MONTHYEARML20217P2061999-10-26026 October 1999 Forwards for First Energy Nuclear Operating Co Insp Rept 50-346/99-17 on 990928-1001.Insp Was Exam of Activities Conducted Under License Re Implementation of Physical Security Program.No Violations Identified ML20217N3851999-10-20020 October 1999 Forwards RAI Re Licensee 990521 Request for License Amend to Allow Irradiated Fuel to Be Stored in Cask Pit at Davis-Besse,Unit 1.Response Requested within 60 Days from Receipt of Ltr ML20217N2321999-10-15015 October 1999 Requests NRC Approval to Use Alternative to Requirements of 10CFR50.55a(f)(4)(ii).Licensee Requests Extension to Specified Schedule for Implementing Updates to IST Program PY-CEI-NRR-2438, Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl1999-10-14014 October 1999 Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl ML20217G9201999-10-14014 October 1999 Discusses Utils Request for Approval of Quality Assurance Program Changes ML20217F3901999-10-14014 October 1999 Discusses Request That Proprietary Document NEDE-32907P,DRF A22-0084-53, Safety Analysis Rept for Perry NPP 5% Power Uprate, Class III Dtd Sept 1999 Be Withheld.Determined Document Proprietary & Will Be Withheld PY-CEI-NRR-2435, Responds to NRC Re Violations Noted in Insp Rept 50-440/99-13.Corrective Actions:Ts SRs with Incorrect Descriptions Were Annotated to Ensure That CR Operators Are Aware That ACs Are Effect1999-10-13013 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-440/99-13.Corrective Actions:Ts SRs with Incorrect Descriptions Were Annotated to Ensure That CR Operators Are Aware That ACs Are Effect ML20217F8371999-10-0808 October 1999 Forwards Insp Rept 50-346/99-10 on 990802-0913.One Violation Occurred Being Treated as NCV ML20217A5641999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Davis-Besse on 990901.Informs That NRC Plans to Conduct Addl Insps to Address Questions Raised by Issues Re Operator Errors & Failure to Commit to JOG Topical Rept on MOV Verification ML20212J1451999-09-30030 September 1999 Forwards Order,In Response to 990505 Application PY-CEI/NRR- 2394L.Order Approves Conforming License Amend Which Will Be Issued & Made Effective When Transfer Completed ML20212L0691999-09-30030 September 1999 Forwards,For Review & Comment,Copy of Preliminary ASP Analysis of Operational Condition Discovered at Unit 1 on 981014,as Reported in LER 346/98-011 ML20212K9271999-09-30030 September 1999 Refers to 990927 Meeting Conducted at Perry Nuclear Power Plant to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff ML20217E7111999-09-30030 September 1999 Documents Telcon Conducted on 990929 Between M Underwood of Oh EPA & D Tizzan of Pnpp,Re Request to Operate Pnpp Sws,As Is,Until Resolution Can Be Obtained ML20216J6701999-09-24024 September 1999 Forwards Post Examination Documentation for Written Operator Initial License Examination Administered at Davis-Besse Nuclear Power Station on 990920.Without Encls ML20212G4161999-09-24024 September 1999 Informs of Completion of Licensing Action for Generic Ltr 98-01, Y2K Readiness of Computer Systems at Nuclear Power Plants, for Perry Nuclear Power Plant ML20212G5811999-09-23023 September 1999 Informs That Licenses for Ta Lentz,License SOP-31449,PJ Arthur,License SOP-30921-1 & Dp Mott,License SOP-31500 Are Considered to Have Expired,Iaw 10CFR50.74(a),10CFR55.5 & 10CFR55.55 ML20212D3501999-09-21021 September 1999 Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006 PY-CEI-NRR-2432, Forwards NRC Form 536, Operator Licensing Exam Data, in Response to Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams1999-09-21021 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, in Response to Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams