Letter Sequence Draft RAI |
---|
EPID:L-2020-LLA-0238, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition (Withdrawn, Closed) |
|
MONTHYEARML20304A1472020-10-29029 October 2020 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition Project stage: Request ML21036A1102021-02-0404 February 2021 NRR E-mail Capture - Draft RAIs for Byron Station, Unit Nos. 1 and 2, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition Project stage: Draft RAI RS-21-024, Response to Request for Additional Information (RAI) Regarding Byron Station, Units 1 and 2, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition2021-03-16016 March 2021 Response to Request for Additional Information (RAI) Regarding Byron Station, Units 1 and 2, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition Project stage: Response to RAI ML21081A0972021-03-19019 March 2021 Acceptance Review for Byron Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis-External Events (EPID L-2021-JLD-0004) (E-mail) Project stage: Acceptance Review ML21081A0792021-03-19019 March 2021 Acceptance Review for Byron Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Acceptance Review RS-21-060, Post-Shutdown Decommissioning Activities Report2021-07-28028 July 2021 Post-Shutdown Decommissioning Activities Report Project stage: Request RS-21-068, Response to Request for Additional Information 2 Regarding License Amendment Request - Proposed Defueled Tech Specs and Revised License Conditions for Permanently Defueled Condition2021-07-29029 July 2021 Response to Request for Additional Information 2 Regarding License Amendment Request - Proposed Defueled Tech Specs and Revised License Conditions for Permanently Defueled Condition Project stage: Response to RAI ML21260A1392021-09-28028 September 2021 ISFSI Withdrawal of Licensing Actions Associated with the Scheduled Permanent Shut Down and Decommissioning of Units (EPIDs L-2020-LLA-0215,L-2020-LLE-0156,L-2020-LLA-0238,L-2020-LLA-0240,L-2021-JLD-0004,L-2021-JLD-0005,L-2021-LRO-0041 Project stage: Withdrawal ML21260A1352021-09-28028 September 2021 ISFSI Withdrawal of Licensing Actions Associated with the Scheduled Permanent Shut Down and Decommissioning of Units Project stage: Request 2021-03-19
[Table View] |
Similar Documents at Byron |
---|
Category:E-Mail
MONTHYEARML23317A2012023-11-22022 November 2023 (External_Sender) Supplement - Byron Security Rule Exemption Request ISFSI Docket No. Reference ML23321A2012023-11-17017 November 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML23311A1692023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Exam Categories B-B, B-D, and C-A SG Pressure Retaining Welds and Full Penetration Welded Nozzles (L-2023-LLR-0055 and L-2023-LLR-00 ML23311A1682023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (L-2023-LLR-0053 and L-2023-LLR-005 ML23305A2992023-11-0101 November 2023 NRR E-mail Capture - NRC Acceptance Review of Byron, Unit 2, Relief Request I4R-24 ML23304A0202023-10-30030 October 2023 NRR E-mail Capture - Final RCI - Constellation Energy Generation, LLC - Byron 1 & 2 - Exemption from Security Rule (L-2023-LLE-0027) ML23272A0602023-09-29029 September 2023 NRR E-mail Capture - NRC Acceptance Review of Byron, Unit 1, Relief Request I4R-25 ML23187A0092023-07-0606 July 2023 NRR E-mail Capture - NRC Acceptance Review of Byron and Braidwood Request to Adopt TSTF-370 ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23115A2412023-01-20020 January 2023 NRR E-mail Capture - Preliminary RAIs Related to L-2022-LLA-0131 - Byron, Unit 2, Reinsertion of an Accident Tolerant Fuel Lead Test Assembly ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22284A1022022-10-0606 October 2022 NRR E-mail Capture - NRC Acceptance Review for Byron, Unit 2, License Amendment Request (LAR) to Reinsert an Accident Tolerant Fuel (ATF) Lead Test Assembly (LTA) (L-2022-LLA-0131) ML22255A0132022-09-0909 September 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, Calvert Cliffs, Ginna - License Amendment Request to Adopt TSTF-577 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22189A0602022-07-0707 July 2022 NRR E-mail Capture - Draft RAI for Byron/Braidwood TSTF-501 ML22136A2722022-05-16016 May 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood and Byron Adoption of TSTF-501 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22116A0242022-04-25025 April 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, and Ginna Request to Adopt TSTF-246 