Letter Sequence RAI |
---|
EPID:L-2021-LLA-0066, Response to Request for Additional Information Regarding License Amendment Request to Address the Issues Identified in Westinghouse Documents NSAL-09-5, Rev.1 and NSAL-15-1, Rev. 0 (Approved, Closed) |
|
MONTHYEARML21123A2442021-05-0303 May 2021 NRR E-mail Capture - NRC Acceptance Review of Braidwood/Byron/Ginna - Application to Address the Issues Identified in Westinghouse Documents NSAL-09-5 and NSAL-15-1 (L-2021-LLA-0066) Project stage: Acceptance Review ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs Project stage: RAI ML21225A0052021-08-13013 August 2021 Response to Request for Additional Information Regarding License Amendment Request to Address the Issues Identified in Westinghouse Documents NSAL-09-5, Rev.1 and NSAL-15-1, Rev. 0 Project stage: Request ML22026A4892022-03-22022 March 2022 Issuance of Amendment Nos. 225, 225, 227, 227, and 148, Respectively, Regarding Issues Identified in Westinghouse Documents (EPID L-2021-LLA-0066) Nonproprietary Project stage: Approval ML22145A5862022-06-0303 June 2022 R. E. Ginna Correction to Pages Issued for Amendments Nos. 225, 225, 227, 227, & 148, Respectively, Regarding Issues Identified in Westinghouse Documents Project stage: Other 2021-08-13
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24298A0202024-10-24024 October 2024 NRR E-mail Capture - Braidwood Station, Units 1 and 2, Byron Station, Units 1 and 2, Relief Request I4R-19 and I4-26, Associated with the Fourth and Fifth Inservice Inspection Intervals ML24282A7042024-10-0808 October 2024 NRR E-mail Capture - Acceptance Reviews of Relief Requests Associated with the Fifth Inservice Inspection Interval at Byron and Braidwood Stations ML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24180A0032024-06-28028 June 2024 NRR E-mail Capture - NRC Acceptance Review of Byron/Braidwood Amendment for Transition to Framatome Gaia Fuel (L-2024-LLA-0072) ML24180A0042024-06-28028 June 2024 NRR E-mail Capture - Acceptance Review for Braidwood and Byron - Request for Exemption from 10 CFR 50.46 and Appendix K (L-2024-LLE-0019) ML24306A0072024-06-26026 June 2024 NRR E-mail Capture - Verbal Relief for Byron, Unit 2, Three Specific Air-operated Valves in the Essential Service Water System (L-2024-LLR-0042) ML24176A0182024-06-20020 June 2024 NRR E-mail Capture - NRC Acceptance Review of Byron/Braidwood Amendment to Remove Extraneous Detail Related to Beacon ML24170A3912024-06-18018 June 2024 NRR E-mail Capture - Revision of Estimated Hours to Complete Review of Byron/Braidwood Amendment to Revise TS 3.7.15, 3.7.16, and 4.3.1 (L-2023-LLA-0136) ML24141A2452024-05-20020 May 2024 NRR E-mail Capture - NRC Acceptance Review of Byron/Braidwood Amendment to Delete Technical Specification 5.6.5.b.5 (L-2024-LLA-0055) ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24073A3602024-03-13013 March 2024 Request for Additional Information (RAI) Alternative Request PR-03 Sixth Interval Inservice Testing Program ML24053A3382024-02-22022 February 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML24045A2892024-02-14014 February 2024 R. E. Ginna Nuclear Power Plant Acceptance Review: IST Relief Request for B Auxiliary Feedwater Pump ML24039A0412024-01-30030 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Braidwood Request for Alternative (I4R-18) ML24030A0022024-01-30030 January 2024 NRR E-mail Capture - NRC Acceptance Review for Braidwood Station, Units 1 and 2, Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators ML23317A2012023-11-22022 November 2023 (External_Sender) Supplement - Byron Security Rule Exemption Request – ISFSI Docket No. Reference ML23331A8922023-11-22022 November 2023 Supplement - Braidwood Security Rule Exemption Request – ISFSI Docket No. Reference ML23321A2012023-11-17017 November 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML23311A1692023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Exam Categories B-B, B-D, and C-A SG Pressure Retaining Welds and Full Penetration Welded Nozzles (L-2023-LLR-0055 and L-2023-LLR-00 ML23311A1682023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (L-2023-LLR-0053 and