ML20247J710: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 33: Line 33:
==Subject:==
==Subject:==
Zion Nuclear Power Station Units 1 and 2 License Nos. DPR-39 and DPR-48 Response to Allegation No. RIII-88-A-162
Zion Nuclear Power Station Units 1 and 2 License Nos. DPR-39 and DPR-48 Response to Allegation No. RIII-88-A-162
                                                                   'NRC Dockgt Nos. 50-295 and 50-304 References- March 17, 1989 letter from C.E. Nerelius to Cordell Reed
                                                                   'NRC Dockgt Nos. 50-295 and 50-304 References- {{letter dated|date=March 17, 1989|text=March 17, 1989 letter}} from C.E. Nerelius to Cordell Reed


==Dear Mr. Davis:==
==Dear Mr. Davis:==

Latest revision as of 14:33, 16 March 2021

Forwards Response to Allegation RIII-88-A-162.Encl Withheld (Ref 10CFR2.790(a))
ML20247J710
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 05/18/1989
From: Kovach T
COMMONWEALTH EDISON CO.
To: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20247J701 List:
References
0016V-13, 16V-13, NUDOCS 8907310305
Download: ML20247J710 (1)


Text

-_._- -

.Ai

./ '*#*;*,*.;'

~. 4 f; N Comm:nw=lth Edison

__ / 72 West Adams Street, Chicago, Illinois

^ L'

\ V 2 Adduss Reply to: Post Office EIxi 77

\%/ . Chicago, filinois 60690 0767 May 18, 1989 10 CFR 2.F ' C <'

L' WITHHOLD FROM

[-

L.

Mr. A'. Bert' Davis.

Regional Administrator U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Zion Nuclear Power Station Units 1 and 2 License Nos. DPR-39 and DPR-48 Response to Allegation No. RIII-88-A-162

'NRC Dockgt Nos. 50-295 and 50-304 References- March 17, 1989 letter from C.E. Nerelius to Cordell Reed

Dear Mr. Davis:

The referenced letter transmitted the allegation and requested a response within 45 days from receipt.of the letter. A telephone conversation

.on May 2, 1989, between Messrs. G. Pirtle'and P.J. Laird established that a due date' extension.until May 11, 1989, would be appropriate. We informed Mr.

J. Kniceley of your staff that the response was mailed late because of an.

administrative error.

The response to the allegation is contained in the Attachment to this.

letter. The Attachment to this letter containe information that is considered as-Exempt from Public Disclosure in accordance with 10 CFR 2.790(a).

Please direct any questions you may have regarding this matter to this office.

Very truly yours,

/ ,

T. J.dovach Nuclear Licensing Manager 1m

100FR 2. 790 INFORMATION MARKING Attachment DOES NOT APPLY WHEN THIS LETTER 8907310305 890721 IS SEPARATE FROM THE ENCLOSURE" PDR- ADOCK 05000295 p PDu 0016V/13 MAY 2 21989

___ _ _ _ _ - _ - _ _ _ _ - _