ML20234C226

From kanterella
Revision as of 17:00, 28 February 2021 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Ack Receipt of 870821 Ltr Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-454/87-07 & 50-455/87-24.Requests That Util Provide Written Statement Describing Corrective Actions Taken Re Listed Violations
ML20234C226
Person / Time
Site: Byron  Constellation icon.png
Issue date: 09/16/1987
From: Harrison J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML20234C230 List:
References
NUDOCS 8709210209
Download: ML20234C226 (3)


See also: IR 05000454/1987007

Text

- - _ _ _ _ _ _ _ _ _ _ _ _ _

.

SEP 161987

Docket No. 50-454

Docket No. 50-455

Commonwealth Edison Company

ATTN: Mr. Cordell Reed .

3 Senior Vice President l

Post Office Box 767 l

Chicago, IL 60690 l

l

Gentlemen.

Thank you for your letter dated August 21, 1987, informing us of the steps you

have undertaken to correct the noncompliance which we brought to your

attention in our letter dated July 9,1987 regarding Commonwealth Edison's

.

Q_ ,

q- snubber reduction program at the Byron facility.

We have reviewed your responses to violation examples ic, 2b and 2d and will

'

examine these matters in a future inspection. We have also reviewed your

J responses contesting the validity of the violation examples la, Ib, 2a and 2c

and the severity levels of the two violations. At this time we do not agree

with portions of your response on the following basis:

With regard to Violation la, we do not agree with your statement that Nutech's

walkdown requirements were never less than those previously committed to at

Byron Station. The procedure revision that was being implemented through

May 1987, only addressed those rattle points near critical areas (nozzles,

branch lines and break locations) on the snubber reduction piping itself.

At that time, absolutely no consideration was given for rattle points near

critical areas on any adjacent piping systems. The flaw in the procedure

that was not recognized by Commonwealth Edison was that during original

construction, all of the rattle points near critical areas eventually would

be reviewed since all of the piping was part of the program. For the snubber

reduction program, however, a limited number of piping systems were involved

and, as a result, not all potentially affected critical areas were reviewed.

The procedure was eventually corrected by requiring all rattle points on the

snubber reduction piping to be evaluated to verify that critical areas on

'

adjacent piping systems were not adversely affected as well. This revision

was only initiated after the NRC inspector identified the above deficiency. (It

should be noted that Nutech revised its original "more extensive" walkdown

procedure under the direct guidance of Commonwealth Edison.) Although the

procedure was corrected by the inspection exit meeting, this was more a result

of direct intervention from the NRC inspectors than through initiatives by

CECO. On this basis, we have concluded that this example of the violation

remains valid.

'With regard to Violation 1b, we do not agree with your statement that seismic

anchor movements need not be considered during seismic interaction walkdowns.

$$$ $&6

.

JP

l+

- - - - - - - - - - - - - - - - - - - -

_ _ _ _ __ _ _ _ _

i

c

'

1

SEP 161997

Commonwealth Edison Company 2 I

i

I

The seismic anchor displacements that are pertinent to this discussion do not

come from the structure, as you suggest, but from the piping to which the

snubber reduction piping is attached or " anchored." This anchor movement is

the inertial movement of the piping attachment point.that is considered the i

boundary for the seismic analysis model. This movement must be' considered- )

since it is the only way to recouple two different piping analyses that were l

separated for analytical reasons. j

While it m6y be true that most of the piping has insignificant seismic anchor j

displacement, the fact is that certain snubber reduction piping systems were l

" anchored" to piping that was judged to have significant seismic movements.

The procedure as reviewed during May 1987, did not consider these inertial

movements from the attached piping. On this basis, we have concluded that

this example of the violation remains valid.

With regard to Violation 2a, we agree with your statement that there is no

requirement to explicitly address zero period acceleration. However, zero

period acceleration is a fundamental engineering principle associated with

response spectra analysis and as such can not be ignored. On this basis, we

have concluded that this example of the violation remains valid.

With regard to Violation 2c, we do not agree with your position that the 90% l

stress or insulation criteria were not utilized to resolve interferences.  !

The original version of COM-PI-BYR15, " Resolution of Rattle Point Interference

Problems" was being utilized at least until April 1987. As part of this

procedure the resolution criteria for seismic interferences utilized the

90% stress and insulation criteria. Although the final version of COM-PI-BRY21

contained an adequate approach to interference resolution, this change in

methodology was more a direct result of the NRC inspector's intervention than

a result of initiatives by CECO. On this basis, we have concluded that this l

example of the violation remains valid.  !

Since we have concluded that the above violations remain valid, we further

conclude that both violations should remain classified as Severity Level IV.

The minimal safety significance that you have assigned to these violations

may possibly be attributed to the substantial inspection effort that was

expended by the NRC during the course of the snubber reduction project. Had

the inspections not taken place until the latter stages of the project, the

significance of these violations may have been increased substantially.

Based on the above discussion, it will be necessary for you to comply with

the provisions of 10 CFR 2.201 for violation examples la, Ib, 2a and 2c and

to submit a written statement describing (1) corrective actions taken and the

results achieved; (2) corrective actions to be taken to avoid further

violations; and (3) the date when full compliance will be achieved for these ,

portions of the violations.  !

l

!

!

.

- - - _ i

,  ;

e i

g.

i  : r,

t .

I

i

SEP 161987

Coninonwealth. Edison Coinpany. 3 1

We appreciate your cooperation in t'h is matter.

'

Si nce rely , .

yjud Signed by J. J. 'liarrison -

J. J... Harrison, Chief

Engineering Branch

Enclosure: Ltr dtd 8/21/87~

l

.cc w/ enclosure:

D.~ Butterfield, Nuclear

Licensing Manager .

.

V. I.:,Schlosser,' Project' Manager

'

- Gunner Sorensen, Site Project -

Superintendent ,-

.R. E. Querio, Plant Manager. y

~DCS/RSB (RIDS).

-Licensing Fee Management Branch

Resident Inspector, RIII Byron

Resident Inspector, RIII

Braidwood

D. W. Cassel, Jr. , Esq.

.

Richard Hubbard

J. W. McCaffrey, Chief, Public

- Utilities Division

. Diane-Chavez, DAARE/ SAFE-

L. Olshan, NRR LPM

H. S. Taylor, Quality Assurance

Division

l

LO

RIII III III RII g RIII

G /lc- f_ iu (, D ison H son

. . .

]