L-2023-LLR-005 ML23312A1302023-11-0707 November 2023 Final Rci/Rai - Constellation – R. E. Ginna Nuclear Power Plant - Exemption from Security Rule (EPID L-2023-LLE-0029) (Email) ML23305A2992023-11-0101 November 2023 NRR E-mail Capture - NRC Acceptance Review of Byron, Unit 2, Relief Request I4R-24 ML23304A0202023-10-30030 October 2023 NRR E-mail Capture - Final RCI - Constellation Energy Generation, LLC - Byron 1 & 2 - Exemption from Security Rule (L-2023-LLE-0027) ML23304A0222023-10-30030 October 2023 NRR E-mail Capture - Final RCI - Constellation Energy Generation, LLC - Braidwood 1 & 2 - Exemption from Security Rule (L-2023-LLE-0030) ML23272A0602023-09-29029 September 2023 NRR E-mail Capture - NRC Acceptance Review of Byron, Unit 1, Relief Request I4R-25 ML23187A0092023-07-0606 July 2023 NRR E-mail Capture - NRC Acceptance Review of Byron and Braidwood Request to Adopt TSTF-370 ML23103A4692023-04-12012 April 2023 NRR E-mail Capture - NRC Acceptance Review of Braidwood Request for Amendment to Revise TS 3.7.9 ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23115A2412023-01-20020 January 2023 NRR E-mail Capture - Preliminary RAIs Related to L-2022-LLA-0131 - Byron, Unit 2, Reinsertion of an Accident Tolerant Fuel Lead Test Assembly ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22325A0052022-11-18018 November 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-273-A, Revision 2 ML22284A1022022-10-0606 October 2022 NRR E-mail Capture - NRC Acceptance Review for Byron, Unit 2, License Amendment Request (LAR) to Reinsert an Accident Tolerant Fuel (ATF) Lead Test Assembly (LTA) (L-2022-LLA-0131) ML22339A0032022-09-28028 September 2022 R. E. Ginna Nuclear Power Plant - Ginna: Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report ML22269A4522022-09-22022 September 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report (COLR) NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22255A0132022-09-0909 September 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, Calvert Cliffs, Ginna - License Amendment Request to Adopt TSTF-577 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22189A0602022-07-0707 July 2022 NRR E-mail Capture - Draft RAI for Byron/Braidwood TSTF-501 ML22136A2722022-05-16016 May 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood and Byron Adoption of TSTF-501 ML22138A1672022-05-16016 May 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review TS to Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes (EPID-L-2022-LLA-0057) ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22116A0242022-04-25025 April 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, and Ginna Request to Adopt TSTF-246 ML22105A0722022-04-15015 April 2022 NRR E-mail Capture - Braidwood/Byron Verbal Authorization for Proposed Alternative I4R-15/I4R-21 ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22088A1562022-03-0202 March 2022 NRR E-mail Capture - Byron, Braidwood, Calvert Cliffs, and Ginna - Non-acceptance of Application to Revise Technical Specifications 5.6.5.b, the Core Operating Limits Report (COLR) ML22091A0842022-02-24024 February 2022 NRR E-mail Capture - Braidwood and Byron - Withdrawal of Draft RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24297A2702024-10-23023 October 2024 Notification of NRC Baseline Inspection and Request for Information: Inspection Report 05000455/2025002 ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary ML24250A1182024-09-0606 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24113A2892024-04-22022 April 2024 Notification of NRC Baseline Inspection and Request for Information ML24073A3602024-03-13013 March 2024 Request for Additional Information (RAI) Alternative Request PR-03 Sixth Interval Inservice Testing Program ML24053A3382024-02-22022 February 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML24039A0412024-01-30030 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Braidwood Request for Alternative (I4R-18) ML23339A0452023-12-0505 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000546/2024010 ML23312A1302023-11-0707 November 2023 Final Rci/Rai - Constellation – R. E. Ginna Nuclear Power Plant - Exemption from Security Rule (EPID L-2023-LLE-0029) (Email) ML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection ML23209A7242023-07-31031 July 2023 Request for Information on the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000454/2024010 and 05000455/2024010 ML23198A0372023-07-17017 July 2023 Information Request to Support Upcoming Problem Identification and Resolution (PIR) Inspection at Byron Nuclear Plant ML23191A8442023-07-10010 July 2023 05000456; 05000457 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23172A1172023-06-22022 June 2023 Notification of NRC Fire Protection Team Inspection Request for Information ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23094A1352023-04-0404 April 2023 Request for Information for Nrc Commercial Grade Dedication Inspection Inspection Report 05000456/2023010 05000457/2023010 ML23069A0342023-03-0606 March 2023 Unit 1 Lr Commitment 10 RAI Set 1 - (Non-Proprietary) ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23115A2412023-01-20020 January 2023 NRR E-mail Capture - Preliminary RAIs Related to L-2022-LLA-0131 - Byron, Unit 2, Reinsertion of an Accident Tolerant Fuel Lead Test Assembly ML23018A1632023-01-18018 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22241A0522022-08-29029 August 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000456/2022004 05000457/2022004 ML22237A0272022-08-25025 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22160A3962022-06-0909 June 2022 R. E. Ginna Nuclear Power Plant, LLC - Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2022010 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 IR 05000454/20220022022-04-26026 April 2022 Unit 2 RFI for an NRC Triennial Heat Exchanger/Sink Performance Inspection and RFI IR 05000454/2022002 05000455/2022002 ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 IR 05000456/20224022022-02-0404 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000456/2022402 05000457/2022402 ML21350A4372021-12-16016 December 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000456/2022010 and 05000457/2022010 ML21308A5592021-11-0404 November 2021 NRR E-mail Capture - NRC Request for Additional Information for Ginna Biennial EP Exercise Exemption Request ML21273A3312021-10-0404 October 2021 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Byron Station ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21228A2352021-08-17017 August 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000457/2021004 ML21203A3112021-07-21021 July 2021 NRR E-mail Capture - Final Byron Permanently Defueled Technical Specifications (PDTS) - Second Round RAI ML21193A0942021-07-12012 July 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21189A1612021-07-0808 July 2021 NRR E-mail Capture - Second Round Request for Additional Information - Byron Permanently Defueled Technical Specification Amendment ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21119A1082021-04-27027 April 2021 Ti 2515/194 Inspection Documentation Request ML21076A5152021-03-17017 March 2021 R. E. Ginna Nuclear Power Plant - RAI Steam Generator LAR to Revise Technical Specifications for Steam Generator Tube Inspection Frequency (EPID L-2020-LLA-0207) (e-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1022021-02-25025 February 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000456/2021010; 05000457/2021010 ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21036A1102021-02-0404 February 2021 NRR E-mail Capture - Draft RAIs for Byron Station, Unit Nos. 1 and 2, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21020A1292021-01-20020 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000456/2021002; 05000457/2021002 2024-09-06
[Table view] |
Text
From: Wiebe, Joel Sent: Thursday, July 8, 2021 8:44 AM To: 'Jessie.Hodage@exeloncorp.com' Cc: 'Henderson, Phillip A:(Exelon Nuclear)'
Subject:
Request for Additional Information - Braidwood, Byron, and Ginna -
Amendment to Address the Issues in Westinghouse NSALs Attachments: L-2021-LLA-0066 RAI.docx
- Jessie, Let me know if you need a clarification call. A response to the RAI is requested within 30 days of receipt of this request.
