MONTHYEARML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a Project stage: Request PMNS20201224, Pre-Application Meeting with Exelon Generation Company, LLC (Exelon) Regarding a Proposed Alternative to Certain Requirements in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a Codes and Standards2020-10-20020 October 2020 Pre-Application Meeting with Exelon Generation Company, LLC (Exelon) Regarding a Proposed Alternative to Certain Requirements in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a Codes and Standards Project stage: Meeting ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs Project stage: Meeting PMNS20201359, Pre-Application Meeting with Exelon Generation Company, LLC (Exelon) Regarding a Proposed Exemption from Certain Requirements in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a, Codes and Standards2020-12-14014 December 2020 Pre-Application Meeting with Exelon Generation Company, LLC (Exelon) Regarding a Proposed Exemption from Certain Requirements in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a, Codes and Standards Project stage: Meeting ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs Project stage: Meeting 2020-12-14
[Table View] |
Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection ProgramsML20351A283 |
Person / Time |
---|
Site: |
Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle |
---|
Issue date: |
12/18/2020 |
---|
From: |
Blake Purnell Plant Licensing Branch III |
---|
To: |
Bryan Hanson Exelon Generation Co, Exelon Nuclear |
---|
Purnell B |
References |
---|
EPID L-2020-LRM-0089 |
Download: ML20351A283 (6) |
|
Similar Documents at Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle |
---|
Category:Meeting Summary
MONTHYEARML24270A2612024-10-17017 October 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom, Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System ML24277A2972024-10-10010 October 2024 October 2, 2024, Summary of Pre Submittal Public Meeting with Constellation Fitzpatrick, LLC to Discuss Future Amendment on Main Steam Line Radiation Monitor High Radiation System Isolations ML24275A0302024-10-0707 October 2024 Summary of Meeting with Constellation Energy Generation, LLC, Related to the Planned Amendment Request to Allow Modification of the Standby Gas Treatment System ML24261B7722024-09-18018 September 2024 Summary of Partially Closed Observation Meeting with Constellation Energy Generation, LLC, Related to the License Amendment Request to Support Replacement of Existing Safety-Related Analog Control Systems with a Single Digital PPS ML24232A1532024-08-21021 August 2024 Summary of the August 8, 2024, Public Outreach to Discuss the NRC 2023 End-of-Cycle Plant Performance Assessment of Dresden Nuclear Power Plant, Units 2 and 3 ML24214A1402024-08-0505 August 2024 July 24, 2024, Summary of the Public Meeting Regarding Clinton Power Station, Unit 1, Partial Site Release ML24206A1782024-07-29029 July 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System ML24193A3432024-07-12012 July 2024 Summary of the Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 ML24192A2122024-07-10010 July 2024 Summary of the May 22, 2024, Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Lasalle County Station, Units 1 and 2 ML24183A1642024-07-0202 July 2024 June 27, 2024, Summary of the Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Clinton Power Station, Unit 1 ML24162A2212024-06-24024 June 2024 Summary of April 11, 2024, Closed Meeting with Constellation Energy Generation, LLC, Related to the LAR to Support Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (EPID L-2022-LLA- ML24170A8392024-06-18018 June 2024 June 12, 2024, Summary of the Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Byron Station, Units 1 and 2 ML24164A0182024-06-12012 June 2024 May 29, 2024, Summary of the Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2 ML24152A1852024-06-0404 June 2024 Summary of March 28, 2024, Closed Hybrid Pre-Submittal Meeting Between Constellation Energy Generation, LLC and the U.S. Nuclear Regulatory Commission Regarding a Future Amendment Request for Fuel Transition ML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML24151A2592024-06-0303 June 2024 May 22, 2024, Summary of Closed Meeting with Constellation Energy Generation, LLC, Related to the LAR to Support Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24135A3722024-05-22022 May 2024 Enclosure 1 - Meeting Summary for May 7 and May 9 2024 Public Scoping Meetings ML24128A2512024-05-14014 May 2024 Summary of April 