PY-CEI-NRR-2428, Submits Resolution to Seventh Question Proposed within NRC 980615 RAI Relating to Cooling Water Sys That Serve Containment Air Coolers & Assessment,Post Accident,Of Potential Water Hammer & two-phase Flow Conditions1999-09-16016 September 1999 Submits Resolution to Seventh Question Proposed within NRC 980615 RAI Relating to Cooling Water Sys That Serve Containment Air Coolers & Assessment,Post Accident,Of Potential Water Hammer & two-phase Flow Conditions ML20212D0151999-09-14014 September 1999 Requests Cancellation of NPDES Permit 3II00036.Permit Has Been Incorporated in Permit 3IB00016*ED.Discharge Point Sources & Associated Fees Currently Covered Under Permit 3IB00016*ED ML20212A8371999-09-13013 September 1999 Forwards Insp Rept 50-440/99-13 on 990712-30 & Notice of Violation.Insp Included Evaluation of Engineering Support, Design Change & Modification Activities,Internal Assessment Activities & Corrective Actions 05000346/LER-1998-001, Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached1999-09-0909 September 1999 Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached ML20217A8971999-09-0909 September 1999 Forwards Insp Rept 50-440/99-09 on 990709-0825.One Violation of NRC Requirements Occurred & Being Treated as NCV, Consistent with App C of Enforcement Policy PY-CEI-NRR-2431, Forwards Revised Emergency Plan for Perry NPP, IAW 10CFR50.54(q).Changes Constitute Revs,Temporary Changes or Reissued Pages1999-09-0909 September 1999 Forwards Revised Emergency Plan for Perry NPP, IAW 10CFR50.54(q).Changes Constitute Revs,Temporary Changes or Reissued Pages ML20211P3001999-09-0707 September 1999 Forwards FEMA Transmitting FEMA Evaluation Rept for 990504 Emergency Preparedness Exercise at Davis-Besse Nuclear Power Plant.No Deficiencies Identified.One Area Requiring C/A & Two Planning Issues Identified ML20216E5961999-09-0707 September 1999 Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation ML20211Q6911999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Perry Operator License Applicants During Wks of 010108 & 15.Validation of Exam Will Occur at Station During Wk of 001218 IR 05000440/19990011999-08-31031 August 1999 Requests That Page Number 4, P2 Status of EP Facilities, Equipment & Resources, of Insp Rept 50-440/99-01 Be Replaced with Encl Rev ML20211K6681999-08-30030 August 1999 Forwards Copies of Certified Personal Qualification Statement - Licensee (NRC Form 398) for Operator Candidates Listed Below.Without Encls ML20211K6611999-08-30030 August 1999 Forwards Copies of Operator License Renewal Applications for Individuals Listed.Operators Have Successfully Completed Appropriate Operator Requalification Training Program at Dbnps.Without Encls ML20211K0951999-08-30030 August 1999 Forwards Request for Addl Info Re Fire & Seismic Analyses of IPEEE for Davis-Besse Nuclear Power Station,Unit 1. Response Requested within 60 Days PY-CEI-NRR-2425, Forwards Copy of Oh EPA Approval for Use of Nalco 7348 & Nalco 7468 at Pnpp,Iaw License NPF-58,App B,Epp,Section 3.21999-08-26026 August 1999 Forwards Copy of Oh EPA Approval for Use of Nalco 7348 & Nalco 7468 at Pnpp,Iaw License NPF-58,App B,Epp,Section 3.2 ML20211H0201999-08-25025 August 1999 Forwards semi-annual FFD Rept for 990101-0630 for DBNPS, Unit 1,IAW 10CFR26.71(d) ML20211G3911999-08-20020 August 1999 Forwards Update to Estimated Info for Licensing Action Requests Through 010930,re Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates ML20211D1171999-08-20020 August 1999 Forwards Insp Rept 50-346/99-09 on 990623-0802.Violations Identified & Being Treated as Noncited Violations PY-CEI-NRR-2411, Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl1999-08-19019 