Other: ML13212A367, ML14050A304, ML14071A620, ML14072A369, ML14092A346, ML14177A430, ML14238A691, ML14245A371, ML14300A218, ML14317A783, ML15027A196, ML15098A181, ML15106A736, RS-14-183, Updated Responses to NRC Set 14 Requests for Additional Information, Related License Renewal Application, RS-14-249, Results of Detailed Review Performed in Response to Request 1 of NRC RAI B.2.1.7-7 from Set 17, Related to License Renewal Application, RS-15-049, Units 1 and 2 - LRA Impact Assessment Associated with Earlier Responses to Set 29 RAI B.2.1 .5-1a, Related to the License Renewal Application, ULNRC-06118, Updated RAI Response to the License Renewal Application, Enclosures 1 and 2
|
MONTHYEARML13212A3672013-08-12012 August 2013 Plan for the Aging Management Program Regulatory Audits Regarding the Byron and Braidwood Nuclear Stations License Renewal Application Review Project stage: Other ML13262A0352013-10-0707 October 2013 Requests for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application -Aging Management, Set 1 Project stage: RAI ML13281A5572013-10-28028 October 2013 Summary of Telephone Conference Call Held on September 25, 2013 Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning RAIs Pertaining to the Byron-Braidwood License Renewal Application (TAC Nos. MF187 Project stage: RAI ML13303B4632013-11-25025 November 2013 Summary of Telephone Conference Call Held on October 22, 2013, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning RAI Set 3 for the Byron-Braidwood LRA Project stage: RAI ML13281A5742013-11-25025 November 2013 Requests for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Aging Management, Set 3 (TAC Nos. MF1879, MF1880, MF1881, and MF1882 Project stage: RAI ML13281A5692013-12-12012 December 2013 Request for Additional Information for the Review of the Byron Nuclear Station Units 1 and 2, and the Braidwood Nuclear Station Units 1 and 2, LRA - Aging Management, Set 4 Project stage: RAI ML13282A3692013-12-13013 December 2013 Requests for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Aging Management, Set 2 Project stage: RAI RS-13-273, Responses to NRC Requests for Additional Information, Set 3, Dated November 25, 2013, Related to the License Renewal Application2013-12-17017 December 2013 Responses to NRC Requests for Additional Information, Set 3, Dated November 25, 2013, Related to the License Renewal Application Project stage: Response to RAI RS-13-274, Response to NRC Requests for Additional Information, Set 5, Dated November 22, 2013, Related to License Renewal Application2013-12-19019 December 2013 Response to NRC Requests for Additional Information, Set 5, Dated November 22, 2013, Related to License Renewal Application Project stage: Response to RAI ML13317A0752014-01-13013 January 2014 Requests for Additional Information for Review of Byron, Units 1 & 2, and Braidwood, Units 1 & 2, License Renewal Applications, Set 6 Project stage: RAI RS-14-003, Bryon, Units 1 and 2, Response to NRC Requests for Additional Information, Set 2, Dated December 13, 2013, Related to the License Renewal Application2014-01-13013 January 2014 Bryon, Units 1 and 2, Response to NRC Requests for Additional Information, Set 2, Dated December 13, 2013, Related to the License Renewal Application Project stage: Response to RAI ML14017A0072014-01-16016 January 2014 Enclosure 1 to ULNRC-06072, Callaway Plant, Unit 1, Responses to Request for Additional Information (RAI) Sets 29 and 27 (RAI B2.1.6-4b) Project stage: Response to RAI ML14007A6582014-01-22022 January 2014 Requests for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 9 Project stage: RAI ML13309A9322014-01-23023 January 2014 Summary of Telephone Conference Call Held on October 31, 2013, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Byron Station and Braid Project stage: Draft RAI ML13330A9322014-01-23023 January 2014 Bbs Record of Conference Call-Regarding-RAI Set 4 110513 Project stage: RAI ML13318A4152014-01-23023 January 2014 November 12, 2013, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Byron Station and Braidwo Project stage: Draft RAI RS-14-030, Response to NRC Requests for Additional Information, Set 6, Dated January 13, 2014, Related to License Renewal Application2014-02-0404 February 2014 Response to NRC Requests for Additional Information, Set 6, Dated January 13, 2014, Related to License Renewal Application Project stage: Response to RAI ML14006A0212014-02-0606 February 2014 Requests for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application- Aging Management, Set 8 Project stage: RAI ML14023A5642014-02-0707 February 2014 RAI for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 13 Project stage: RAI ML14030A5962014-02-10010 February 2014 Requests for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 12 Project stage: RAI ML14007A6032014-02-18018 