March 11,2021 Pilgrim Request for Additional Information Response Clarifiction Meeting - Proposed Physical Security Plan
ML21075A315
Person / Time
Site: Pilgrim
Issue date: 03/17/2021
From: Amy Snyder
Reactor Decommissioning Branch
To:
Holtec Decommissioning International
Snyder A
References
EPID L-2020-LLA-0230
Download: ML21075A315 (4)


Text

March 17, 2021 LICENSEE: Holtec Decommissioning International, LLC FACILITY: Pilgrim Nuclear Power Station

SUBJECT:

SUMMARY

OF MARCH 11, 2021, CLOSED MEETING WITH HOLTEC DECOMMISSIONING INTERNATIONAL, LLC, REQUEST FOR ADDITIONAL INFORMATION RESPONSE CLARIFICATION MEETING REGARDING PROPOSED PHYSICAL SECURITY PLAN CHANGE FOR THE PILGRIM NUCLEAR POWER STATION - ALTERNATIVE MEASURES (L-2020-LLA-0230)

The U.S. Nuclear Regulatory Commission (NRC) conducted a closed meeting with representatives of Holtec Decommissioning International, LLC (HDI) on March 11, 2021. The purpose of the meeting was a clarification teleconference to ensure NRC staff understands the certain request for additional information (RAI) responses (non-public) that were submitted on February 25, 2021 (Agencywide Document Access and Management System

[ADAMS] Accession No. ML21063A104) for the Pilgrim Nuclear Power Station (Pilgrim) physical security plan amendment application - alternative measures.

The meeting began with opening remarks by the NRC staff, followed by introductions of the attendees. A list of attendees is enclosed.

The NRC staff reviewed three RAI responses to ensure understanding related to one responders response time-line, the use of a particular physical barrier, and the use of a personnel barrier. The discussion of the RAI responses involved official use only - security related information (OUO-SRI) that is not made publicly available. HDI explained that it plans on submitting the RAI response clarifying information for each RAI response discussed on or about March 17, 2021.

The submittals will contain OUO-SRI and therefore will be sent via either overnight mail or via the secure NRC BOX for sensitive information.

The NRC staff informed HDI that given the nature and the level of detail expected in the RAI response clarifying information, the NRC staff believes that it will be able to develop the rest of the NRC review reschedule the week of March 15.

At this meeting, the NRC staff made no regulatory decisions regarding the merits of the proposed physical security plan change at Pilgrim.

Please direct any inquiries to me at (301) 415-6822 or Amy.Snyder@nrc.gov.

Amy M. Digitally signed by Amy M. Snyder Snyder Date: 2021.03.22 13:33:32 -04'00' Amy M. Snyder, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Reactor Regulation Docket No. 50-293

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES MARCH 11, 2021 CLOSED MEETING WITH HOLTEC DECOMMISSIONING INTERNATIONAL, LLC CLARIFICATION MEETING ON FEBRUARY 25, 2021 REQUEST FOR ADDITIONAL INFORMATION RESPONSES A PROPOSED REVISION TO THE PHYSICAL SECURITY PLAN - ALTERNATIVE MEASURES PILGRIM NUCLEAR POWER STATION Name Affiliation Amy Snyder U.S Nuclear Regulatory Commission (NRC)

Vince Williams NRC Matthew Tonanek NRC Contractor, U.S. Army Corps of Engineers Brian McWilliams Holtec Decommissioning International, LLC (HDI, Holtec, or Licensee)

David Burke HDI Joseph Dwyer HDI Kevin Traver Comprehensive Decommissioning International (CDI)

Steven Harmon CDI J. Scott Thomson HDI Andrea Sterdis HDI Enclosure

ML21075A315 *via email OFFICE RBD/PM NSIR/DPCP/MSB/BC RDB/BC RBD/PM NAME ASnyder ARivera BWatson ASnyder DATE 3/16/2021 03/17/2021 03/17/2021 03/17/2021