06/23/2014 Summary of Telephone Conference Call Between NRC and Exelon Generation Co., LLC, Concerning the Byron and Braidwood, License Renewal Application (TAC Nos. MF1879, MF1880, MF1881 and MF1882)
ML14177A430
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 07/02/2014
From: Robinson L
License Renewal Projects Branch 1
To:
Robinson L, 415-4115
References
TAC MF1879, TAC MF1880, TAC MF1881, TAC MF1882
Download: ML14177A430 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 2, 2014 LICENSEE: Exelon Generation Company, LLC FACILITY: Byron Station, Units 1 and 2 Braidwood Station, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON JUNE 23, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS.

MF1879, MF1880, MF1881, AND MF1882)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on June 23, 2014, to discuss and clarify the applicants responses to staff requests for additional information (RAIs), which were submitted by the applicant dated May 23, 2014. Specifically, the staff discussed the responses submitted for RAI 4.6.4-1 and RAI 4.6.5-1. The applicant addressed the staffs concerns.

The applicant had an opportunity to comment on this summary.

/RA/

Lindsay Robinson, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455, 50-456, and 50-457

Enclosure:

List of Participants cc w/encl: Listserv

ML14177A430 *concurred via email OFFICE LA:DLR PM: RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME IKing LRobinson YDiazSanabria LRobinson DATE 6/27/14 7/1/14 7/1/14 7/2/14

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON JUNE 23, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS.

MF1879, MF1880, MF1881, AND MF1882)

DISTRIBUTION EMAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsOgcMailCenter RidsNrrPMByron Resource RidsNrrPMBraidwood Resource


LRobinson DMcIntyre, OPA EDuncan, RIII JBenjamin, RIII AGarmoe, RIII JMcGhee, RIII JRobbins, RIII VMitlyng, RIII PChandrathil, RIII

TELEPHONE CONFERENCE CALL BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS June 23, 2014 PARTICIPANTS AFFILIATIONS Lindsay Robinson U.S. Nuclear Regulatory Commission (NRC)

Andrew Prinaris NRC Alice Erickson NRC John Hufnagel Exelon Generating Company, LLC (Exelon)

Don Warfel Exelon Jim Annett Exelon Tom Quintenz Exelon Pete Tamburro Exelon Don Brindle Exelon ENCLOSURE