ML22105A0722022-04-15015 April 2022 NRR E-mail Capture - Braidwood/Byron Verbal Authorization for Proposed Alternative I4R-15/I4R-21 ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22088A1562022-03-0202 March 2022 NRR E-mail Capture - Byron, Braidwood, Calvert Cliffs, and Ginna - Non-acceptance of Application to Revise Technical Specifications 5.6.5.b, the Core Operating Limits Report (COLR) ML22091A0842022-02-24024 February 2022 NRR E-mail Capture - Braidwood and Byron - Withdrawal of Draft RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML23089A0152022-01-0505 January 2022 NRR E-mail Capture - NRC Acceptance Review of Byron - Proposed Alternative for Examinations of Categories B-B, B-D, and C-A SG Welds and Nozzles ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21272A1492021-09-29029 September 2021 NRR E-mail Capture - NRC Acceptance Review of Braidwood and Byron - Proposed Alternative for Examinations of Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0042021-08-26026 August 2021 NRR E-mail Capture - NRC Acceptance Review - Braidwood/Byron/Clinton - Adoption of TSTF-273, Safety Function Determination Program Clarifications ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21203A3112021-07-21021 July 2021 NRR E-mail Capture - Final Byron Permanently Defueled Technical Specifications (PDTS) - Second Round RAI ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21189A1612021-07-0808 July 2021 NRR E-mail Capture - Second Round Request for Additional Information - Byron Permanently Defueled Technical Specification Amendment ML21154A0172021-06-0202 June 2021 NRR E-mail Capture - Acceptance Review of Byron - Proposed Alternative for Exam of Pzr Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Shell Welds ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21123A2442021-05-0303 May 2021 NRR E-mail Capture - NRC Acceptance Review of Braidwood/Byron/Ginna - Application to Address the Issues Identified in Westinghouse Documents NSAL-09-5 and NSAL-15-1 (L-2021-LLA-0066) ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21081A0792021-03-19019 March 2021 Acceptance Review for Byron Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation ML21081A0972021-03-19019 March 2021 Acceptance Review for Byron Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis-External Events (EPID L-2021-JLD-0004) (E-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21036A1102021-02-0404 February 2021 NRR E-mail Capture - Draft RAIs for Byron Station, Unit Nos. 1 and 2, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML21033A5372021-02-0101 February 2021 Email transmission- 01-29-2021, FEMA Letter to Governor of Commonwealth of PA Regarding Implementation of TMI EP Exemptions ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21004A1452020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Relief Requests Braidwood I4R-11 and Byron I4R-18 2023-09-29
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection ML23209A7242023-07-31031 July 2023 Request for Information on the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000454/2024010 and 05000455/2024010 ML23198A0372023-07-17017 July 2023 Information Request to Support Upcoming Problem Identification and Resolution (PIR) Inspection at Byron Nuclear Plant ML23172A1172023-06-22022 June 2023 Notification of NRC Fire Protection Team Inspection Request for Information ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23069A0342023-03-0606 March 2023 Unit 1 Lr Commitment 10 RAI Set 1 - (Non-Proprietary) ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23115A2412023-01-20020 January 2023 NRR E-mail Capture - Preliminary RAIs Related to L-2022-LLA-0131 - Byron, Unit 2, Reinsertion of an Accident Tolerant Fuel Lead Test Assembly ML22237A0272022-08-25025 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22116A1272022-04-26026 April 2022 Unit 2 RFI for an NRC Triennial Heat Exchanger/Sink Performance Inspection and RFI IR 05000454/2022002 05000455/2022002 ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21273A3312021-10-0404 October 2021 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Byron Station ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21203A3112021-07-21021 July 2021 NRR E-mail Capture - Final Byron Permanently Defueled Technical Specifications (PDTS) - Second Round RAI ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21189A1612021-07-0808 July 2021 NRR E-mail Capture - Second Round Request for