August 1999 Informs That Firstenergy Nuclear Operating Co Has Developed Corporate QA Program Manual for Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant,As Discussed on 990318 Between Util & Nrc.Revised USAR Pages,Encl ML20210Q8421999-08-13013 August 1999 First Final Response to FOIA Request for Documents.Records Listed in App a Being Released in Entirety & Records Listed in App B Being Withheld in Part (Ref FOIA Exempt 5) ML20211B0161999-08-13013 August 1999 Forwards SE Accepting Evaluation of Second 10-year Interval Inservice Insp Program Request for Relief Numbers RR-A16, RR-A17 & RR-B9 for Plant,Unit 1 ML20211J9201999-08-13013 August 1999 Urges NRC to Find Funds for Stockpiling Radiation Pills for Residents Living Near Plant ML20210R7861999-08-12012 August 1999 Forwards Insp Rept 50-440/99-12 on 990712-16.No Violations Noted.New Emergency Preparedness Program Staff & Mgt Personnel Were Professional & Proactive ML20210T1061999-08-12012 August 1999 Forwards Preliminary NRC Forms 398 & 396 for Listed Candidates,Per Operator License Exam Scheduled for Week of 990913.Encl Withheld ML20210S6071999-08-11011 August 1999 Provides Final Response to NRC RAI Re GL 98-01, Y2K Readiness of Computer Systems at Npps ML20210S3961999-08-11011 August 1999 Requests That Ten Listed Individuals Be Registered to Take 991006 BWR Gfes of Written Operating Licensing Exam.Two Listed Personnel Will Have Access to Exams Before Exams Are Administered ML20210Q7981999-08-10010 August 1999 Informs That Intention to Utilize Sulfuric Acid in Pnpp Circulating Water Sys to Lower Ph Is Anticipated to Be Completed in Nov ML20210Q5831999-08-10010 August 1999 Requests Permission to Chemically Treat CWS for Algae Due to Cooling Water Basin Becoming Infected with Algae of Various Types PY-CEI-NRR-2421, Forwards Semiannual fitness-for-duty Rept,Iaw 10CFR26.71(d) for Pnpp Covering Period of 990101-9906301999-08-10010 August 1999 Forwards Semiannual fitness-for-duty Rept,Iaw 10CFR26.71(d) for Pnpp Covering Period of 990101-990630 PY-CEI-NRR-2422, Forwards Addl Info Re ASME Section IX Relief Request (IR-023) for Inservice Examination Program at Pnpp,Submitted on 9808261999-08-10010 August 1999 Forwards Addl Info Re ASME Section IX Relief Request (IR-023) for Inservice Examination Program at Pnpp,Submitted on 980826 PY-CEI-NRR-2423, Provides Final Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Npps. Remediation of Meteorological Monitoring Sys Has Been Completed & Ppnp Facility Is Now Y2K Ready1999-08-10010 August 1999 Provides Final Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Npps. Remediation of Meteorological Monitoring Sys Has Been Completed & Ppnp Facility Is Now Y2K Ready ML20210P8051999-08-0909 August 1999 Forwards Insp Rept 50-346/99-15 on 990712-16.No Violations Noted.However,Several Deficiencies Were Identified with Implementation of Remp,Which Collectively Indicated Need for Improved Oversight of Program 05000346/LER-1998-009, Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl1999-08-0606 August 1999 Forwards LER 98-009-01,IAW 10CFR50.73(a)(2)(ii)(B). Commitments Made by Util Are Encl 1999-09-09
