R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary
ML23263B106
Person / Time
Site: Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle  Constellation icon.png
Issue date: 09/22/2023
From: Scott Wall
Plant Licensing Branch III
To: Rhoades D
Constellation Energy Generation
Wall, SP
References
EPID L-2023-LRM-0062
Download: ML23263B106 (1)


Text

September 22, 2023 LICENSEE: Constellation Energy Generation, LLC FACILITIES: Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2; Calvert Cliffs Nuclear Power Plant, Units 1 and 2; and R. E. Ginna Nuclear Power Plant

SUBJECT:

SUMMARY

OF SEPTEMBER 18, 2023, WITH CONSTELLATION ENERGY GENERATION, LLC ON PLANNED REQUESTS FOR ALTERNATIVES FOR CERTAIN STEAM GENERATOR WELD INSPECTIONS (EPID L-2023-LRM-0062)

On September 18, 2023, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Generation, LLC (CEG, the licensee) via webinar. The purpose of this meeting was to discuss CEGs plans to submit a request for alternatives for certain steam generator weld inspections for Braidwood Station, Units 1 and 2 (Braidwood); Byron Station, Unit Nos. 1 and 2 (Byron); Calvert Cliffs Nuclear Power Plant, Units 1 and 2; and R. E. Ginna Nuclear Power Plant (collectively, the CEG facilities). The meeting notice and agenda dated August 22, 2023, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML23256A258, and CEGs meeting handout is available at ML23255A104. Additionally, two NRC products referenced in the handouts are locates at ML23114A034 and ML23158A180. A list of attendees is enclosed.

The licensee presented information regarding the schedule and contents of the upcoming alternatives plans for the CEG facilities. The licensee stated that to satisfy the American Society of Mechanical Engineers (ASME) Code,Section XI, requirements applicable to the components covered by the proposed alternative, the CEG facilities would be required to perform a combined 67 examinations each inspection interval. The licensee also provided a table to identify the number of required examinations by unit, Examination Category, and the Item Number, and a graphical representation of the performance monitoring plan. In the proposed alternative, the license would be seeking to reduce the number of examinations required in future inspection intervals. CEG currently plans to submit the alternative requests in Fall 2023.

The NRC staff provided feedback on the following topics:

Interval Completion Status: The NRC staff appreciated the information provided regarding the current interval period and suggested that it would be helpful if similar information was provided for the next interval periods.

Pressurizer Shell Weld Inspections: The NRC staff recommended that CEG ensure that the information provided for Byron and Braidwood was consistent with the example for pressurizer shell welds provided on slides 20 and 21 of the April 27, 2023, presentation (ML23114A034).

The NRC staff appreciated that the licensee held the meeting sufficiently early in the development process so that any staff comment could be considered in the application.

No members of the public had questions or comments during the meeting. No regulatory decisions were made at this meeting. Please direct any inquiries to me at 301-415-2855, or Scott.Wall@nrc.gov.

Sincerely,

/RA/

Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-317, 50-318, and 50-244

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES SEPTEMBER 18, 2023, PUBLIC MEETING WITH CONSTELLATION ENERGY GENERATION, LLC PLANNED REQUESTS FOR ALTERNATIVES FOR CERTAIN STEAM GENERATOR WELDINSPECTIONS Name Organization Scott Wall Nuclear Regulatory Commission (NRC)

Angie Buford NRC Hipo Gonzalez NRC Jeff Whited NRC Dan Widrevitz NRC John Tsao NRC David Rudland NRC Michael Benson NRC David Dijamco NRC Jay Robinson NRC Sujata Goetz NRC V Sreenivas NRC Tom Loomis Constellation Energy Generation, LLC (CEG)

Mark Weis CEG Romit Patel CEG Brian Seawright CEG Dane Brunswick CEG Gabe Chavez CEG Zoe Cox CEG Justin Knowles CEG Austin Bowley CEG Sailaja Mokkapati CEG Joe Buchanan CEG David Gutierrez CEG Enclosure

ML23263B106 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM NAME SWall SRohrer JWhited SWall DATE 09/20/2023 09/20/2023 09/21/2023 09/22/2023