Advises That Completion Date for Implementing Rev to PWR Emergency Action Levels (EAL) Changed to 850815,per Response to Insp Repts 50-295/85-08 & 50-304/85-09.Addl Time Needed to Revise Release Rate Calculations
ML20128P223
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 06/28/1985
From: Leblond P
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
0314K, 314K, NUDOCS 8507260355
Download: ML20128P223 (1)


Text

Commonwealth Edison one First Natiorr 1 Pina, Chicigo, Illinois Address Reply to: Post Office Box 767 Chicago, Illinois 60690 June 28, 1985 i

Mr. James G. Keppler Regional Administrator U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Zion Nuclear Power Station Units 1 and 2 Response to Inspection Report Nos. 50-295/85-008 and 50-304/85-009 Reference (a): May 13, 1985 letter from D. L. Farrar to J. G. Keppler.

Dear Mr. Keppler:

The referenced letter transmitted Commonwealth Edison Company's response to Inspection Report Nos. 50-295/85-008 and 50-304/85-009. That response contained a commitment to revise the PWR EALs by July 1, 1985. It has been determined that additional time is required to complete the revised release rate calculations needed to alter the EALs. Thus, Commonwealth Edison is revising the implementation date for the new Zion EALs to August 15, 1985.

If there are any questions regarding this matter, please contact this office.

Very truly yours, f

P. C. LeBlond Nuclear Licensing Administrator 1m cc: NRC Resident Inspector - Zion 8507260355 850628 .tu

. q @5 PDR ADOCK 05000295 tm 0314K G PDR i.0 L_