|
---|
Category:Letter
MONTHYEARRS-24-098, Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality2024-10-23023 October 2024 Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality ML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000456/20240022024-08-0808 August 2024 Integrated Inspection Report 05000456/2024002 and 05000457/2024002 ML24172A1252024-07-26026 July 2024 Environmental Assessment and Finding of No Significant Impact Related to a Requested Increase in Ultimate Heat Sink Temperature (EPID L-2024-LLA-0075) - Transmittal Letter ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24163A3922024-06-25025 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0075)- Letter RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink IR 05000456/20240102024-05-31031 May 2024 License Renewal Phase 1 Report 05000456/2024010 RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24136A0132024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report ML24136A2452024-05-15015 May 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000457/2024004 ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) ML24122A6522024-05-0101 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000456/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000456/2024301; 05000457/2024301 RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A0052024-04-25025 April 2024 Transmittal of Braidwood Station, Unit 1, Core Operating Limits Report, Braidwood Unit 1 Cycle 25 IR 05000456/20240012024-04-24024 April 2024 Integrated Inspection Report 05000456/2024001 and 05000457/2024001 ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) IR 05000457/20240902024-04-19019 April 2024 Final Significance Determination for 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Dilution Issue - NRC Inspection Report 05000457/2024090 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24094A2692024-04-0303 April 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Report, WCAP-17451-P, Revision 2, Reactor Internals Guide Tube Wear Westinghouse Domestic Fleet Operational Projections RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24057A0372024-03-26026 March 2024 Proposed Alternative from Certain Requirements Contained in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML24067A3252024-03-0707 March 2024 U.S. Department of Energy, Office of Legacy Management, 2023 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 IR 05000456/20244012024-03-0505 March 2024 Cyber Security Inspection Report 05000456/2024401 and 05000457/2024401 (Public) IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML24057A3022024-02-26026 February 2024 Regulatory Conference Supplemental Information ML24047A2382024-02-20020 February 2024 Regulatory Conference to Discuss Risk Associated with 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Leak RS-24-013, Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-02-13013 February 2024 Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators IR 05000456/20230042024-02-0202 February 2024 Integrated Inspection Report 05000456/2023004 and 05000457/2023004 2024-09-23
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24053A3382024-02-22022 February 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML24039A0412024-01-30030 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Braidwood Request for Alternative (I4R-18) ML23339A0452023-12-0505 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000546/2024010 ML23191A8442023-07-10010 July 2023 05000456; 05000457 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23094A1352023-04-0404 April 2023 Request for Information for Nrc Commercial Grade Dedication Inspection Inspection Report 05000456/2023010 05000457/2023010 ML23069A0342023-03-0606 March 2023 Unit 1 Lr Commitment 10 RAI Set 1 - (Non-Proprietary) ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23018A1632023-01-18018 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22241A0522022-08-29029 August 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000456/2022004 05000457/2022004 ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 IR 05000456/20224022022-02-0404 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000456/2022402 05000457/2022402 ML21350A4372021-12-16016 December 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000456/2022010 and 05000457/2022010 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21228A2352021-08-17017 August 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000457/2021004 ML21193A0942021-07-12012 July 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1022021-02-25025 February 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000456/2021010; 05000457/2021010 ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21020A1292021-01-20020 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000456/2021002; 05000457/2021002 ML21004A1452020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Relief Requests Braidwood I4R-11 and Byron I4R-18 ML20289A1142020-10-0909 October 2020 NRR E-mail Capture - Preliminary RAIs for LAR Regarding Non-conservative TS EDG Frequency Tolerance ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20104C1452020-04-10010 April 2020 NRR E-mail Capture - Preliminary RAIs for Exelon'S April 6, 2020, Application to Defer Braidwood, Unit 2, Steam Generator Inspections ML20023A0812020-01-23023 January 2020 NRR E-mail Capture - RAIs for L-2019-LLA-0201 - Braidwood, Units 1 and 2, LAR to Revise TS 3.7.9, Ultimate Heat Sink ML19350B2952019-12-16016 December 2019 NRR E-mail Capture - Draft Request for Additional Information Regarding Braidwood Station, Units 1 and 2, Impractical Inservice Inspection Requirements (L-2019-LLA-0081) ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19252C1542019-08-22022 August 2019 NRR E-mail Capture - Issuance of the Remainder