ML20199E886

From kanterella
Jump to navigation Jump to search
Discusses Two Unresolved Security Items Identified in Sections S3.b1 & S3.b2 of Insp Repts 50-454/98-03 & 50-455/98-03,dtd 980211.One Item Re Adequacy of Alarm Sys Testing When Two Alarm Zones Were Returned to Svc
ML20199E886
Person / Time
Site: Byron  Constellation icon.png
Issue date: 01/15/1999
From: Creed J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Kingsley O
COMMONWEALTH EDISON CO.
References
50-454-98-03, 50-454-98-3, 50-455-98-03, 50-455-98-3, NUDOCS 9901210111
Download: ML20199E886 (3)


See also: IR 05000454/1998003

Text

l

.

'

,

.

!

January 15, 1999

Mr. Oliver D. Kingsley

President, Nuclear Generation Group

Commonwealth Edison Company

ATTN: Regulatory Services

Executive Towers West lll

1400 Opus Place, Suite 500

Downers Grove, IL 60515

SUBJECT:

BYRON STATION SECURITY ISSUE RESOLVED

Dear Mr. Kingsley:

Sections S3.b1 and S3.b2 of Inspection Reports No. 50-454/98003; 50-455/98003, dated

February 11,1998, identified two unresolved security items. One of the items pertained to the

adequacy of compensatory measures implemented for a section of the vehicle barrier system.

The other item pertained to the adequacy of alarm system testing when two alarm zones were

returned to service. These issues have been reviewed and resolved by the Safeguards

Branch, Division of Reactor Program Management, Office of Nuclear Reactor Regulation.

Both issues are briefly described below.

,

a.

A security officer with a contingency weapon was used to compensate for

approximately 30 feet of a degraded portion of the Vehicle Barrier System (VBS)

between December 8-21,1997. The compensatory measures were in effect to allow

fence and VBS removal for exit of the old steam generators. When discussed with

your security staff, their position was that three unanchored jersey barriers were in

position during this period and that the unanchored barriers were adequate temporary

barriers as described in Nuclear Energy Institute (NEI) Document 96-01," Guidance For

Operational Planning and Maintaining Integrity of Vehicle Barrier Systems", dated

February 1990, and therefore an armed officer was not necessary for the degraded

VBS. Both options for passive VBS barriers were allowed by the station security

procedure (Sections 5.3.2.a and b of procedure CNSG No. 4, Revision 1," Operational

Planning and Maintaining Integrity of Vehicle Barrier Systems", dated August 1996).

We were unsure if the compensatory measures implemented were adequate, although

they did comply with the station security procedure.

NRC Headquarters has concluded that the combination of compensatory measures

(armed security officer and unanchored jersey barriers) met the intent of NEl Document

96-1 and were adequate.

l

b.

10 CFR 73.55(g)(2) requires each intrusion alarm to be tested for performance at the

beginning and end of any period that it is used for security. Section 2.b of NRC

Regulatory Guide 5.44, " Perimeter intrusion Alarm Systems", which the introduction to

210002

"

9901210111 990115

!

PDR

ADOCK 05000454

l

G

PDR

!

__

__

_

.-

.

_ _

.

_ . . _ _ _ _ _ _ _ _ _

_ _ _ _ ._____

.

.

.

.

O

O. Kingsley

-2-

,

the Byron Security Plan states was used for guidance, recommends that inoperative

alarm zones be tested upon return to service against manufacturer's specifications and

detection probability to include line supervision and tamper testing. Section 13.2 of the

Byron Security Plan states an alarm zone will be " functionally tested" when placed into

service. However, only two types of alarm system testing are described in the security

plan. One of the tests is a weekly test for alarm systems in continuous use; the other

test (which includes multiple tests and tamper and line supervision testing) is for annual

testing purposes .

On December 21,1997, two alarm zones were placed back into service from an

inoperative state. A test was not performed before taking the zones out-of-service, and

1

only a single alarm test (which did not include tamper and line supervision testing) was

performed on each zone when retumed to service. This test methodology was the

same test procedure performed for alarm zones in continuous use for seven or more

days. The unresolved item was if such testing was adequate for retuming an

inoperative alarm zone back to service.

)

NRC Headquarters has concluded that the more extensive testing described above

(annual test criteria) was appropriate for inoperative alarm systems retumed to service,

and an operational test is appropriate prior to taking an alarm system out-of-service.

i

Resolution of these issues is being provided so your staff can assure adequate security

)

procedures exist for testing alarm systems prior to taking them out-of-service and upon

retuming them to service.

In accordance with 10 CFR 2.790 of the NRC's * Rules of Practice," a copy of this letter will be

l

placed in the NRC Public Document Room (PDR).

Sincerely,

Original Signed by Thomas J. Ploski (for)

James R. Creed, Chief

Plant Support Branch 1

Docket Nos.: 50-454;50-455

License Nos.: NPF-37; NPF-66

l

See Attached Distribution

DOCUMENT NAME: G:DRS\\BYR011.f9.WPD

vo r.c.~. . .. .nhi. ooeum.ne. inaient. In the bor C" a Copy wthout attachmentienclosuee

"E" a Copy wth attachment #enckmore

"N" a No copy

OFFICE

Rlll

l

Rill

6

Rlli

. .l#

.

m

,,

!

NAME

Pirtle :]p N

Jordan WM Creed 7t 47

6

'

DATE

01/ri/99

01//4199

01//f/99

.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

7,, '

O

O. Kingsley

-3-

cc:

D. Helwig, Senior Vice President

H. Stanley, PWR Vice President

C. Crane, BWR Vice President

R. Krich, Vice President, Regulatory Services

DCD - Licensing

K. Graesser, Site Vice President

W. Levis, Station Manager

B. Adams, Regulatory Assurance Manager

R. Hubbard, MHB Technical Associates

M. Aguilar, Assistant Attorney General

State Liaison Officer

State Liaison Officer, Wisconsin

Chairman, Illinois Commerce Commission

Distribution:

SAR (E-Mail)

RPC (E-Mail)

Project Mgr., NRR w/enci

J. Caldwell, Rill w/enct

C. Pederson, Rlll w/enci

B. Clayton, Rill w/enci

SRI Byron w/enci

DRP w/ encl

TSS w/ encl

DRS (2) w/enct

Rlli PRR w/enci

G

PUBLlQ4E41 w/enci [h /

Docket File w/enci

GREENS

LEO (E-Mail)

DOCDESK (E-Mail)

/

0

210003