Advises That Fire Protection & Alternate Shutdown Sys Mods Required to Meet 10CFR50.48 Scheduled to Be Completed by End of Sixth Refueling Outage,Per Generic Ltr 86-10, Implementation of Fire Protection Requirements
ML20206M021
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/09/1987
From: Miraglia F
Office of Nuclear Reactor Regulation
To: Shelton D
TOLEDO EDISON CO.
References
GL-86-10, TAC-52156, NUDOCS 8704170372
Download: ML20206M021 (2)


Text

<

L7 Docket No. 50-346 April 9,1987 \/ ()

Mr. Donald Shelton Vice President, Nuclear Toledo Edison Company Edison Plaza - Stop 712

. 300 Madison Avenue Toledo, Ohio 4365?

Dear Mr. Shelton:

SUBJECT:

IMPLEMENTATION SCHEDULE FOR 10 CFR 50.48; FIRE PROTECTION Generic letter 86-10 " Implementation of Fire Protection Requirements" stated that the NRC would review the dockets of plants covered by 50.48 to determine the schedule deadlines for those plants and confirm those deadlines with the licensees.

We have reviewed the docket for information related to the schedule for implementation of 10 CFR 50.48 for the Davis-Besse Nuclear Power Station.

Based on that review, we have determined that the fire protection and alternate shutdown system modifications required to meet the regulations are scheduled by Toledo Edison Company to be completed by the end of the sixth refueling outage. This is expected to occur by late sumer of 1989. Although the modifications have not been completed consistent with the schedule requirements of 10 CFR 50.48, continued operation of the plant has been allowed because of your compensatory measures which have been approved by the NRC.

If the schedule identified above is not correct, please contact your NRC Project Manager not later than May 15, 1987. You should notify the NRC Project Manager when the required modifications to bring the plant into compliance with the regulation have been completed. Furthermore, if ~a schedule delay develops you should notify the NRC Project Manager.

These notifications should be in writing.

Sincerely Original signed by Frank J. Miraglia

. Frank J. Miraglia, Director Division of PWR Licensing-B cc: See next page Distribution:

Docket File NRC & LPDRs Branch Files ADeAgazio i Ringram ACRS I OGC EJordan 3 -JPartlow BGrimes PWR#6 PWR#6 Ph D ADeAgazio GEdison FM ia l JStg /87 y /pB7 V/p/87 /) p /87 l g41703728704o9 p ADOCK 05000346 l PDR

.. - j l

Mr. J. Williams Davis-Besse Nuclear Power Station '

Toledo Edison Company Unit No. 1 cc:

Donald H. Hauser, Esq.

The Cleveland Electric Radiological Health Program Illuminating Company Ohio Department of Health P. O. Box 5000 I??d Kinnear Road Cleveland, Ohio 44101 Columbus, Ohio 43212 Mr. Robert F. Peters Attorney General Manager, Nuclear Licensing Department of Attorney Toledo Edison Company General Edison Plaza 30 East Broad Street 300 Madison Avenue Columbus, Ohio 43215 Toledo, Ohio 43652 Mr. James W. Harris, Director Gerald Charnoff, Esq. (Addressee Only)

Shaw, Pittman, Potts Division of Power Generation and Trowbridge Ohio Department of Industrial Relations P300 N Street N.W. 2323 West 5th Avenue Washington, D.C. 20037 P. O. Box 825 Columbus, Ohio 43216 Mr. Paul M. Smart, President Ohio Environmental Protection Toledo Edison Company Agency 300 Madison Avenue 361 East Broad Street Toledo, Ohio 43652 Columbus, Ohio 43P66-0558 Mr. Robert B. Borsum President, Board of Babcock & Wilcox County Commissioners of Nuclear Power Generation Ottawa County Division Port Clinton, Ohio 43452 Suite 200, 7910 Woodmont Avenue Bethesda, Maryland 20814 State of Ohio Public Utilities Commission Resident Inspector 180 East Broad Street U.S. Nuclear Regulatory Commission Columbus, Ohio 43266-0573 5503 N. State Route 2 Oak Harbor, Ohio 43449 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137