of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19232A2242019-08-0707 August 2019 NRR E-mail Capture - Partial Issuance of Final RAIs for Braidwood/Byron TSTF-505 Application ML19207A0672019-07-26026 July 2019 NRR E-mail Capture - Partial Issuance of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19128A2362019-05-0202 May 2019 NON- PROPRIETARY- Request for Additional Information- Amendment Request Regarding Utilization of Tvel TVS-K Lead Test Assemblies Braidwood Station, Units 1 and 2 ML19066A0432019-03-0707 March 2019 NRR E-mail Capture - Preliminary RAIs for Quality Assurance Review of Braidwood Tvel LTA Application ML18324A8072018-12-12012 December 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action One-Time Extension of Technical Specification 3.8.1, AC Sources-Operating, A2 Completion Time ML18192C1712018-07-11011 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Braidwood Station, Units 1 and 2, Relief Request IR4-03 ML18190A4072018-07-0505 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Braidwood Station, Units 1 and 2, Relief Request IR4-06 ML18150A6902018-05-30030 May 2018 NRR E-mail Capture - Preliminary RAIs Regarding Braidwood TORMIS Amendment Request ML18149A2842018-05-24024 May 2018 NRR E-mail Capture - B/B 50.69 RAI - Potential Typo ML18135A2202018-05-15015 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood Relief Request IR4-05 ML18129A1082018-05-0909 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood and Byron Stations 50.69 Amendment 2024-09-23
[Table view] |
See also: IR 05000457/2021004
Text
August 17, 2021
Mr. David Rhoades
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: BRAIDWOOD GENERATING STATION, UNIT 2NOTIFICATION OF NRC
BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
REPORT 05000457/2021004
Dear Mr. Rhoades:
On October 18, 2021, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline
Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed
October 18, 2021, through October 28, 2021.
Experience has shown that this inspection is resource intensive both for the NRC inspector and
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
inspection for both sides, we have enclosed a request for documents needed for this inspection.
These documents have been divided into two groups.
The first group identifies information necessary to ensure that the inspector is adequately
prepared. The second group identifies the information the inspector will need upon arrival at the
site. It is important that all of these documents are up-to-date, and complete, in order to
minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We have discussed the schedule for inspection activities with your staff and understand that
our regulatory contact for this inspection will be Mr. R. Schliessmann of your organization. If
there are any questions about this inspection or the material requested, please contact the
lead inspector John V. Bozga at 630-829-9613.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
D. Rhoades -2-
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
Exemptions, Requests for Withholding.
Sincerely,
Signed by Bozga, John
on 08/17/21
John V. Bozga, Senior Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket No. 50-457
License No. NPF-77
Enclosure:
Document Request for Inservice
Inspection
cc: Distribution via LISTSERV
D. Rhoades -3-
Letter to David Rhoades from John V. Bozga dated August 17, 2021.
SUBJECT: BRAIDWOOD GENERATING STATION, UNIT 2NOTIFICATION OF NRC
BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
REPORT 05000457/2021004
DISTRIBUTION:
Jessie Quichocho
Aaron McCraw
RidsNrrDorlLpl3
RidsNrrPMBraidwood Resource
RidsNrrDroIrib Resource
John Giessner
Mohammed Shuaibi
Jamnes Cameron
Allan Barker
DRPIII
DRSIII
ADAMS Accession Number: ML21228A235
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
OFFICE RIII
NAME JBozga:mb
DATE 08/17/2021
OFFICIAL RECORD COPY
DOCUMENT REQUEST FOR INSERVICE INSPECTION
Inspection Report: 05000457/2021004
Inspection Dates: October 18, 2021 - October 28, 2021
Inspection Procedures: Inspection Procedure 71111-08, Inservice Inspection
Lead Inspector: John V Bozga, DRS
630-829-9613
A. Information for the In-Office Preparation Week
The following information (electronic copy) is requested by October 4, 2021, to facilitate
the selection of specific items that will be reviewed during the onsite inspection week.
The inspector will select specific items from the information requested below and request
a list of additional documents needed onsite to your staff. We request that the specific
items selected from the lists be available and ready for review on the first day of
inspection. The following information is applicable to the outage Unit unless otherwise
indicated. If you have any questions regarding this information, please call the inspector
as soon as possible.
1. For the upcoming outage, a detailed schedule and description of:
a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems and
containment, performed as part of your American Society of Mechanical
Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition and
addenda of Code committed to), and NDEs planned for other systems performed
as part of a Risk-Informed ISI Program, or other augmented inspection programs
(e.g., ASME Code Case N-770 examination of dissimilar metal welds and
examinations to meet an industry initiative);
b. Reactor vessel upper head examinations required by Title 10 of the Code of
Federal Regulations (CFR), Part 50.55a(g)(6)(ii)(D) and Code Case N-729;
c. Steam generator (SG) tube inspection and repair activities for the upcoming
outage or SG secondary side examinations1; and
d. Welding on Code Class 1, 2, or 3 components. For each weld examination,
include the weld identification number, description of weld (component name),
category, class, type of exam and procedure number, and date of examination.