February 2014 Request for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, LRA - Aging Management - Set 17 Project stage: RAI ML14034A0682014-02-18018 February 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 11 Project stage: RAI ML14035A5342014-02-20020 February 2014 January 22, 2014, Summary of Telephone Conference Call Held Between NRC and Exelon Generation Company, Llc., Concerning Draft Requests for Additional Information Pertaining to the Byron Station and Braidwood Station, License Renewal Applica Project stage: Draft RAI ML14035A1892014-02-20020 February 2014 Summary of Telephone Conference Call Held on January 30, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Draft Request for Additional Information Pertaining to the Byron Station and Braidw Project stage: Draft RAI ML14050A1222014-02-24024 February 2014 Summary of Telephone Conference Call Held on January 16, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning RAI Set 7, Tor the Byron-Braidwood License Renewal Application (TAC Nos. MF1879, Mf Project stage: RAI ML14038A3362014-02-26026 February 2014 Request for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Aging Management - Set 10 Project stage: RAI RS-14-051, Response to NRC Requests for Additional Information, Set 8, Dated February 6, 2014 Related to the License Renewal Application2014-02-27027 February 2014 Response to NRC Requests for Additional Information, Set 8, Dated February 6, 2014 Related to the License Renewal Application Project stage: Response to RAI ML14063A4952014-03-0404 March 2014 Response to NRC Requests for Additional Information, Set 13, Dated February 7, 2014 Re License Renewal Application Project stage: Response to RAI ML14051A4312014-03-0404 March 2014 Summary of Telephone Conferene Call Held on January 29, 2014, Between the NRC and Exelon Generating Company, Llc., Concerning RAI Set 10, for the Byron and Braidwood Station License Renewal Application (TAC Nos. MF1879, MF1880, MF1881, and Project stage: RAI ML14036A3102014-03-0404 March 2014 Summary of Telephone Conference Call Held on January 28, 2014, Between NRC and Exelon, Concerning RAI Set 10, for the Byron and Braidwood Station, LRA Project stage: RAI ML14050A1672014-03-0404 March 2014 Summary of Telephone Conference Call on January 23, 2014, Between U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning RAI Set 11, for Byron-Braidwood License Renewal Application (TAC Nos. MF1879, MF1880, MF1881 Project stage: RAI ML14051A4282014-03-0606 March 2014 January 13, 2014, Summary of Telephone Conference Call Held Between the NRC and Exelon RAI Set 8, for the Byron and Braidwood Station LRA Project stage: RAI ML14050A0812014-03-0707 March 2014 Correction to Request for Additional Information B.2.1.10-1, Letter Dated February 7, 2014, for the Review of the Byron Station and Braidwood Station, Units 1 and 2, LRA Set 13 Project stage: RAI ML14064A3912014-03-11011 March 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 15 Project stage: RAI ML14064A4032014-03-11011 March 2014 Summary of Telephone Conference Call on February 27, 2014, Between U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC Concerning Draft Request for Additional Information Re Byron Station & Braidwood Station License Renewal Project stage: Draft RAI ML14058B1802014-03-11011 March 2014 Summary of Telephone Conference Call on February 18, 2014, Between U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC Concerning Draft Request for Additional Information Regarding Byron & Braidwood Stations, License Renewal Project stage: Draft RAI ML14072A3692014-03-13013 March 2014 AMP Audit Enclosure (3) Project stage: Other ML14071A6202014-03-13013 March 2014 Aging Management Programs Audit Report Regarding the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 (Tac Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: Other ML14050A3042014-03-14014 March 2014 Scoping and Screening Methodology Audit Report Regarding the Byron Station, and Braidwood Station, Units 1 and 2, LRA Project stage: Other ML14058B1822014-03-18018 March 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 14 Project stage: RAI ML14051A5032014-03-20020 March 2014 Request for Additional Information for the Review of the Byron Nuclear Station Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Set 17 Project stage: RAI RS-14-084, Responses to NRC Requests for Additional Information, Set 10, Dated February 26, 2014 Related to the License Renewal Application2014-03-28028 March 2014 Responses to NRC Requests for Additional Information, Set 10, Dated February 26, 2014 Related to the License Renewal Application Project stage: Response to RAI ML14073A7052014-04-0303 April 2014 Summary of Telephone Conference Call Held on February 12, 2014, Between the NRC and Exelon, Concerning Drais Pertaining to the