Forwards Insp Repts 50-321/86-21 & 50-366/86-21 on 860714-18 & Notice of Violation.W/O Notice of Violation
ML20212K279
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/06/1986
From: Brownlee V
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML20212K283 List:
References
NUDOCS 8608190361
Download: ML20212K279 (2)


See also: IR 05000321/1986021

Text

,

.4

i-

h

AUG 0 61986

Docket Nos. 50-321, 50-366

License Nos. DPR-57, NPF-5

-

eorgia Power Company -

ATTN: Mr. J. H. Miller, Jr.

President

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

SUBJECT: NOTICE OF VIOLATION

(NRC INSPECTION REPORT NOS. 50-321/86-21 AND 50-366-86-21)

This refers to the Nuclear Regulatory Commission (NRC) inspection conducted by /

J. D. Harris on July 14-18, 1986. The inspection included a review of activities /

authorized for your Hatch facility. At the conclusion of the inspection, the

findings were discussed with those members of your staff identified in the

enclosed inspection report.

Areas examined during the inspection are identified in the report. Within these

areas, the inspection consisted of selective examinations of procedures and

representative records, interviews with personnel, and observations of activities

in progress. The inspector also conducted independent measurements, in the

Region II Mobile Laboratory at your site, to verify your capability for analyzing

radioactive effluents and to establish and maintain standardized methodology

among regulated facilities and the NRC.

The inspection findings indicate'that certain activities appeared to violate NRC

requirements. The violations, references to pertinent requirements, and elements

to be included in your response are described in the enclosed Notice of

Violation.

The enclosed Inspection Report documents an oral commitment (see Paragraph 3)

made by a licensee representative and discussed in the exit interview. If your

understanding of this commitment differs from the report statements, please

inform this office promptly.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and its enclosures

will be placed in :he NRC Public Document Room.

The responses directed by this letter and its enclosure are not subject to the

clearance procedures of the Office of Management and Budget as required by the

Paperwork Reduction Act of 1980, PL 96-511.

86081903ol

DR 860806 <

ADOCK 05000321

PDR

1

TPcol m

, __ , . _ . _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ .

.

Georgia Power Company 2

Atlanta, GA

1

Should you have any questions concerning this letter, please contact us.

Sincerely,

Virgil L. Brownlee, Chief

Reactor Projects Branch 3

Division of Reactor Projects

Enclosures:

1. Notice of Violation

2. Inspection Report

jcc w/encls:

V J.,P. O'Reilly, Senior Vice President

/ Nuclear Operations

VJ. T. Beckham, Vice President and

General Manager-Nuclear Operation

C. Nix, Site General Manager

. Fraser, Acting Site QA Supervisor

L. Gucwa, Manager, Nuclear Safety

and Licensing

Accw/encls:

FRC Resident Inspector

/Hugh S. Jordan, Executive Secretary

Document Control Desk

,/ State of Georgia

b LSr

JHarris PStoddart DCollins RCroteau

j/31/86 h /86 8/ / /86 8/f/86 Alg(natonis

8/ /86

.-- -- -