ML14035A575: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 25, 2014 LICENSEE Union Electric Company d/b/a Ameren Missouri FACILITY: Callaway SUBJECT | ||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL HELD ON JANUARY 28, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI), PERTAINING TO THE CALLAWAY PLANT UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708) The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company d/b/a Ameren Missouri (the applicant) held a telephone conference call on January 28, 2014, to discuss and clarify the applicant's Commitments Nos. 34 and 35 on Callaway's Safety Evaluation Report with Open Items. | OF TELEPHONE CONFERENCE CALL HELD ON JANUARY 28, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI), | ||
The applicant had an opportunity to comment on this summary_ Docket No. 50-483 | PERTAINING TO THE CALLAWAY PLANT UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708) | ||
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company d/b/a Ameren Missouri (the applicant) held a telephone conference call on January 28, 2014, to discuss and clarify the applicant's Commitments Nos. 34 and 35 on Callaway's Safety Evaluation Report with Open Items. provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with the applicant A brief description on the status of the items is also included. | |||
The applicant had an opportunity to comment on this summary_ | |||
*~ | |||
Daily, Sr. Project Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483 | |||
==Enclosures:== | ==Enclosures:== | ||
: 1. List of Participants | : 1. List of Participants | ||
: 2. Summary of the Discussion cc w/encls: Listserv | : 2. Summary of the Discussion cc w/encls: Listserv | ||
*.. ML14035A575 *concurred via email OFFICE LA:RPB1 :DLR PM:RPB1 :DLR BC:RPB1 :DLR PM:RPB1 :DLR NAME Y Edmonds J Daily (S Cuadrado for) Y Diaz Sanabria (JUribe for) J Daily (S Cuadrado for) | |||
DATE 3121114 3121114 3124114 3125114 | |||
==SUBJECT:== | ==SUBJECT:== | ||
Summary of Telephone Conference Call conducted on January 28, 2014 DISTRIBUTION: | Summary of Telephone Conference Call conducted on January 28, 2014 DISTRIBUTION: | ||
HARDCOPY: | HARDCOPY: | ||
DLR RF E-MAIL: PUBLIC [or NON-PUBLIC, if applicable] | DLR RF E-MAIL: | ||
RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrPMCallaway Resource JDaily YDiaz-Sanabria BMizuno (OGC) GPick (RIV) | PUBLIC [or NON-PUBLIC, if applicable] | ||
RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrPMCallaway Resource JDaily YDiaz-Sanabria BMizuno (OGC) | |||
GPick (RIV) | |||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL CALLAWAY | OF TELEPHONE CONFERENCE CALL CALLAWAY LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS January 28, 2014 PARTICIPANTS AFFILIATIONS Samuel Cuadrado de JesUs U.S. Nuclear Regulatory Commission (NRC) | ||
Ameren Missouri Ameren Missouri Ameren Missouri ENCLOSURE 1 | Kenneth Karwoski NRC Cristopher Hunt NRC Dave Shafer Union Electric Company (Ameren Missouri) | ||
Kenny Blair Ameren Missouri Andrew Burgess Ameren Missouri Eric Blocher Ameren Missouri ENCLOSURE 1 | |||
==SUMMARY== | ==SUMMARY== | ||
OF TELEPHONE CONFERENCE CALL CALLAWAY LICENSE RENEWAL APPLICATION January 28, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company d/b/a Ameren Missouri (the applicant) held a telephone conference call on January 28, 2014, to discuss the applicant's Commitments Nos. 34 and 35 on Callaway's Safety Evaluation Report with Open Items. Commitments Nos. 34 and 35 Implementation Discussion: | OF TELEPHONE CONFERENCE CALL CALLAWAY LICENSE RENEWAL APPLICATION January 28, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company d/b/a Ameren Missouri (the applicant) held a telephone conference call on January 28, 2014, to discuss the applicant's Commitments Nos. 34 and 35 on Callaway's Safety Evaluation Report with Open Items. | ||
Commitments Nos. 34 and 35 Implementation Discussion: | |||
The applicant stated that inspection of the steam generators (SGs) will be performed between Fall 2025 and 2029 when the SGs have at least 20 years of operation and if an analysis were to be provided it would be provided before the inspections would be performed. | The applicant stated that inspection of the steam generators (SGs) will be performed between Fall 2025 and 2029 when the SGs have at least 20 years of operation and if an analysis were to be provided it would be provided before the inspections would be performed. | ||