11, 2024, Public Meeting with Constellation Energy Generation, LLC Regarding Proposed Alternative to Implement American Society of Mechanical Engineers Operation and Maintenance Code Case OMN-32 ML24113A2872024-04-25025 April 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Regarding Hooded Masks ML24079A2382024-03-19019 March 2024 Summary of March 7, 2024 Regulatory Conference with Constellation Nuclear Regarding Braidwood Station, Unit 2 ML24032A0862024-02-0202 February 2024 Summary of Meeting with Constellation Energy Generation, LLC, on Planned Requests to Use Code Case N-932 ML24009A0552024-01-24024 January 2024 Summary of January 8, 2024, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Removal of the Power Distribution Monitoring System from Technical Specifications ML24018A1772024-01-19019 January 2024 Summary of August 30, 2023, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Relaxation of Inspection Requirements for the Head Penetration P-75 Flaw ML23352A0592024-01-0909 January 2024 Summary of December 11, 2023, Meeting with Constellation on Alternative Request Involving Carbon Fiber Reinforced Polymer Composite ML23363A0942024-01-0303 January 2024 Summary of October 4, 2023, Pre Submittal Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Revising Technical Specification 3.7.9. Ultimate Heat Sink (UHS) ML23362A0042024-01-0202 January 2024 Documentation of Cancelled September 1, 2023, Presubmittal Meeting Between the NRC and Constellation Energy Generation, LLC, Regarding 6-Month Extension of Certain Reactor Pressure Vessel Weld Inspections ML23352A3822023-12-19019 December 2023 Summary of December 11, 2023, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Deletion of Technical Specification 5.6.5.b.5 ML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23276A6522023-10-11011 October 2023 Pre-submittal Meeting Summary, September 14, 2023 ML23271A2682023-10-0505 October 2023 September 25, 2023, Summary of with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23236A5132023-08-31031 August 2023 Summary of Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request ML23234A2342023-08-29029 August 2023 Summary of August 18, 2023, Meeting with Constellation Energy Generation, LLC, Related to the LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23237A2692023-08-25025 August 2023 Summary of the August 23, 2023 Public Outreach to Discuss the NRC 2022 End-of Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 ML23212A9892023-08-0303 August 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23198A0152023-07-27027 July 2023 License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23200A2592023-07-24024 July 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting-Meeting Summary ML23181A0612023-06-30030 June 2023 Summary of the June 15, 2023 Public Outreach to Discuss the NRC 2022 End-Of-Cycle Plant Performance Assessment of Dresden Nuclear Power Station, Units 2 and 3 ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23173A0072023-06-22022 June 2023 Summary of the Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23173A0142023-06-22022 June 2023 Summary of the June 14, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Clinton Power Station, Unit 1 ML23164A2112023-06-14014 June 2023 Summary of the June 1, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML23156A2472023-06-0909 June 2023 Summary of Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML23118A3752023-06-0909 June 2023 Summary of Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 ML23145A0352023-05-31031 May 2023 Summary of May 17, 2023, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 ML23129A0202023-05-30030 May 2023 Summary of March 22, 2023, Closed Meeting with Constellation Energy Generation, LLC, to Discuss a Future License Amendment Request That Allows Byron Station and Braidwood Station to Utilize a New Citicality Analysis for the Spent Fuel Pools ML23142A1602023-05-23023 May 2023 Summary of April 11, 2023, Public Observation Meeting with Constellation Energy Generation, LLC Re Proposed Exemption Request from Work Hour Requirements ML23132A3082023-05-18018 May 2023 Summary of May 3, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 ML23076A0132023-05-12012 May 2023 March 15, 2023, Summary of Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 ML23121A0022023-05-12012 May 2023 Summary of March 29, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 2024-09-18
[Table view] |
Text