Byron and Braidwood Station, LRA Project stage: RAI ML14084A3352014-04-0303 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 16 Project stage: RAI ML14084A4882014-04-0707 April 2014 Summary of Telephone Conference Call Held Between NRC and Exelon Generation Company, LLC, Concerning Draft Request for Additional Information Pertaining to the Byron and Braidwood License Renewal Application Set 16 Project stage: Draft RAI ML14092A2612014-04-0707 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 20 Project stage: RAI ML14092A3462014-04-0707 April 2014 Project Manager Change for the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 Project stage: Other ML14094A3662014-04-0808 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 19 Project stage: RAI ML14093B2472014-04-10010 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 18 Project stage: RAI ML14099A4852014-04-17017 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 & 2, and Braidwood Station, Units 1 & 2, License Renewal Application, Set 21, Project stage: RAI 2014-02-27
[Table View] |
Summary of Telephone Conference Call Held on March 19, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC Concerning Draft Request for Additional Information, Set 18, Pertaining to the Byron Station and| ML14094A275 |
| Person / Time |
|---|
| Site: |
Byron, Braidwood  |
|---|
| Issue date: |
05/19/2014 |
|---|
| From: |
Robinson L License Renewal Projects Branch 1 |
|---|
| To: |
Gallagher M Exelon Generation Co |
|---|
| Robinson L, 415-4115 |
| References |
|---|
| TAC MF1879, TAC MF1880, TAC MF1881, TAC MF1882 |
| Download: ML14094A275 (7) |
|
Text
May 19, 2014 LICENSEE:
Exelon Generation Company, LLC FACILITY:
Byron Station, Units 1 and 2 Braidwood Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 19, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 18, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF1879, MF1880, MF1881, MF1882)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on March 19, 2014, to discuss and clarify the staffs draft request for additional information (DRAI),
Set 18, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAIs.
provides a listing of the participants, and Enclosure 2 contains a listing of the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Lindsay Robinson, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455, 50-456, and 50-457
Enclosures:
- 1. List of Participants
- 2. List of Draft Request for Additional Information cc w/encls: Listserv
ML14094A275
- concurred via email OFFICE LA:DLR*
PM: RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds LRobinson YDiazSanabria LRobinson DATE 5/8/14 5/14/14 5/15/14 5/19/14
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 19, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 18, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION, SET 18 (TAC NOS. MF1879, MF1880, MF1881, MF1882)
DISTRIBUTION EMAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsOgcMailCenter RidsNrrPMByron Resource RidsNrrPMBraidwood Resource LRobinson DMcIntyre, OPA EDuncan, RIII JBenjamin, RIII AGarmoe, RIII JMcGhee, RIII JRobbins, RIII VMitlyng, RIII PChandrathil, RIII
ENCLOSURE 1 TELEPHONE CONFERENCE CALL BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS March 19, 2014 PARTICIPANTS AFFILIATIONS Lindsay Robinson U.S. Nuclear Regulatory Commission (NRC)
William Holston NRC John Wise NRC Allen Hiser NRC Aloysius Obodoako NRC Ken Karwoski NRC John Hufnagel Exelon Generating Company, LLC (Exelon)
Don Warfel Exelon Al Fulvio Exelon Albert Piha Exelon Gary Becknell Exelon Al Fulvio Exelon Casey Muggleston Exelon Don Brindle Exelon
ENCLOSURE 2 DRAFT REQUEST FOR ADDITIONAL INFORMATION BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION March 19, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on March 19, 2014, to discuss and clarify the following draft request for additional information (DRAI), Set 18, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application (LRA).
DRAI 3.1.2.3.4-1 Applicability:
Byron and Braidwood, Unit 1
Background:
License renewal application (LRA) Table 3.1.2-4 addresses loss of fracture toughness in steam generator internal structural supports exposed to treated water > 482 ºF at Byron and Braidwood Stations, Unit 1. The LRA states that the steam generator tube support lattice bar is fabricated from SA-240 410S martensitic stainless steel (SS), and the steam generator tube support lattice bar attachment component is fabricated from SA-351 CF3M cast austenitic SS. The LRA Table provides a note H for this component, material, and environment. Note H states that this aging effect (i.e., loss of fracture toughness) is not in NUREG-1801 for the component, material, and environment combination. Visual inspections and eddy current testing were proposed to manage this degradation mechanism.