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217P2061999-10-26026 October 1999 Forwards for First Energy Nuclear Operating Co Insp Rept 50-346/99-17 on 990928-1001.Insp Was Exam of Activities Conducted Under License Re Implementation of Physical Security Program.No Violations Identified ML20217N3851999-10-20020 October 1999 Forwards RAI Re Licensee 990521 Request for License Amend to Allow Irradiated Fuel to Be Stored in Cask Pit at Davis-Besse,Unit 1.Response Requested within 60 Days from Receipt of Ltr ML20217F3901999-10-14014 October 1999 Discusses Request That Proprietary Document NEDE-32907P,DRF A22-0084-53, Safety Analysis Rept for Perry NPP 5% Power Uprate, Class III Dtd Sept 1999 Be Withheld.Determined Document Proprietary & Will Be Withheld ML20217G9201999-10-14014 October 1999 Discusses Utils Request for Approval of Quality Assurance Program Changes ML20217F8371999-10-0808 October 1999 Forwards Insp Rept 50-346/99-10 on 990802-0913.One Violation Occurred Being Treated as NCV ML20212L0691999-09-30030 September 1999 Forwards,For Review & Comment,Copy of Preliminary ASP Analysis of Operational Condition Discovered at Unit 1 on 981014,as Reported in LER 346/98-011 ML20212K9271999-09-30030 September 1999 Refers to 990927 Meeting Conducted at Perry Nuclear Power Plant to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff ML20212J1451999-09-30030 September 1999 Forwards Order,In Response to 990505 Application PY-CEI/NRR- 2394L.Order Approves Conforming License Amend Which Will Be Issued & Made Effective When Transfer Completed ML20217A5641999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Davis-Besse on 990901.Informs That NRC Plans to Conduct Addl Insps to Address Questions Raised by Issues Re Operator Errors & Failure to Commit to JOG Topical Rept on MOV Verification ML20212G4161999-09-24024 September 1999 Informs of Completion of Licensing Action for Generic Ltr 98-01, Y2K Readiness of Computer Systems at Nuclear Power Plants, for Perry Nuclear Power Plant ML20212D3501999-09-21021 September 1999 Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006 ML20212A8371999-09-13013 September 1999 Forwards Insp Rept 50-440/99-13 on 990712-30 & Notice of Violation.Insp Included Evaluation of Engineering Support, Design Change & Modification Activities,Internal Assessment Activities & Corrective Actions ML20217A8971999-09-0909 September 1999 Forwards Insp Rept 50-440/99-09 on 990709-0825.One Violation of NRC Requirements Occurred & Being Treated as NCV, Consistent with App C of Enforcement Policy ML20211P3001999-09-0707 September 1999 Forwards FEMA Transmitting FEMA Evaluation Rept for 990504 Emergency Preparedness Exercise at Davis-Besse Nuclear Power Plant.No Deficiencies Identified.One Area Requiring C/A & Two Planning Issues Identified ML20211Q6911999-09-0606 September 1999 Informs That NRC Tentatively Scheduled Initial Licensing Exam for Perry Operator License Applicants During Wks of 010108 & 15.Validation of Exam Will Occur at Station During Wk of 001218 IR 05000440/19990011999-08-31031 August 1999 Requests That Page Number 4, P2 Status of EP Facilities, Equipment & Resources, of Insp Rept 50-440/99-01 Be Replaced with Encl Rev ML20211K0951999-08-30030 August 1999 Forwards Request for Addl Info Re Fire & Seismic Analyses of IPEEE for Davis-Besse Nuclear Power Station,Unit 1. Response Requested within 60 Days ML20211D1171999-08-20020 August 1999 Forwards Insp Rept 50-346/99-09 on 990623-0802.Violations Identified & Being Treated as Noncited Violations ML20210Q8421999-08-13013 August 1999 First Final Response to FOIA Request for Documents.Records Listed in App a Being Released in Entirety & Records Listed in App B Being Withheld in Part (Ref FOIA Exempt 5) ML20211B0161999-08-13013 August 1999 Forwards SE Accepting Evaluation of Second 10-year Interval Inservice Insp Program Request for Relief Numbers RR-A16, RR-A17 & RR-B9 for Plant,Unit 1 ML20210R7861999-08-12012 August 1999 Forwards Insp Rept 50-440/99-12 on 990712-16.No Violations Noted.New Emergency Preparedness Program Staff & Mgt Personnel Were Professional & Proactive ML20210P8051999-08-0909 August 1999 Forwards Insp Rept 50-346/99-15 on 990712-16.No Violations Noted.However,Several Deficiencies Were Identified