Additional Information - Byron Permanently Defueled Technical Specification Amendment ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21036A1102021-02-0404 February 2021 NRR E-mail Capture - Draft RAIs for Byron Station, Unit Nos. 1 and 2, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21004A1452020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Relief Requests Braidwood I4R-11 and Byron I4R-18 ML20329A4852020-11-24024 November 2020 Notification of NRC Fire Protection Team Inspection Request for Information ML20294A5492020-10-21021 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML20289A1142020-10-0909 October 2020 NRR E-mail Capture - Preliminary RAIs for LAR Regarding Non-conservative TS EDG Frequency Tolerance ML20077M2212020-03-20020 March 2020 Ti 2515/194 Inspection Documentation Request ML20008D3992020-01-0808 January 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000454/2020001 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19252C1542019-08-22022 August 2019 NRR E-mail Capture - Issuance of the Remainder of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19232A2242019-08-0707 August 2019 NRR E-mail Capture - Partial Issuance of Final RAIs for Braidwood/Byron TSTF-505 Application ML19207A0672019-07-26026 July 2019 NRR E-mail Capture - Partial Issuance of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19032A1062019-02-0101 February 2019 NRR E-mail Capture - Preliminary RAIs for Byron On--time Extension of Completion Time 3.8.1, A.2 ML19011A3452019-01-11011 January 2019 NRR E-mail Capture - Preliminary RAIs Regarding Byron Request to Use ATF LTAs ML18149A2842018-05-24024 May 2018 NRR E-mail Capture - B/B 50.69 RAI - Potential Typo ML18129A1082018-05-0909 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood and Byron Stations 50.69 Amendment ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML18022A0422018-01-19019 January 2018 18 Byron Station, Units 1 and 2 - Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection (DRS-I.Hafeez) ML17179A2852017-06-28028 June 2017 NRR E-mail Capture - Request for Additional Information Regarding Braidwood and Byron Amendments to Remove Obsolete License and Technical Specification Items ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17137A0562017-05-17017 May 2017 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Byron Station, Units 1 and 2 ML17062A4912017-03-0303 March 2017 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative to RPV Threads in Flange Examination (CAC Nos. MF8712-MF8729) ML17019A2022017-01-19019 January 2017 NRR E-mail Capture - Preliminary RAIs for Byron Station TORMIS License Application Request ML16355A0322016-12-19019 December 2016 Notification of NRC Inspection and Request for Information (Msh) ML16343A2522016-12-0808 December 2016 NRR E-mail Capture - Preliminary Request for Additional Information (RAI) Regarding Relief Request I4R-10 ML16196A1102016-07-14014 July 2016 Notification of NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000454/2016004; 05000455/2016004 2023-07-31
[Table view] |
Text
From: Wiebe, Joel Sent: Thursday, February 4, 2021 2:15 PM To: Lisa Simpson (Lisa.Simpson@exeloncorp.com)
Cc: 'Simpson, Patrick R.:(Exelon Nuclear)'
Subject:
DRAFT RAIs for Byron Station, Unit Nos. 1 and 2, re: Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition (EPID L-2020-LLA-0238)
- Lisa, By application dated October 29, 2020 (Agencywide Documents Access and Management System Accession No. ML20304A147), Exelon Generation Company, LLC, requested a License Amendment Request re: Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition for Byron Station, Unit Nos. 1 and 2. The proposed changes would revise the renewed facility operating licenses and TSs consistent with the permanent cessation of operations and permanent defueling of the reactors.
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing your submittal and has identified areas where additional information is needed to complete the review. Below, please find DRAFT requests for additional information (RAIs). Following a brief evaluation period by your staff we will contact you. Should your staff identify the need to discuss the DRAFT RAIs any further, we will coordinate a teleconference (non-public). Should no follow-up discussions or clarifications be necessary, the NRC staff will proceed by designating these RAIs as FINAL at which time an established response date by Exelon will be determined.