December 18, 2020 LICENSEE: Exelon Generation Company, LLC FACILITIES: Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2; Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Clinton Power Station, Unit No. 1; Dresden Nuclear Power Station, Units 2 and 3; James A. FitzPatrick Nuclear Power Plant; LaSalle County Station, Units 1 and 2; Limerick Generating Station, Units 1 and 2; Nine Mile Point Nuclear Station, Units 1 and 2; Peach Bottom Atomic Power Station, Units 2 and 3; Quad Cities Nuclear Power Station, Units 1 and 2; and R. E. Ginna Nuclear Power Plant
SUBJECT:
SUMMARY
OF DECEMBER 15, 2020, MEETING WITH EXELON GENERATION COMPANY, LLC REGARDING A PLANNED REQUEST FOR AN EXEMPTION TO REDUCE THE FREQUENCY OF UPDATES TO ITS INSERVICE TESTING AND INSPECTION PROGRAMS (EPID L-2020-LRM-0089)
On December 15, 2020, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC or Commission) staff and representatives of Exelon Generation Company, LLC (Exelon, the licensee). The purpose of the meeting was to discuss a proposed exemption to certain requirements in Title 10 of the Code of Federal Regulations (10 CFR)
Section 50.55a, Codes and standards, for the subject facilities. The meeting notice and agenda are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML20349A251. A list of attendees is enclosed. No decisions were made at this meeting. A pre-application meeting with Exelon on a similar proposal was held on November 4, 2020 (summary is available under ADAMS Accession No. ML20323A033).
Background
The regulations in 10 CFR 50.55a include, in part, requirements for the use of Section XI of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (BPV Code) and the ASME Code for Operation and Maintenance of Nuclear Power Plants (OM Code) for the inservice inspection (ISI) and inservice testing (IST) of nuclear power plants. Specific editions and addenda of these ASME Codes have been incorporated by reference into 10 CFR 50.55a, subject to certain limitations. Every 10 years, licensees are required to update their ISI and IST programs to the latest editions and addenda of the applicable ASME Code incorporated by reference in 10 CFR 50.55a.
In June 2020, the NRC Embark Venture Studios (Embark) recommended (ADAMS Accession No. ML20153A752) rulemaking to relax the requirement to update the ISI and IST programs every 10 years following the update to the 2019 or later edition of the ASME BPV Code and the 2020 or later edition of the ASME OM Code.
Discussion For the subject facilities, Exelon plans to request an exemption that would allow it to reduce the frequency of updates to the containment, ISI, and IST programs from every 10 years to every 24 years. The proposed exemption would also allow Exelon to increase the ISI and IST intervals from 10 years to 12 years. Under this proposal, each facility would remain on the current code of record for two consecutive 12-year intervals. The ISI intervals would then consist of three 4-year periods, which would allow for skip outages where most inspections would not be performed. Exelon plans to submit a single exemption request under 10 CFR 50.12, Specific exemptions, for its entire operating fleet in January 2021.
As discussed during the November 4, 2020, meeting, Exelon previously planned to submit a proposed alternative under 10 CFR 50.55a to accomplish these same objectives. The summary of the November 4, 2020, meeting states, in part:
The NRC staff stated that it would review and respond, as appropriate, to any licensing action that Exelon submitted. However, the staff believes the changes that Exelon is seeking should be implemented through a revision of 10 CFR 50.55a. The reasons provided in the presentation do not appear to be unique to Exelon. Therefore, it would be beneficial to consider the views of the broader industry and other stakeholders regarding Exelons proposed changes.
Additionally, the staff stated that Exelon should consider working through the ASME consensus committees to revise the ISI and IST intervals.
Exelon stated that there are some similarities between its proposed exemption and previously granted exemptions from the requirements in Appendix J, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors, to 10 CFR Part 50. However, Exelon did not elaborate on this statement.
Exelon stated that the application for exemption would identify the specific regulations in 10 CFR 50.55a for which they would be requesting an exemption. Exelon did not specifically identify these regulations during the meeting, but Exelon did state that it was not planning to request a complete exemption from 10 CFR 50.55a.