Issue:
The staff needs additional information concerning the degradation mechanism and the component/environment to ascertain whether the proposed aging management program is adequate.
Request:
Please provide a description briefly discuss the nature of these components (including their function) and the extent to which they are used throughout the steam generator; a sketch/diagram may be useful. Please discuss the susceptibility of these particular components to thermal aging embrittlement (
Reference:
Letter from C.I. Grimes, NRC, to Douglas J.
Walters, Nuclear Energy Institute, License Renewal Issue No. 98-0030, Thermal Aging Embrittlement of Cast Stainless Steel Components, dated May 19, 2000, ML003717179).
Discuss how visual inspections and eddy current testing will be adequate to ensure any loss of fracture toughness that does occur will be limited such that the component will continue to be able to perform its intended safety function during normal operation, transient, and accident conditions. That is, discuss the possibility that the loss of fracture toughness would render the component incapable of performing its function without the component showing any visual evidence of cracking, deformation, or damage.
Discussion: The applicant requested clarification on the staffs request. The applicant requested the staff to identify the applicability of the question and whether there was a need for a sketch or diagram when discussing the steam generator components. The staff agreed to identify the applicability of the question for Byron Unit 1 and Braidwood Unit 1; and after further review, the staff agreed to remove the request for a sketch or diagram. The staff also added eddy currents to the scope of the request as indicated by the underlined portion in the Background and Request sections. All underlined portions indicated additions made to the original DRAI, and the strikethrough indicates a deletion. This question will be sent as a formal RAI titled: RAI 3.1.2.3.4-1.
DRAI 3.0.3-3a Applicability:
Byron and Braidwood
Background:
In a letter dated January 13, 2014, the responses to RAIs 3.0.3-3 and B.2.1.23-1 state that cracking due to stress corrosion cracking is not an aging effect in outdoor air environments for stainless steel and aluminum components that have jacketed insulation.
In regards to potential cracking due to halides in the atmosphere, the responses stated that (a) halide accumulation from the environment is not expected on components that are shielded by jacketed insulation and (b) insulated components located outdoors do not operate at high temperatures where concentration of environmental halides is expected to occur due to evaporation of any present moisture.
The Generic Aging Lessons Learned (GALL) Report aging management program (AMP)
XI.M38, External Surfaces Monitoring of Mechanical Components, recommends visual inspections for leakage to detect cracking on external surfaces that are exposed to an air environment containing halides.
Issue:
The staff recognizes that proper jacketing configuration can be a preventive measure for atmospheric halide intrusion; however, the staff considers a one-time inspection of exposed metal for evidence of cracking as necessary to ensure that the jacketing at Byron and Braidwood is an effective barrier. Also, it is not clear to the staff why the absence of high operating temperatures would prevent moisture from evaporating on an outdoor components surface.
Request:
For insulated stainless steel and aluminum components exposed to outdoor air, provide the technical justification for why exposed metal inspections for cracking are not necessary to confirm the effectiveness of the insulation jacketing in preventing halide intrusion. Alternatively, propose a baseline exposed metal inspection for cracking that may be used to validate the subsequent use of insulation-only inspections and revise the associated AMR items to include cracking as an applicable aging effect.
Discussion: The applicant requested clarification on the staffs request. Minor editorial comments were addressed. In the Background section, the staff decided to specify visual inspections, as indicated by the underlined portion in the last paragraph. It was noted by the applicant that the GALL Report AMP was improperly listed as XI.M38; it will be correctly labeled: XI.M36. The staff decided to include an additional discussion regarding potential leakage of nonwater-filled piping and piping components and agreed to revise the request per the following:
Request:
For insulated stainless steel and aluminum piping and piping components exposed to outdoor air, provide the technical justification for why insulation does not need to be removed to conduct visual inspections to detect cracking in order to confirm the effectiveness of the insulation jacketing in preventing halide intrusion. Alternatively, propose to remove insulation during a baseline inspection for cracking that may be used to validate the subsequent use of insulation-only inspections and revise the associated AMR items to include cracking as an applicable aging effect. For nonwater-filled piping and piping components, state how potential leakage will be identified.
This question will be sent as a formal RAI titled: RAI 3.0.3-3a.