2. A copy of the NDE procedures, SG eddy current examination (ET) acquisition and
analysis procedures, and welding procedures used to perform the activities identified
in Item A.1 (including NDE calibration and flaw characterization/sizing procedures
and Welding Procedure Qualification Records). For ultrasonic examination
1 Note 1 - If no SG examinations are planned for this outage, please confirm when the next SG examination will
occur and no further information is required for the items identified above requesting SG related information.
Enclosure
DOCUMENT REQUEST FOR INSERVICE INSPECTION
procedures qualified in accordance with Appendix VIII, of Section XI of the ASME
Code, provide documentation supporting the procedure qualification (e.g., the
Electric Power Research Institute performance demonstration qualification summary
sheets). For SG tube ET this includes the acquisition and analysis procedures.
3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations
identified in Item A.1.
4. A copy of the 10-year ISI Program showing those required exams scheduled to be
performed this outage, and those which have been completed.
5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye
penetrant), which have identified relevant indications on Code Class 1 and 2
Systems since the beginning of the last refueling outage.
6. List of repair/replacement welds in Code Class 1, 2 and 3 Systems, which have been
fabricated since the beginning of the last refueling outage and identify the system,
weld number, and reference applicable documentation (e.g., NIS-2 forms with
definitions of system and component acronyms).
7. List of reactor vessel weld examinations required by the ASME Code that are
scheduled to occur during the upcoming refueling outage, and please provide a
detailed description of the welds and the extent of the planned examination.
8. Corrective action list of ISI and SG-related issues such as piping or SG tube
degradation or damage (e.g., cracks, wall thinning, wear, microbiologically induced
corrosion) or errors identified during piping/SG tube examinations since the
beginning of the last refueling outage. Also, include a list of corrective actions
associated with foreign material in the reactor vessel, primary coolant system, SG or
feed systems since the beginning of the last refueling outage.
9. 10 CFR Part 21 reports applicable to your structures, systems, or components within
the scope of ASME Code Section XI that have been identified since the beginning of
the last refueling outage.
10. Copy of SG history documentation given to vendors performing ET of the SGs during
the upcoming outage1.
11. Copy of procedure containing screening criteria used for selecting tubes for in-situ
pressure testing and the procedure to be used for in-situ pressure testing1.
12. Copy of previous outage SG tube operational assessment completed following ET of
the SGs (provide this document even if no SG ET is planned for current outage).
13. Copy of most recent SG Degradation Assessment (provide this document even if no
SG ET is planned for current outage).
14. Copy of most recent SG Condition Monitoring Assessments1.
1 Note 1 - If no SG examinations are planned for this outage, please confirm when the next SG examination will
occur and no further information is required for the items identified above requesting SG-related information.
2
DOCUMENT REQUEST FOR INSERVICE INSPECTION
15. Copy of the document defining the planned SG ET scope (e.g., 100 percent of
unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion
transition regions with rotating probe) and identify the scope expansion criteria,
which will be applied. Also identify and describe any deviations in this scope or
expansion criteria from the Electric Power Research Institute Guidelines1.
16. Copy of the document describing the ET acquisition equipment to be applied
including ET probe types. Also identify the extent of planned tube examination
coverage with each probe type (e.g., rotating probe - 0.080 inches, 0.115 inches
pancake coils and mid-range + point coil applied at the top-of-tube-sheet plus
3 inches to minus 12 inches)1.
17. Provide procedures with guidance/instructions for identifying (e.g., physically locating
the tubes that require repair) and plugging SG tubes1.
18. Identify and quantify any SG tube leakage experienced during the previous operating
cycle. Also provide documentation identifying which SG was leaking and corrective
actions completed or planned for this condition.
19. Point of contact information (name and site number) for the following activities:
a. ISISite and vendor leads;
b. Boric Acid Inspections and Evaluations;
c. Reactor Vessel Head InspectionSite and vendor leads;
d. SG InspectionSite and vendor leads;
e. Aging Management Programs; and
f. Site Welding Engineer.
B. Onsite Information to Be Provided to the Inspector on the First Day of the
Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies
(e.g., Paper Records) of the Following Documents.
1. For welds selected by the inspector from Item A.1.d and A.6 above, provide copies of
the following documents:
a. Document of the weld number and location (e.g., system, train, branch);
b. Document with a detail of the weld construction (e.g., drawing);
c. Applicable portions of the Design Specification and applicable Code of
construction for the weldment (e.g., B31.1 or ASME Section III);
d. Applicable Code Edition and Addenda for weld procedure qualification;
1 Note 1 - If no SG examinations are planned for this outage, please confirm when the next SG examination will
occur and no further information is required for the items identified above requesting SG related information.