If you have any questions/comments, please contact me at 301-415-6606 or Joel.Wiebe@nrc.gov.
Joel BYRON, UNITS 1 and 2 REQUEST FOR ADDITIONAL INFORMATION PROPOSED DEFUELED TECHNICAL SPECIFICATIONS AND REVISED LICENSE CONDITIONS FOR PERMANENTLY DEFUELED CONDITION DOCKET NOS. STN 50-454 AND STN 50-455 By application dated October 29, 2020 (Agencywide Documents Access and Management System Accession No. ML20304A147), Exelon Generation Company, LLC, requested a change to the Technical Specifications (TS) for Byron Station, Unit Nos. 1 and 2 (Byron). The proposed changes would revise the TSs consistent with the permanent cessation of operations and permanent defueling of the reactors.
The provisions in 10 CFR 50.36(c)(6), Decommissioning, in part, apply only to nuclear power reactor facilities that have submitted the certifications required by 10 CFR 50.82(a)(1). For such facilities, technical specifications involving safety limits, limiting safety system settings, and limiting control
system settings; limiting conditions for operation; surveillance requirements; design features; and administrative controls will be developed on a case-by-case basis.
In the application the licensee states, [t]his request applies the principles identified in 10 CFR 50.36(c)(6), Decommissioning, for a facility which has submitted certifications required by 50.82(a)(1) and proposes changes to the Administrative Controls appropriate for the Byron permanently defueled condition.
To complete its review of the TS changes, the U.S. Nuclear Regulatory Commission (NRC) staff requests the following additional information:
Discussion: (DRAFT-RAI-1a & 1b) - re: Final Safety Analysis Report (FSAR)
The Final Safety Analysis Report (FSAR) is the principal document upon which the NRC bases its safety evaluation supporting the issuance of an operating license for a nuclear power plant. The updated FSAR (UFSAR) incorporates changes made to the FSAR in accordance with 10 CFR 50.71(e). The UFSAR serves as a major source of information on the current plant design and supporting analyses.
NRC decommissioning guidance (e.g., RG 1.184) discusses that the FSAR, which provides a licensing basis for the evaluation of licensing activities under 10 CFR 50.59, will have to be updated to cover decommissioning activities.
The Byron license amendment request (LAR) Attachment 1 states, [t]he Technical Specifications Bases Control Program is being modified to reflect that once the facility is permanently defueled the title of the UFSAR will be revised to DSAR. LAR Attachment 3, Markup of Technical Specifications Pages, reflects this proposed change in a markup of TS 5.5.14, The Technical Specifications (TS) Bases Control Program, by replacing UFSAR with DSAR. DSAR is not a term that is described, defined, or required by NRC regulation. The proposed change, UFSAR revised to DSAR, occurs in two instances within Byron TS 5.5.14 (emphasis added in bold italic):
Bryon TS 5.5.14.b currently states:
Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
- 1. a change in the TS incorporated in the license; or
- 2. a change to the UFSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
Byron TS 5.5.14.c currently states:
The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the UFSAR.
Staff Requests:
Given that NRC regulations, such as 10 CFR 50.59, are written in terms of FSAR, and DSAR is not a term that is described, defined, or required in NRC regulations; (DRAFT-RAI-1a): Please explain how the DSAR (replaces UFSAR in TS 5.5.14.b.2 above) will remain subject to the provisions of 10 CFR 50.59.
Additionally, 10 CFR 50.71(e)(6) states, The updated FSAR [UFSAR] shall be maintained by the licensee until the Commission terminates their license. Given NRC requirements for licensees to maintain the updated FSAR until the Commission terminates their license and that a DSAR is not described, defined, or required in NRC regulations; (DRAFT-RAI-1b): Please explain how the Byron TS Bases (DSAR replaces UFSAR in TS 5.5.14.c above) will be maintained consistent with the updated FSAR under this proposed title change.
Discussion: (DRAFT-RAI-2) - Regulatory Basis/Issue re: New Fuel Handling Accident Analysis Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, Rev. 0, July 2000 provides the methodology for analyzing the radiological consequences of several design-basis accidents (DBAs) to show compliance with 10 CFR 50.67.