Joel
Hearing Identifier: NRR_DRMA Email Number: 1262 Mail Envelope Properties (MN2PR09MB4971457527E247C59402D9C68B199)
Subject:
Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs Sent Date: 7/8/2021 8:43:47 AM Received Date: 7/8/2021 8:43:48 AM From: Wiebe, Joel Created By: Joel.Wiebe@nrc.gov Recipients:
"'Henderson, Phillip A:(Exelon Nuclear)'" <Phillip.Henderson@exeloncorp.com>
Tracking Status: None
"'Jessie.Hodage@exeloncorp.com'" <Jessie.Hodage@exeloncorp.com>
Tracking Status: None Post Office: MN2PR09MB4971.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 144 7/8/2021 8:43:48 AM L-2021-LLA-0066 RAI.docx 29221 Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
REQUEST FOR ADDITIONAL INFORMATION PROPOSED CHANGES TO HEAT FLUX HOT CHANNEL FACTOR TECHNICAL SPECIFICATIONS SELECT EXELON GENERATION UNITS EPID L-2021-LLA-0066
1.0 INTRODUCTION
By application dated April 7, 2021, Exelon Generation (the licensee) requested changes to the Technical Specifications (TSs) for Braidwood Station, Units 1 and 2, Byron Station, Units 1 and 2, and R. E. Ginna Nuclear Power Plant (Braidwood 1 and 2, Byron 1 and 2, and Ginna, respectively) (Agencywide Document Access and Management System Accession No. ML21097A226). The proposed changes would revise Required Actions and Surveillance Requirements associated with TS 3.2.1, Heat Flux Hot Channel Factor (FQ(Z)). These revisions implement a series of more restrictive required actions and more thorough surveillance requirements that are used in instances where the transient heat flux hot channel factor, ,
is not within its operating limits.
Similar required actions and surveillance requirements had been administratively implemented at each facility under the auspices of NRC Administrative Letter (AL) 89-10, Dispositioning of Technical Specifications that are Insufficient to Assure Plant Safety. These actions had been implemented since Westinghouse notified its customers, including the licensee, that the existing required actions and surveillance requirements associated with TS 3.2.1 may not restore adequate operating margin to ensure that the FQ operating limit would prevent any of the facilities from exceeding the linear heat rate assumed in the plants emergency core cooling system (ECCS) evaluations.
2.0 REGULATORY REQUIREMENTS The performance requirements and design criteria applicable to the power distribution assumed in the safety analysis are those that pertain to accident and transient analysis. Primarily these include the requirements contained in 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors, and General Design Criterion (GDC) 10, contained in Appendix A, General Design Criteria for Nuclear Power Plants, to 10 CFR 50.
The requirements in 10 CFR 50.46 state, in part, that ECCS shall be designed such that an evaluation performed using an acceptable evaluation model demonstrates that acceptance criteria, set forth in 10 CCFR 50.46(b), including peak cladding temperature, cladding oxidation, hydrogen generation, maintenance of coolable core geometry, and long-term cooling are met for a variety of hypothetical loss-of-coolant accidents (LOCAs), including the most severe hypothetical LOCA.
GDC 10, Reactor Design, states as follows:
The reactor and associated coolant, control, and protection systems shall be designed with appropriate margin to assure that specified acceptable fuel design limits are not exceeded during any condition of normal operation, including the effects of anticipated operational occurrences.
The requirements for TS are set forth in 10 CFR 50.36, Technical Specifications. Specific categories of TS are provided in 10 CFR 50.36(c). These include limiting conditions for operation (LCOs). If an LCO is not met, the facility must be shut down, or other acceptable remedial action must be taken. The licensee proposed a set of remedial actions, including reductions in the operating space defined by the combination of rated thermal power and axial flux difference (AFD) that would ensure that the margins continue to ensure that the plants continue to operated in a manner bounded by the initial conditions assumed in the design basis accident and transient analyses. These actions should, therefore, continue to assure compliance with the requirements of 10 CFR 50.46 and GDC 10.
3.0 REQUEST The licensee stated that the required thermal power and axial flux difference (AFD) reductions, which were proposed to be relocated to the Core Operating Limits Report, would initially be those contained in Table 1 of Attachment 1 to the licensees April 7, 2021, submittal. These were based on interim, compensatory measures that had been recommended from Westinghouse when the current required actions and completion times were deemed inadequate. The technical basis for these reductions in thermal power and AFD is not apparent to the NRC staff. Provide information that demonstrates the proposed operating space reductions contained in Table 1 bring about the desired margin improvements, thus assuring compliance with 10 CFR 50.46 and GDC 10 requirements.