Schedule Revision for the Review of the Byron and Braidwood Stations, Units 1 and 2, License Renewal Application (TAC No. MF1832, MF1833, MF1792, MF1793, MF1879, MF1880, MF1881, and MF1882)
ML15008A442
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 01/29/2015
From: Chris Miller
Division of License Renewal
To: Gallagher M
Exelon Generation Co
Tran T, 415-3617
References
TAC MF1792, TAC MF1793, TAC MF1832, TAC MF1833, TAC MF1879, TAC MF1880, TAC MF1881, TAC MF1882
Download: ML15008A442 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-001 January 29, 2015 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way P.O. Box 500 Kennett Square, PA 19348

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE BYRON AND BRAIDWOOD STATIONS, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NO. MF1832, MF1833, MF1792, MF1793, MF1879, MF1880, MF1881, AND MF1882)

Dear Mr. Gallagher:

By letter dated May 29, 2013, Exelon Generation Company, LLC, submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating licenses NPF-37, NPF-66, NPF-72 and NPF-77, respectively, for Byron Station, Units 1 and 2 (Byron), and for Braidwood Station, Units 1 and 2 (Braidwood), for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the Braidwood license renewal review and a change to the safety review for Byron and Braidwood.

Regarding the staffs environmental review, by letter dated October 17, 2014, the staff issued a letter revising the environmental review schedule. This revision established a January 2015 issuance date for the Braidwood draft Supplemental Environmental Impact Statement (SEIS).

Due to issues related to technical editing and review of the SEIS, the staff needs additional time to complete the draft SEIS. The new issuance date for the final SEIS is March 2015. The projected issuance date for the final SEISs for Byron and Braidwood have not changed and are scheduled for July 2015 and September 2015, respectively.

The staff is also revising the following safety review milestones: Issue final SER [Safety Evaluation Report] and Advisory Committee on Reactor Safeguards (ACRS) full committee meeting. The final SER issuance milestone is revised from April 2015 to July 2015 because the staff needs additional information to complete its review of unresolved technical issues, in particular those concerning: (1) the Flux Thimble Tube Inspection Aging Management Program (AMP); (2) Cracking of Nickel-Alloy Components and Loss of Material Due to Boric Acid-Induced Corrosion in Reactor Coolant Pressure Boundary Components AMP; (3) metal fatigue time-limited aging analysis (TLAA); (4) any recent current licensing basis changes that affect the staffs evaluation as reported in the Safety Evaluation with Open Items issued October 30, 2014 (ADAMS Accession No. ML14296A176); and (5) all outstanding requests for additional information. Due to the

M. Gallagher revision of the final SER issuance milestone, the ACRS full committee meeting milestone is revised from May 2015 to September 2015.

The staff notes that to complete all necessary safety review milestones (e.g. issue final SER and ACRS full committee meeting) to support the November 2015 final decisions on renewed licenses for Byron and Braidwood, Exelon needs to resolve all technical issues by March 16, 2015. Therefore, final responses to all unresolved technical issues need to be provided to the staff no later than March 2, 2015. After receiving your responses to the unresolved technical issues discussed above, the staff will review the responses, determine if there is reasonable assurance that the safety concern(s) and aging management issue(s) are addressed, and then document the final determination in its safety review. The completeness and quality of your responses are essential to maintain the revised schedule, and any delay could result in additional revisions to the enclosed schedule, with the added potential of leaving milestone schedule dates to be determined.

Enclosed is the NRC staff's revised review schedule for the Byron and Braidwood license renewal application. If you have any questions related to the revised environmental schedule for Braidwood, please contact Tam Tran at 301-415-3617 or by e-mail at Tam.Tran@nrc.gov. If you have any questions related to the revised safety schedule, please contact John Daily at 301-415-3873 or by e-mail at John.Daily@nrc.gov.

Sincerely,

/RA/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455, 50-456, and 50-457

Enclosure:

Revised Schedule cc w/encl: Listserv

ML15008A442 *concurred via email OFFICE LA:DLR:RPB2* PM:DLR:RPB2 PM:DLR:RPB2 PM:DLR:RPB1 PM:DLR:RPB1 NAME IBetts TTran LJames LRobinson JDaily DATE 1/26/15 1/27/15 1/28/15 1/28/15 1/28/15 OFFICE BC:DLR:RPB2 BC:DLR:RPB1 D:DLR NAME BWittick YDiaz- CMiller Sanabria DATE 1/28/15 1/29/15 1/29/15

BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Schedule Actual Milestones Date Date Receive license renewal application (LRA) 05/29/13 05/29/13 Publish Federal Register Notice (FRN) - LRA availability 06/2013 06/13/13 Publish FRN - acceptance/rejection and opportunity for hearing 07/2013 07/24/13 Publish FRN - environmental scoping meeting 07/2013 08/06/13 Audit - Scoping & Screening Methodology 1 (at Byron) 07/2013 07/2013 Audit - Aging Management Programs 1 (at Byron) 08/2013 08/2013 Public Meeting - License Renewal Overview and Environmental 08/20/13- 08/20/13 Scoping meetings 08/21/13 (Byron) 08/21/13 (Braidwood)

Deadline for filing hearing requests and petitions for intervention 09/2013 09/23/13 Audit - Environmental (Byron) 09/2013 09/19/13 Environmental scoping period ends 09/2013 09/27/13 Audit - Scoping & Screening Methodology 2 (at Braidwood) 10/2013 12/02/13-12/04/13 Audit - Aging Management Programs 2 (at Braidwood) 10/2013 12/02/13-12/06/13 Audit - Environmental (Braidwood) 11/2013 11/19/13 Regional Inspection (Byron) 08/2014 8/4/14-8/8/14 and 8/22/14 Regional Inspection (Braidwood) 09/2014 9/15/14-9/26/14 Issue safety evaluation report (SER) with open items 11/2014 10/30/14 Issue draft supplemental environmental impact statement (SEIS) - 12/2014 12/31/14 Byron Advisory Committee on Reactor Safeguards (ACRS) 12/2014 12/3/14 Subcommittee meeting Publish U.S. Environmental Protection Agency (EPA) FRN 01/2015 01/02/15 Published - availability of final SEIS FRN - Byron draft SEIS available for comments Issue draft SEIS - Braidwood 03/2015 Publish EPA FRN - Braidwood draft SEIS available for comments 03/2015 Public Meeting - Byron draft SEIS meeting 02/2015 ENCLOSURE

Public Meeting - Braidwood draft SEIS meeting 04/2015 End of draft SEIS comment period - Byron 03/2015 End of draft SEIS comment period - Braidwood 05/2015 Issue final SER 07/2015 ACRS full committee meeting 09/2015 Issue final SEIS - Byron 07/2015 Publish EPA FRN - availability of final SEIS - Byron 08/2015 Issue final SEIS - Braidwood 09/2015 Publish EPA FRN - availability of final SEIS - Braidwood 09/2015 Decision - Director, NRR 11/2015 Commission decision, if hearing granted TBD

Letter to M. Gallagher from C. Miller dated January 29, 2015

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE BYRON AND BRAIDWOOD STATIONS, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NO. MF1832, MF1833, MF1792, MF1793, MF1879, MF1880, MF1881, AND MF1882)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1Resource RidsNrrDlrRpb2Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource