ML14183A017
ML14183A017 | |
Person / Time | |
---|---|
Site: | Byron, Braidwood |
Issue date: | 07/23/2014 |
From: | Robinson L R License Renewal Projects Branch 1 |
To: | Exelon Generation Co |
Robinson L R, 415-4115 | |
References | |
TAC MF1879, TAC MF1880, TAC MF1881, TAC MF1882 | |
Download: ML14183A017 (5) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 23, 2014 LICENSEE: Exelon Generation Company, LLC FACILITY: Byron Station, Units 1 and 2 Braidwood Station, Units 1 and 2 SUBJECT: SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON JUNE 26, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 37, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF1879, MF1880, MF1881, MF1882) The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on June 26, 2014, to discuss and clarify the staff's draft request for additional information (DRAI),
Set 37, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staff's DRAIs.
Enclosure 1 provides a listing of the participants, and Enclosure 2 contains a listing of the DRAIs discussed with the applicant, including a brief description on the status of the items. The applicant had an opportunity to comment on this summary.
/RA/ Lindsay Robinson, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455, 50-456, and 50-457 Enclosures:
1. List of Participants 2. List of Draft Request for Additional Information cc w/encls: Listserv
July 23, 2014 LICENSEE: Exelon Generation Company, LLC FACILITY: Byron Station, Units 1 and 2 Braidwood Station, Units 1 and 2
SUBJECT: SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON JUNE 26, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 37, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF1879, MF1880, MF1881, MF1882) The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on June 26, 2014, to discuss and clarify the staff's draft request for additional information (DRAI),
Set 37, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staff's DRAIs.
Enclosure 1 provides a listing of the participants, and Enclosure 2 contains a listing of the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary. /RA/ Lindsay Robinson, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455, 50-456, and 50-457
Enclosures: 1. List of Participants 2. List of Draft Request for Additional Information
cc w/encls: Listserv DISTRIBUTION: See next page ADAMS Accession No.: ML14183A017 *concurred via email OFFICE LA:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME IKing LRobinson YDiazSanabria (JDaily for) LRobinson DATE 7/21/14 7/21/14 7/22/14 7/23/14 OFFICIAL RECORD COPY SUBJECT: SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON JUNE 26, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 37, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF1879, MF1880, MF1881, MF1882)
DISTRIBUTION EMAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsOgcMailCenter RidsNrrPMByron Resource RidsNrrPMBraidwood Resource ---------------------------------- LRobinson DMcIntyre, OPA EDuncan, RIII JBenjamin, RIII AGarmoe, RIII JMcGhee, RIII JRobbins, RIII VMitlyng, RIII PChandrathil, RIII ENCLOSURE 1 TELEPHONE CONFERENCE CALL BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS June 26, 2014 PARTICIPANTS AFFILIATIONS Lindsay Robinson U.S. Nuclear Regulatory Commission (NRC) Allen Hiser NRC Seung Min NRC Carolyn Fairbanks NRC John Hufnagel Exelon Generating Company, LLC (Exelon)
Al Fulvio Exelon Don Warfel Exelon Gary Becknell Exelon Tom Quinitenz Exelon ENCLOSURE 2 DRAFT REQUEST FOR ADDITIONAL INFORMATION BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION June 26, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on June 26, 2014, to discuss and clarify the following draft request for additional information (DRAI), Set 37, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application (LRA).
DRAI B.2.1.19-1b Applicability: Byron Station (Byron) and Braidwood Station (Braidwood), Units 1 and 2
Background: By letter dated May 23, 2014, the applicant responded to request for additional information (RAI) B.2.1.19-1a that requested an updated surveillance capsule withdrawal schedule for each unit at Byron and Braidwood.
Issue: In its response, the applicant deleted information regarding the next capsule withdrawal schedule (e.g., capsules and capsule fluences) from the updated final safety analysis report (UFSAR) supplement, program enhancement, and commitment. The staff cannot determine the adequacy of the applicant's Reactor Vessel Surveillance program because the deleted information is necessary to confirm the program's compliance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix H.
Request:
Provide a basis for the deletion of the information regarding the capsule withdrawal schedule from the UFSAR supplement, program enhancement, and commitment. In addition, provide alternative information upon which the staff could assess the program's compliance with 10 CFR Part 50, Appendix H. Discussion: The applicant requested clarification on the staff's concern. No edits were made to this request. This question will be sent as a formal request titled: "RAI B.2.1.19-1b."