Forwards SER Re Util 900706 Request for Relief Concerning Inservice Testing Program.Relief Granted from Testing Requirements Which Would Impose Undue Hardship If Immediate Compliance Was Imposed
ML20059L305
Person / Time
Site: Byron  Constellation icon.png
Issue date: 09/14/1990
From: Boyce T
Office of Nuclear Reactor Regulation
To: Kovach T
COMMONWEALTH EDISON CO.
Shared Package
ML20059L310 List:
References
TAC-77523, TAC-77524, NUDOCS 9009260244
Download: ML20059L305 (4)


Text

{{#Wiki_filter:_ - _= -_ . -- . . - - ~ -- -- - - - - --- - --

  .       p ,,, %                                                                         p or M F//e, f,          . ?,,                              UNITED STATES                                                    :
     -{5                   rg                NUCLEAR REGULATORY COMMISSION W ASHING T ON, D. C. 20666 j

i (*****)a September 14, 1990 I Docket Nos. STN 50-454 and STN 50-455 -

                                                                                                                        )

I Mr. Thomas J. Kovach I Nuclear Licensing Manager. l Commonwealth Edison Company Suite 300 i OPUS West III 1400 OPUS Place i Downers Grove, Illinois 60515

Dear Mr. Kovach:

SUBJECT:

INSERVICETESTING(IST)PROGRAMRELIEFRE UNITS 1 AND 2 (TAC NOS. 77523 AND 77524) QUESTS AT BYRON STATION The enclosed Safety Evaluation Report provides the results of the staff review i of the inservice testing (IST) program relief requests submitted by the i Commonwealth Edison Company for Byron Station, Units 1 and 2, in a letter dated July 6,1990. The Code of Federal Pegulations, paragraph 10 CFR 50.55a, requires certain Class 1, 2, and 3 pumps and valves in water-cooled nuclear reactor facilities to meet the inservice testing requirements stated in the ASME Boiler and i Pressure Yessel Code, Section XI; specifically, Subsection IWP, Inservice " l Testing of Pumps in Nuclear Power Plants, and Subsection IWV, Inservice Testing of Valves in Nuclear Power Plants. Each facility is required to  ! establish a program for the inservice testing of pumps and valves which is updated every ten years to meet the requirements in the latest approved edition and addenda to Section XI of the ASME Code. The IST program relief  ! requests are submitted to the NRC for review and approval. The review entails , verifying that the program is based on the applicable Code edition and

  • addenda, verifying that the program covers testing of all appropriate pumps and valves, and verifying the acceptability of the requests for relief from the 1 requirements of Subsections IWP and IWV.

The Mechanical Engineering Branch evaluated the licensee's submittal against therequirementsof10CFR50.55a,GenericLetter(GL)89-04,andtheASME . Code, Section XI. The IST program covers the first ten-year interval, from . , September 16, 1985 to September 16, 1995, for Byron Unit I and from August 21,  ! 1987 to August 21, 1997, for Byron Unit 2. Interim relief is granted from the testing requirements which we have determined would impose undue hardship j

         'if immediate compliance was imposed; current testing provides an acceptable                                 {

1evel of qualit and safety. Interim relief is granted pursuant to 10 CFR 50.55(a)y(3)(ii) to continue current testing methods while the licensee investigates the possibility of acceptable alternatives. For relief request VR-21, this relief is' granted for 6 months; for relief request VR-22, this , relief is granted for 1 year or until the next refueling outage, whichever is longer. C?2D 9009260244 900914 . DR ADOCK 050 g 4 g

Mr. Thomas J. Kovach September 14, 1990 After ex)iration of these interim reliefs, the IST Program tests for these valves sia11 be performed at their next scheduled time, as prescribed in the Byron IST program incorporating the requirements of GL 89-04 and any applicable approve,d program changes and relief requests. Sincerely, Thomas H. Boyc ProjectManager Project Directorate III-2 Division of Reactor Projects - III, IV, Y and Special Projects Office of Nuclear Reactor Regulation

Enclosure:

Safety Evaluation Report cc w/ enclosure: See next page i l l

             -     m               ,           --m               ,           m.-. ,yv s._

O' O Mr. Thomas J. Kovach -2 September 14, 1990 After ex)iration of these interim reliefs, the IST Program tests for these valves s1all be performed at their next scheduled time, as prescribed in the Byron IST program, incorporating the requirements of GL 89-04 and any applicable approved program changes and relief requests. Sincerely. Origina1 signed By: Thomas H. Boyce, Project Manager , Project Directorate 111-2 Division of Reactor Projects - Ill, IV, Y and Special Projects . Office of Nuclear Reactor Regulation +

Enclosure:

Safety Evaluation Report cc w/ enclosure: See next page DISTRIBUTION ipottetJ11e,:: a NRC & Local PDRs PDill-2 r/f DCrutchfield JZwolinski CMoore TBoyce OGC-EJordan MS MNBB 3701 ACRS(10) Plant File WShafer R111 0FFICIAL RECORD COPY 00CVMENT NAME: [KOVACH 77523/24] PDI - :LA PDIll-2:P PDl'r 6 ore TBoyce:t RBai

         /P/90           q / p(/90         7 //y/90 l

L

_ Mr. Thomas J. Kovach Byron Station Comonwealth idison Company Unit Nos. I and 2 cc: Mr. Gabe Toth Regional Administrator Westinghouse Electric Corporation U.S. Nuclear Regulatory Energy Systems Business Unit Comission Post Office Box 355 Bay 236 West 799 Roosevelt Road Bldg. d4 Pittsburgh, Pennsylvania 15230 GlenEllyn, Illinois 60137 Michael Miller,inEsq. Illinois Department of c Sidley and Aust Nuclear Safety One First National Plaza Office of Nuclear Facility Safety Chicago, Illinois 60690 1035 Outer Park Drive Springfield, Illinois, 62704 Mrs. Phillip B. Johnson Joseph Gallo Esq. 1907 Stratford Lane Hopkins and Sutter Rockford, Illinois 61107 888 16th Street, N.W. Suite 700 Ms. Lorraine Creek Rt. 1. Box 182 Douglass Cassel, Esq. Manteno, Illinois 60950 109 N. Dearborn Street Suite 1300 Mr. Edward R. Crass Chicago, Illinois 60602 Nuclear Safeguards & Licensing Sargent & Lundy Engineers Attorney General 55 East Monroe Street 500 South 2nd Street Chicago, Illinois 60603 Springfield, Illinois 62701 U. S. Nuclear Regulatory Comission Chairman Ogle County Board Byron / Resident Inspectors Office PostOffIceBox357 4448 North German Church Offices Oregon, Illinois 61061 Byron, Illinois 61010 EIS Review Coordinator Environmental Protection Agency Region V 230 S. Dearborn Street Chicago, Illinois 60604 Commonwealth Edison Company Byron Station Manager 4450 North German Church Road Byron, Illinois 61010 Robert Neumann Office of Public Counsel State of Illinois Center 100 W. Randolph Suite 11-300 Chicago, Illinois 60601}}