Forwards Table Outlining Status of Significant Events Re PWR Reload Safety Analysis Methods for Plant Cycle 13.Requests That Transient Analysis Topical Rept Be Reviewed & SERs Issued Prior to 910830
ML20055D529
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 06/27/1990
From: Silady J
COMMONWEALTH EDISON CO.
To: Murley T
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
GL-83-11, NUDOCS 9007090059
Download: ML20055D529 (3)


Text

__

o -.

/~m

') 1400 Opus Pirce f

Commonwealth Edison

( ~

D;"m;f a Grove, Illinois 60515 m

June 27, 1990 Dr. Thomas E. Murley, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 ATTN:- Document Control Desk

Subject:

Zion Nuclear Power Station Units 1 and 2

[

PHR Reload Safety Analysis Methods EC 00.ddtLHos. 50-29 Land _1Q-303

References:

(a) Letter from C.P. Patel (NRC) to T.J. Kovach dated February 13,1990.

I (b) Letter from G.E. Trzyna (CECO) to T.E. Murley dated November 30, 1990.

(c) Letter from R.A. Chrzanowski (CECO) to T.E. Hurley dated February 27, 1990.

(d) Generic Letter 83-11 from D.G. Eisenhut to all Licensees dated February 8, 1983, " Licensee Qualification of Performing Safety Analysis in Support of Licensing Analysis "

Dr. Hurley:

As previously indicated, Commonwealth Edison (CECO) is planning to perform the Reload Safety Analysis for Zion 2 Cycle 13 (Z2C13) utilizing the methodology demonstrated in our Thermal Limit and Transient Analysis Topical t

Reports.

22Cl3 is currently scheduled to begin in Spring, 1992.

The Thermal Limit Topical Report was approved in Reference (a).

References (b) and (c) submitted proprietary and non-proprietary versions of the Transient Analysis Topical Report for NRC Staff review.

Because Z2Cl3 will be utilizing Westinghouse Vantage 5 fuel CECO will also submit a supplement to our Transient Analysis Report to address the i

effects of Vantage 5 fuel upon the Reload Design Safety Analysis by February 1, 1991.

This supplement will be more limited in scope and therefore should not significantly impact the review of the previously submitted Transient Analysis Topical Report.

I The attached table outlines the status of significant events associated with our Reload Safety Analysis Vendor Independence Program.

As l

indicated in the attachment, the issuance of an SER for the Transient Analysis i

L Topical Report (and the Vantage 5 fuel supplement) is the remaining milestone associated with our commitment to performing the Reload Safety Analysis for Zion Unit 2 Cycle 13 and subsequent PHR reloads.

887ME M L fMi P

PDC M

i Dr. T.E. Murley June 27, 1990 CECO believes that our ability to perform Reload Safety Analysis is critical in our efforts to develop and maintain excellence in the arer :f technical and engineering support for our Nuclear Stations. As noted in Reference (d), the NRC has encouraged utilities to perform such analyses and expects CECO to perform as an industry leader in this area.

It is for this reason we request that the Transient Analysis Topical Report (and Vantage S Fuel supplement) be reviewed and SER's issued prior to August 30, 1991 so that CECO may perform the Reload Safety Analysis of record for Z2C13.

Altho >gh the Reload Safety Analysis of record will be performed by CECO utilizing the methods outlined in Attachment A, it should be noted that a parallel analysis will be performed by Westinghouse for this initial cycle. A similar approach was used during the previous transition to in-house PHR reload nuclear.,esign.

To support the Staff's review, CECO suggests a meeting in August or September, 1990 to discuss our overall methodology and any questions regarding the Transient Analysis Topical Report, the planned scope of the Vantage 5 supplement, oc other related items.

This will be arranged through tb NRR Project Manager for Zion if a meeting would be beneficial for the reviewers and/or consultants.

Please dontact this office should further information be required.

Very truly yours, i

J.A. Silady Nuclear Licensing Administrator Attachment cc:

A.B. Davis - Regional Administrator, Region III C.P. Patel - Project Manager, NRR T. Boyce - Project Manager, NRR S.P. Sands - Project Manager, NNR Senior Resident Inspector - Zion Senior Resident Inspector - Byron Senior Resident Inspector - Braidwood

/1wm/ZNLD45 I

AIIACitEMI CECQ.BNLRELOMLSAEflLAMLISISN0GLREVIEW 1.

Initial Discussion with NRC of CECO

- Completed 1/86 Methodology 2.

Thermal Limit Topical Subinitted

- Completed 12/88 3.

Transient Analysis Topical Submitted

- Completed 10/89 4.

Thermal Limit Topical SER Issued

- Completed 2/90 5.

Vantage 5 Transient Analysis Topical

- 2/91 Supplement Submitted 6.

Transient Analysis Topical Report SER

- 8/91 and Vantage S Fuel Supplement SER Issued 7.

22 C13 Startup Utilizing CECO Safety

- 3/92 Analysis Methodology (current schedule) s 5

l l

/Imw/ZNLD41 1

m-e