Regulatory Guide 1.183 provides guidance to licensees on acceptable application of alternate source term (AST) submittals, including acceptable radiological analysis assumptions for use in conjunction with the accepted AST.
NUREG-0800, Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants:
LWR [Light-Water Reactor] Edition, (SRP) Section 15.0.1, Radiological Consequence Analyses Using Alternative Source Terms, Rev. 0, July 2000 provides review guidance to the staff for the review of alternative source term amendment requests. Section 15.0.1 states that the NRC reviewer should evaluate the proposed change against the guidance in RG 1.183. The dose acceptance criteria for the fuel handling accident (FHA) are a Total Effective Dose Equivalent (TEDE) of 6.3 rem at the exclusion area boundary (EAB) for the worst 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, 6.3 rem at the outer boundary of the low population zone (LPZ),
and 5 rem in the control room for the duration of the accident.
In Attachment 1 of the LAR, Exelon states that a new Fuel Handling Accident (FHA) analysis was performed to determine the Control Room (CR), Exclusion Area Boundary (EAB), and Low Population Zone (LPZ) doses at Byron. This analysis is required to replace the current FHA which only covers FHA events due to a fuel assembly being dropped on the reactor core, which currently bounds the radiological consequences of an FHA in the Spent Fuel Pool.
Staff Request:
The LAR indicates that the analysis conforms to RG 1.183 and that the limits of RG 1.183 continue to be met, however, many of the assumptions and parameters used are not specified and the doses calculated are not specified.
(DRAFT-RAI-2): Please provide sufficient technical details of the new FHA to allow for evaluation. The NRC staff requests this information include but not necessarily be limited to; computer program(s) used to calculate dose, key input variables, calculated dose to CR, EAB, and LPZ, source term use in the new
FHA analysis, fall height of fuel assembly, water coverage, decontamination factors, and atmospheric dispersion factors.
In addition to the above RAIs, the NRC staff has identified the following apparent editorial errors:
- a. There appears to be an editorial error in Attachment 1 of the LAR. In the detailed description of the proposed changes to Byron TS Section 5.5.14, Technical Specifications (TS) Bases Control Program, the column entitled Basis for Change uses the acronym DSAR for the first time in the LAR without spelling it out or providing a description/definition. If DSAR is retained (could be changed based on a response to other questions), then spell out the acronym on it first use in the LAR.
- b. There appears to be an editorial error in Attachment 3 (Markups of Technical Specifications Pages) of the LAR. In the markup of the proposed changes to Byron TS Section 5.5.14, Technical Specifications (TS) Bases Control Program, DSAR is used for the first time in the TSs without spelling out the acronym. Please spell out the acronym on it first use in the TSs.
- c. There appears to be an editorial error in Attachment 1 of the LAR. In the detailed description of the proposed changes to Byron TS Section 1.1, Definitions, the column entitled Basis for Change states (on two occasions), the LAR proposing changes to TS Section 1.1 and 5.0 (Reference 2) which is currently under NRC review. However, the citing of Reference 2 appears to be incorrect because Reference 2 does not propose any changes to TS Section 1.1 or 5.0. Please identify the correct reference.
Hearing Identifier: NRR_DRMA Email Number: 1002 Mail Envelope Properties (MN2PR09MB4971F53E53E0435E8657F4288BB39)
Subject:
DRAFT RAIs for Byron Station, Unit Nos. 1 and 2, re: Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition (EPID L-2020-LLA-0238)
Sent Date: 2/4/2021 2:15:18 PM Received Date: 2/4/2021 2:15:00 PM From: Wiebe, Joel Created By: Joel.Wiebe@nrc.gov Recipients:
"'Simpson, Patrick R.:(Exelon Nuclear)'" <patrick.simpson@exeloncorp.com>
Tracking Status: None "Lisa Simpson (Lisa.Simpson@exeloncorp.com)" <Lisa.Simpson@exeloncorp.com>
Tracking Status: None Post Office: MN2PR09MB4971.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 9538 2/4/2021 2:15:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: