Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl
ML20217K109
Person / Time
Site: Davis Besse, Perry  Cleveland Electric icon.png
Issue date: 10/14/1999
From: Stetz J
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20217K112 List:
References
RTR-REGGD-01.064 2620, PY-CEI-NRR-2438, NUDOCS 9910260050
Download: ML20217K109 (3)


Text

, i

& N, FENOC

,. _ ~

Akron. ONo axe n$

QP yo.3g ggyg October 14,1999 DBNPS Serial 2620 PNPP Letter Number PY-CEl/NRR-2438L 1

United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Davis-Besse Nuclear Power Station Operating License No. NPF-3 Docket No. 50-346 n

Perry Nuclear Power Plant Operating License No. NPF-58 Docket No. 50-440

Subject:

Request for Approval of Quality Assurance Program Changes for the Davis-Besse Nuclear Power Station and the Perry Nuclear Power Plant; l Submittal of Revised Positions j Ladies and Gentlemen: l l

The FirstEnergy Nuclear Operating Company (FENOC) submitted a request for review of l changes to the Quality Assurance Programs at the Davis-Besse Nuclear Power Station  !

(DBNPS) and the Perry Nuclear Power Plant (PNPP) on August 19,1939 (DBNPS I etter l Serial 2603 and PNPP Letter Number PY-CEl/NRR-2411L). On September 30 1999 and l October 7,1999, discussions were held between the NRC staff and the licensu staffs regarding the submittal. As a result of these discussions, the DBNPS and PNPP staffs have modified or withdrawn several of the positions proposed within the August i9,1999 letter.

The revised positions for the DBNPS and the PNPP are contained in Attachments 1 and 2, respectively. There are no new commitments generated by this submittal for either the DBNPS or the PNPP (Attachments 3 and 4). 7 Q004 ' i )

1 n10013 9910260050 991014 PDR ADOCK 05000346- l P PDR 1

t T. ~

October 14,'1999 .

_. DBNPS Letter Serial 2620 PY-CEt/NRR-2438L--

Page 2 of 2 If you have questions or require additional information, please contact either-- i Mr. Jamec L. Freels, Manager - Regulatory Affairs (DBNPS), at (419) 321-8466, or - i 1 Mr. Gregory A. Dunn, Manager - Regulatory Affairs (PNPP), at (440) 280-6305.

Very truly yours, L. .

fjf Attachments cc: NRC Project Manager, Davis-Besse' Nuclear Power Station

- NRC Project Manager, Perry Nuclear Power Plant .

NRC Senior Resident inspector, Davis-Besse Nuclear Power Station NRC Senior Resident inspector, Perry Nuclear Power Plant i NRC Region Ill

. Utility Radiological Safety Board

\

i k

l I

l l

i 1k'I

"b Attachmsnt 1 DBNPS Strial Numbzr 2620 PY-CEl/NRR-2438L Page 1 of 3 Revised Quality Assurance Proaram Chanae at the Davis-Besse Nuclear Power Station (DBNPS)

This attachment presents the NRC staff's comment on the DBNPS portion of the August 19,1999 submittal, followed by the DBNPS staff's response. The DBNPS staff's response is in bold print.

Regarding DBNPS USAR Table 17.2-1, item 10, Regulatory Guide 1.64, Revision 2 (6/76) and ANSI N45.2.11-1974:

You need to change the [and] to [or) in item b.

The DBNPS staff agrees with this change. The proposed FirstEnergy Nuclear  ;

Operating Company (FENOC) Quality Assurance Program Manual (QAPM) has been revised to incorporate the recommended change. This change continues to be considered a reduction in commitment to the DBNPS Quality Assurance Program. As detailed in the August 19,1999 letter, this proposed change is acceptable because it does not diminish the effectiveness of implementing qua;ity assurance program requirements and the proposed program continues to satisfy the requireinents of 10 CFR 50, Appendix B. The revised saction of the FENOC QAPM is enclosed; refer to Pages 25 and 26, item M.1.b.