with Implementation of Remp,Which Collectively Indicated Need for Improved Oversight of Program IR 05000346/19980211999-08-0606 August 1999 Refers to NRC Insp Rept 50-346/98-21 Conducted on 980901- 990513 & Forwards Nov.Two Violations Identified Involving Failure to Maintain Design of Valve & Inadequate C/A for Degraded Condition Cited in Encl NOV ML20210K6331999-08-0404 August 1999 Submits Response to Requests for Addl Info to GL 92-01,Rev 1, Reactor Vessel Structural Integrity, for Perry Nuclear Plant,Unit 1 ML20210H6101999-07-30030 July 1999 Informs That Region III Received Rev 21 to Various Portions of Davis-Besse Nuclear Power Station Emergency Plan.Revision Was Submitted Under Provisions of 10CFR50.54(q) in Apr 1999 ML20210G8411999-07-28028 July 1999 Informs That Based on Determination That Rev 14 Changes to Various Portions of Perry Nuclear Power Plant Emergency Plan Does Not Decrease Effectiveness of Licensee Emergency Plan & Meets Standard of 10CFR50.47(b),no NRC Approval Required ML20210E0661999-07-22022 July 1999 Forwards Insp Rept 50-440/99-08 on 990518-0708.No Violations Noted.Overall Conduct of Activities at Perry Facility, Conservative & Professional with Continuing Focus on Safety ML20210C4381999-07-20020 July 1999 Forwards Insp Rept 50-346/99-08 on 990513-0622.Unidentified RCS Leak Approached TS Limit of 1 Gallon Per Minute Prior to Recently Completed Maint Outage.Three Violations of NRC Requirements Identified & Being Treated as NCVs ML20209G3681999-07-15015 July 1999 Advises That Info Submitted in & 990519 Affidavit Re Design & Licensing Rept,Davis-Besse,Unit 1 Cask Pit Rack Installation Project,Holtec Intl, HI-981933,marked Proprietary,Will Be Withheld from Public Disclosure ML20209E5951999-07-0909 July 1999 Ltr Contract:Task Order 46, Perry Engineering & Technical Support (E&Ts) Insp, Under Contract NRC-03-98-021 ML20207H6401999-07-0909 July 1999 Discusses Closure of TAC MA0540 Re Util Responses to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Staff Has Revised Info in Rvid & Releasing It as Rvid Version 2 ML20209D1341999-07-0808 July 1999 Forwards Notice of Withdrawal of Application for Amend to Operating License.Proposed Change Would Have Modified Facility TSs Pertaining to Allowable as-found Pressure Lift Setting Tolerance of Two Pressurizer Code Safety Valves ML20209D5931999-07-0101 July 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Investigation Rept 3-98-005 Issued on 990510.Corrective Actions Will Be Examined During Future Inspections ML20196H9641999-06-29029 June 1999 Confirms 990615 Telcon Request with J Lieberman for Addl Time to Respond to Enforcement Action 99-012.FirstEnergy Has 60 Days to Respond to EA ML20195K2751999-06-16016 June 1999 Forwards Safety Evaluation Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20195G6741999-06-10010 June 1999 Forwards Insp Rept 50-440/99-03 on 990407-0517.Two Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20207G3921999-06-0808 June 1999 Forwards Notice of Consideration of Approval of Transfer of License DPR-58 & Issuance of Conforming Amend & Opportunity for Hearing Re 990505 Application ML20207G0751999-06-0707 June 1999 Forwards Insp Rept 50-346/99-04 on 990323-0513.Violations Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20207G0621999-06-0404 June 1999 Forwards Insp Rept 50-346/98-21 on 980901-1201 & 990425-0513.Violations Identified & Licensee Being Provided Opportunity to Either Respond to Violations within 30 Days or Inform NRC That LER Rept Already Contain Info Requested ML20207B7341999-05-26026 May 1999 Forwards Correction of Typo in TS Table 3.3.6.1-1 for Plant, Unit 1 ML20207B8161999-05-25025 May 1999 Confirms Discussion Between Members of Staffs