrim and Vermont Yankee. Entergys current submittal does not provide an evaluation of this standard and reasons for change.
Please provide an evaluation on the acceptability of a quality assurance alternative that deviates from the earlier NRC approved N18.1 -1971 standard.
1.0.6 Entergys QAPM, Revision 21, Table 1, Regulatory Commitments states that Entergy is committed to Regulatory Guide 1.8, Revision 1, dated 1975. The QAPM, Revision 21, Clarifications/Exception section states, Qualification requirements for personnel, other than Licensed Operators covered under 10 CFR 55, shall meet ANSI/ANS 3.1 1978 except for positions where an exception to either ANSI/ANS 3.1-1978 or N18.1 -1971 is stated in the applicable units Technical Specifications. If an exception exists for a given position, the applicable units Technical Specification qualification requirements shall apply. Entergy is proposing to change the QAPM to the following:
Entergy is committed to Sections 1 - 4 of ANSI/ANS 3.1-1978 with following clarifications and exceptions.
Qualification requirements for personnel shall meet ANSI/ANS 3.1-1978 except the following:
- a. The radiation protection manager shall meet or exceed the qualifications of Regulatory Guide 1.8, Revision 2, 1987.
- b. Managers required to hold an SRO license are specified in the applicable unit's Technical Specifications.
- c. Licensed Operators shall be qualified in accordance with the requirements of 10 CFR 55.
10 CFR 50.120 provides for a system approach to training in accordance with 10 CFR 55.4.
The requirements are for a non-licensed operator, shift supervisor, shift technical advisor, instrument and control technician, electrical maintenance personnel, mechanical maintenance personnel, radiological protection technician, chemistry technician, engineering support personnel. Please provide clarification on how Entergys QAPM will address training for managers, supervisors, and general personnel.