The staff indicated it was concerned that if an analysis were provided too close to the performance of the inspections, the staff may not have enough time to review it. The staff requested the applicant modify the commitments to indicate that if an analysis was submitted to the NRC, it would provide the analysis well before (e.g., 2 years) the scheduled inspection to permit time for the staff to review the analysis. | The staff indicated it was concerned that if an analysis were provided too close to the performance of the inspections, the staff may not have enough time to review it. The staff requested the applicant modify the commitments to indicate that if an analysis was submitted to the NRC, it would provide the analysis well before (e.g., 2 years) the scheduled inspection to permit time for the staff to review the analysis. The applicant understood the staff's concern and stated that it will revise the implementation of Option 2 in Commitments Nos. 34 and 35 to provide ample review time for the staff. | ||
The applicant understood the staff's concern and stated that it will revise the implementation of Option 2 in Commitments Nos. 34 and 35 to provide ample review time for the staff. Action: Applicant will revise Commitments Nos. 34 and 35 on their next License Renewal Application Amendment. | Action: Applicant will revise Commitments Nos. 34 and 35 on their next License Renewal Application Amendment. | ||
ENCLOSURE 2}} | ENCLOSURE 2}} |
Latest revision as of 08:45, 4 November 2019
ML14035A575 | |
Person / Time | |
---|---|
Site: | Callaway |
Issue date: | 03/25/2014 |
From: | Daily J License Renewal Projects Branch 1 |
To: | |
Samuel Cuadrado De Jesus 301-415-2946 | |
References | |
TAC ME7708 | |
Download: ML14035A575 (5) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 25, 2014 LICENSEE Union Electric Company d/b/a Ameren Missouri FACILITY: Callaway SUBJECT
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JANUARY 28, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),
PERTAINING TO THE CALLAWAY PLANT UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company d/b/a Ameren Missouri (the applicant) held a telephone conference call on January 28, 2014, to discuss and clarify the applicant's Commitments Nos. 34 and 35 on Callaway's Safety Evaluation Report with Open Items. provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with the applicant A brief description on the status of the items is also included.
The applicant had an opportunity to comment on this summary_
- ~
Daily, Sr. Project Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483
Enclosures:
- 1. List of Participants
- 2. Summary of the Discussion cc w/encls: Listserv
- .. ML14035A575 *concurred via email OFFICE LA:RPB1 :DLR PM:RPB1 :DLR BC:RPB1 :DLR PM:RPB1 :DLR NAME Y Edmonds J Daily (S Cuadrado for) Y Diaz Sanabria (JUribe for) J Daily (S Cuadrado for)
DATE 3121114 3121114 3124114 3125114
SUBJECT:
Summary of Telephone Conference Call conducted on January 28, 2014 DISTRIBUTION:
HARDCOPY:
DLR RF E-MAIL:
PUBLIC [or NON-PUBLIC, if applicable]
RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrPMCallaway Resource JDaily YDiaz-Sanabria BMizuno (OGC)
GPick (RIV)
SUMMARY
OF TELEPHONE CONFERENCE CALL CALLAWAY LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS January 28, 2014 PARTICIPANTS AFFILIATIONS Samuel Cuadrado de JesUs U.S. Nuclear Regulatory Commission (NRC)
Kenneth Karwoski NRC Cristopher Hunt NRC Dave Shafer Union Electric Company (Ameren Missouri)
Kenny Blair Ameren Missouri Andrew Burgess Ameren Missouri Eric Blocher Ameren Missouri ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL CALLAWAY LICENSE RENEWAL APPLICATION January 28, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company d/b/a Ameren Missouri (the applicant) held a telephone conference call on January 28, 2014, to discuss the applicant's Commitments Nos. 34 and 35 on Callaway's Safety Evaluation Report with Open Items.
Commitments Nos. 34 and 35 Implementation Discussion:
The applicant stated that inspection of the steam generators (SGs) will be performed between Fall 2025 and 2029 when the SGs have at least 20 years of operation and if an analysis were to be provided it would be provided before the inspections would be performed.
The staff indicated it was concerned that if an analysis were provided too close to the performance of the inspections, the staff may not have enough time to review it. The staff requested the applicant modify the commitments to indicate that if an analysis was submitted to the NRC, it would provide the analysis well before (e.g., 2 years) the scheduled inspection to permit time for the staff to review the analysis. The applicant understood the staff's concern and stated that it will revise the implementation of Option 2 in Commitments Nos. 34 and 35 to provide ample review time for the staff.
Action: Applicant will revise Commitments Nos. 34 and 35 on their next License Renewal Application Amendment.