to Have Mgt Meeting on 990608 in Oak Harbor,Oh to Discuss Recent Performance at Davis-Besse as Described in Plant Performance Review ML20207B3141999-05-24024 May 1999 Informs That in September 1998,Region III Received Revision 20 to Various Portions of Davis-Besse Nuclear Power Station Emergency Plan.Rev Submitted Under Provisions of 10CFR50.54(q) ML20207B1251999-05-20020 May 1999 Discusses Investigation Rept 3-98-007 on 981210 & Forwards Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $110,000 DD-99-08, Informs That to Extent That Union of Concerned Scientists Requests Commission Undertake Formal Review of DD-99-08 & Hold Meeting to Directly Receive View on Decision,Request Denied.With Certificate of Svc.Served on 9905211999-05-20020 May 1999 Informs That to Extent That Union of Concerned Scientists Requests Commission Undertake Formal Review of DD-99-08 & Hold Meeting to Directly Receive View on Decision,Request Denied.With Certificate of Svc.Served on 990521 ML20206T0881999-05-18018 May 1999 Confirms 990517 Telcon Between Lindsey & M Bielby Re Arrangements Made for Administration of Licensing Exam at Facility for Week of 990913 ML20206Q5181999-05-14014 May 1999 Responds to to SL Hiatt Re Fee Exemption Granted to Firstenergy Nuclear Operating Co,Operator of Perry Nuclear Plant.Action Consistent with Longstanding Policy & Practice,As Well as Legal Requirements IR 05000440/19980181999-05-14014 May 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-440/98-18 on 981110 ML20196F8081999-05-12012 May 1999 Partially Deleted Ltr Referring to Investigation Case 3-1998-007 Re Determination Whether Recipient Discriminated Against Radiation Protection Supervisor at Perry for Providing Testimony as Witness in DOL Hearing ML20206Q0171999-05-12012 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization, Division of Licensing Project Management Created ML20206S5381999-05-12012 May 1999 Forwards Insp Rept 50-440/99-07 on 990412-16.No Violations Noted.Insp Consisted of Selective Exam of Procedures & Representative Records,Interviews with Personnel & Observation of Activities in Progress 1999-09-09
[Table view] |
Text
-
_, October 14, 1999 John P. Stetz President '
\
FirstEnergy Nuclear Operating Company'.
76 South Main Street
' Akron, Ohio 44308
/
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION AND PERRY NUCLEAR POWER PLANT- REQUEST FOR APPROVAL OF QUALITY ASSURANCE PROGRAM CHANGES (TAC NOS. MA6323 AND MA6314)
Dear Mr. Stetz:
As described in your letter dated August 19,1999 (PY-CEl/NRR-2411L), FirstEnergy Nuclear s Operating Company (FENOC) has developed a corporate Quality Assurance Program Manual (QAPM) for its two nuclear facilities, the Davis-Besse Nuclear Power Station (DBNPS) and the Perry Nuclear Power Plant (PNPP). A comparison of the FENOC QAPM with each facility's docketed Quality Assurance Program identified changes that represent a reduction in commitment from the Quality Assurance Program descriptions previously approved by the NRC. Therefore, pursuant to 10 CF R 50.54(a), your letter submitted these changes for NRC review and approval.
Areas of concem resulting frms our review have been discussed with your staff. As a result, your letter of October 14, *Z9 (PY-CEl/NRR-2438L) addressed our concerns. Based on our need to review this add %nal inforrnation, we are unable, at this time, to make a determination regarding the accepbd.iity of the proposed changes pursuant to 10 CFR 50.54(a). Therefore, you should refrain from implementing these changes until you have been formally notified otherwise. We anticipate completing our review and issuing our findings shortly.
l Should you have any questions, please contact me at (301) 415-1364.