The regulation in 10 CFR 50.12 states that the NRC will not consider granting an exemption unless special circumstances are present. Exelon stated that the following special circumstances were present:
Application of the regulation in the particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule (10 CFR 50.12(a)(2)(ii)).
Compliance would result in undue hardship or other costs that are significantly in excess of those contemplated when the regulation was adopted (10 CFR 50.12(a)(2)(iii)).
For the first of these special circumstances, Exelon stated that the initial rule intended the updates to be minimal impact. Exelon stated that since the incorporation of the initial update requirements in 1976, costs to implement the ASME Code updates have escalated with no substantial benefit. In addition, Exelon stated that implementing updated code editions are not necessary to ensure adequate protection of public health and safety.
For the second of these special circumstances, Exelon stated that it will provide the costs and related analysis as part of its submittal. Exelon stated that the update process takes about 4 years to complete and costs about $1 million for each site. Exelon stated that it does not see a significant difference in costs between its sites, so it plans to provide a single cost value, rather than a plant-specific breakdown of costs. Exelon stated that most of this cost is for administrative changes, such as changes to documentation and procedures. In addition, the 10-year interval is a challenge for certain types of tests because of Exelons divisional outage strategy that includes skip outages.
The NRC staff noted that, over the last few years, there have been major changes to the ASME OM Code requirements to improve the safety of nuclear power plants. For example, the ASME OM Code has been updated to address adverse operating experience of power-operated valves to provide reasonable assurance of their operational readiness to perform the applicable safety functions. Specifically, the staff discussed the improvements to the IST requirements for motor-and air-operated valves in 2009 and 2017, respectively. Exelon stated that it would consider including a discussion of how it will manage such items that will be implemented outside the ASME OM Code requirements as part of its exemption request. Exelon stated that it does not wait for ASME to update the Codes before it makes improvements to its IST and ISI programs.
The NRC staff noted that the licensees ISI and IST programs are established based on the regulatory requirements to implement the ASME Codes, as incorporated by reference in 10 CFR 50.55a. The staff requested that the Exelon submittal address the foundation of the ISI and IST activities at the Exelon plants for NRC review and evaluation in lieu of the specific regulatory requirements in the more recent editions of the ASME Codes incorporated by reference in 10 CFR 50.55a.
Exelon stated that it had considered requesting either an exemption under 10 CFR 50.12 or an alternative under 10 CFR 50.55a(z) to implement its proposal. Exelon asked the NRC staff which approach it would prefer. The NRC staff noted that, consistent with the Embark recommendation and the November 4, 2020, meeting on this subject, rulemaking would be the preferred approach. Exelon stated that it did not expect this rulemaking to be completed until 2023, which would not fit its schedule. In addition, Exelon was concerned that implementing the 2019 edition of the ASME BPV Code would not be cost effective.
No public comments were made during the meeting. Public meeting feedback forms were not received. Please direct any inquiries to me at 301-415-1380 or Blake.Purnell@nrc.gov.
/RA/
Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-317, 50-318, 50-461, 50-237, 50-249, 50-333, 50-373, 50-374, 50-352, 50-353, 50-220, 50-410, 50-277, 50-278, 50-254, 50-265, and 50-244
Enclosure:
List of Attendees cc: Listserv
LIST OF ATTENDEES DECEMBER 15, 2020, MEETING WITH EXELON GENERATION COMPANY, LLC Name Affiliation Blake Purnell NRC Steve Bloom NRC Angela Buford NRC David Rudland NRC Tom Scarbrough NRC Nancy Salgado NRC Robert Krsek NRC Tison Campbell NRC Sheldon Clark NRC Brian Harris NRC Hipo Gonzalez NRC Thomas Loomis Exelon Brendan Casey Exelon Mark DiRado Exelon Mark Weis Exelon Glenn Weiss Exelon Enclosure