3
DOCUMENT REQUEST FOR INSERVICE INSPECTION
e. Applicable weld procedure specifications and weld data sheets used to fabricate
the welds;
f. Copies of procedure qualification records supporting the weld procedure
specifications;
g. Copies of welders performance qualification records;
h. Copies of mechanical test reports identified in the weld procedure qualification
records above;
i. Copies of the nonconformance reports for the selected welds;
j. Access to radiographs and equipment to view radiographs of the selected welds;
k. ASME Code Section XI repair replacement plan and reconciliation for
replacement components/materials;
l. Certified Material Test Reports for replacement pressure boundary materials; and
m. Copies of the NDE required by the construction Code and the pre-service
examination records required by the ASME Code Section XI for the selected
welds.
2. For the ISI-related corrective action issues selected by the inspector from Item A.8
above, provide a copy of the corrective actions and supporting documentation.
3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems
selected by the inspector from Item A.5 above, provide a copy of the examination
records and associated corrective action documents.
4. Updated schedules for Item A.1 (including schedule showing contingency repair
plans if available).
5. Fabrication Drawings (D size) of the reactor vessel welds (including vessel head
J-groove welds) if any are to be examined during the outage. Also provide any
drawings used by NDE vendors to locate these welds.
6. Copy of the procedures which govern the scope, equipment used, and
implementation of the inspections required to identify boric acid leakage fromsystems
and components above the vessel head.
7. Copy of:
a. Engineering evaluations/assessments of boric acid related deposits and
associated wastage or corrosion for safety-related components; and
b. Corrective action records for coolant leakage including boric acid deposits on
safety-related components identified since the beginning of the last refueling
outage.
4
DOCUMENT REQUEST FOR INSERVICE INSPECTION
8. Copy of the plant procedures used to perform inspections to identify reactor coolant
system leaks or boric acid deposits and the procedures for resolution of leaks or
boric acid deposits.
9. Copy of the documents which demonstrate that the procedures to be used for
volumetric examination of the reactor vessel head penetration J-groove welds were
qualified by a blind demonstration test in accordance with 10 CFR
Part 50.55a(g)(6)(ii)(D).
10. Copy of volumetric, surface and visual examination records for the prior inspection of
the reactor vessel head and head penetration J-groove welds.
11. Provide a copy of the Electric Power Research Institute Examination Technique
Specification Sheets and vendor related documents, which support qualification of
the ET probes to be used during the upcoming SG tube inspections1.
12. Provide a copy of the guidance to be followed if a loose part or foreign material is
identified in the SGs1.
13. Identify the types of SG tube repair processes which will be implemented for
defective SG tubes (including any U.S. Nuclear Regulatory Commission
reviews/evaluation/approval of this repair process). Provide the flaw depth sizing
criteria to be applied for ET indications identified in the SG tubes1.
14. Copy of document describing actions to be taken if a new SG tube degradation
mechanism is identified1.
15. Provide document which defines the scope of SG secondary side examinations (if
any are planned) and identify site specific operational history related to degradation
of SG secondary side components (if any).
16. Provide procedures with guidance/instructions for identifying (e.g., physically locating
the tubes that require repair) and plugging SG tubes1.
17. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory
Commission inspection location for the duration of the inspection:
a. Sections V, IX, and XI of the ASME Code with Editions applicable to the
ISIProgram and the Repair/Replacement Program;
b. Copy of the performance demonstration initiative (PDI) generic procedures with
the latest applicable revisions that support site qualified ultrasonic examination of
piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-10
etc.);
c. Electric Power Research Institute and industry standards referenced in the site
procedures used to perform the SG tube ET, which includes Electric Power
Research Institute documents: SG Examination Guidelines, SG Integrity
1 Note 1 - If no SG examinations are planned for this outage, please confirm when the next SG examination will
occur and no further information is required for the items identified above requesting SG related information.
5
DOCUMENT REQUEST FOR INSERVICE INSPECTION
Assessment Guidelines, SG In-Situ Pressure Test Guidelines1; and
d. Boric Acid Corrosion Guidebook Revision 1Electric Power Research Institute
Technical Report 1000975.
If you have questions regarding the information requested, please contact the lead inspector.
1 Note 1 - If no SG examinations are planned for this outage, please confirm when the next SG examination will
occur and no further information is required for the items identified above requesting SG related information.
6