Sincerely, Original Signed By Douglas V. Pickett, Senior Project Manager, Section 2 Project Directorate lli Division of Licensing Project Management l Office of Nuclear Reactor Regulation O l Docket Nos. 50-346 and 50-440 cc: See next page h
DISTRIBUTION:
Docket File TQuay ACRS
!!hhh h hhhh G' pp h PUBLIC DDorman MBugg PDill-2 r/f OGC TKozak, Rill DOCUMENT NANIE: G:\PDill-2\ PERRY \FENOC RAI LETER (TAC NO. MA6323 AND MA6314).WPD To RECElVE A COPY OF THIS DOCUMENT, INDICATE IN THE BOX: "C" = COPY WITHOuT ENCLOSURES "E" = COPY WITH ENCLOSURES "N" OFFICE LA:LPD3-2 C PM:LPD3-g C PM:LPD3-2 C SC:LPD3-2 occe%
NAME Dih DPickitt SBaileydllh AM(nk,t r quw N l DATE 10/ ldM 10/ b /99 ' 10/ / y /99 10h /l[/99 ] O// '//'/9 OFFICIALyCORD COPY 9910220013 991014 PDR ADOCK 05000346 P PDR
,- Mr. John P. Stetz D.wis-Besse Nucle r Power St: tion, Unit 1 FirstEnergy Nucle:r Operating C:mpany
, ;A cc:
Mary E. O'Reilly Robert E. Owen, Chief FirstEnergy . Bureau of Radiological Health 76 South Main Street Service Akron, OH 44308 - Ohio Department of Health P.O. Box 118 James L. Freels Columbus, OH 43266-0118 Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company James R. Williams, Executive Director Davis-Besse Nuclear Power Station Ohio Emergency Management Agency 5501 North State - Route 2 2855 West Dublin Granville Road Oak Harbor, OH 43449-9760 Columbus, OH 43235-2206 Jay E. Silberg, Esq. Director Shaw, Pittman, Potts Ohio Department of Commerce and Trowbridge Division of Industrial Compliance 2300 N Street, NW. Bureau of Operations & Maintenance Washington, DC 20037 6606 Tussing Road P.O. Box 4009 Regional Administrator Reynoldsburg, OH 43068-9009 U.S. Nuclear Regulatory Commission 801 Warrenville Road Ohio Environmental Protection Agency Lisle, IL 60523-4351 DERR--Compliance Unit ATTN;' Zack A. Clayton Michael A. Schoppman P.O. Box 1049 Framatome Technologies Incorporated Columbus, OH 43266-0149 1700 Rockville Pike, Suite 525 3
Rockville, MD 20852 State of Ohio '
Public Utilities Commission Resident inspector - 180 East Broad Street U.S. Nuclear Regulatory Commission Columbus, OH 43266-0573 l 5503 North State Route 2 i Oak Harbor, OH 43449-9760 Attomey General Department of Attomey !
James H. Lash, Plant Manager 30 East Broad Street !
FirstEnergy Nuclear Operating Company Columbus, OH 43216 )
Davis-Besse Nuclear Power Station 5501 North State Route 2 President, Board of County Oak Harbor, OH 43449-9760 Commissioners of Ottawa County Port Clinton, OH 43252 Guy G. Campbell, Vice President - Nuclear FirstEnergy Nuclear Operating Company 5501 North State Route 2 Oak Harbor, Ohio 43449-9760 L _-
' Mr. J;hn P. Stetz Pcrry Nucle:r Power PI:nt, Units 1 cnd 2 FirstEnergy Nucle:r Operating Comp:ny
- h. cc-Mayor, Village of Perry Mary E. O'Reilly P.O. Box 100 FirstEnergy Corporation Perry, OH 44081-0100 76 South Main St.
Akron, OH 44308 Radiological Health Program Ohio Department of Health Resident inspector's Omce P.O. Box 118 U S. Nuclear Regulatory Commission Columbus, OH 43266-0118 P.O. Box 331 Periy, OH 44061-0331 Ohio Environmental Protection Agency Regional Administrator, Region lli DERR-Compliance Unit U.S. Nuclear Regulatory Commission ATTN: Mr. Zack A. Clayton 801 Warrenville Road P.O. Box 1049 Lisle, IL 60532-4531 Columbus, OH 43266-0149 l Sue Hiatt Chairman OCRE Interim Representative Perry Township Board of Trustees 8275 Munson 3750 Center Road, Box 65 Mentor, OH 44060 Perry, OH 44081 Gregory A. Dunn State of Ohio Manager- Regulatory Affairs Public Utilities Commission FirstEnergy Nuclear Operating Company East Broad Street !
Perry Nuclear Power Plant Columbus, OH 43266-0573 I P.O. Box 97, A210 Perry, OH 44081 John K. Wood l i
Vice President - Nuclear, Perry William R. Kanda, Jr., Plant Manager FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company P.O. Box 97, A200 ,
Perry Nuclear Power Plant Perry, OH 44081 P.O. Box 97, SB306 Perry, OH 44081 Mayor, Village of North Perry i North Perry Village Hall 4778 Lockwood Road North Perry Village, OH 44081 Donna Owens, Director Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P. O. Box 4009 Reynoldsburg, OH 43068-9009 James R. Williams Chief of Staff Ohio Emergency Management Agency _
2855 West Dublin Granville Road
. Columbus, OH 43235-7150