Summary of Meeting with Union Electric Company to Discuss Licensee'S Planned Responses to Staff Requests for Additional Information Related to Callaway Plant'S Request to Revise TS 3.3.2, ESFAS Instrumentation Functions
ML103470147
Person / Time
Site: Callaway Ameren icon.png
Issue date: 12/16/2010
From: Thadani M
Plant Licensing Branch IV
To:
Union Electric Co
Thadani, M C, NRR/DORL/LP4, 415-1476
References
TAC ME2822
Download: ML103470147 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 16, 2010 LICENSEE: Union Electric Company FACILITY: Callaway Plant, Unit 1 SUB~IECT:

SUMMARY

OF NOVEMBER 18, 2010, MEETING WITH UNION ELECTRIC COMPANY ON PLANNED RESPONSES TO THE U. S. NUCLEAR REGULATORY COMMISSION STAFF'S REQUESTS FOR ADDITIONAL INFORMATION (TAC NO. ME2822)

On November 18, 2010, the U. S. Nuclear Regulatory Commission (NRC) staff conducted a Category 1 public meeting with representatives of Union Electric Company, licensee for Callaway Plant, Unit 1, via an audio teleconference. The purpose of the meeting was to discuss the licensee's planned responses to the NRC staffs requests for additional information (RAls) dated October 20 and 25, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML102930674 and ML102980369, respectively), regarding Callaway Plant, Unit 1's license amendment request. The licensee requested revision to Technical Specification (TS) 3.3.2, "Engineered Safety Feature Actuation System (ESFAS)

Instrumentation Functions," dated November 25,2009 (ADAMS Accession No. ML093290318).

A list of attendees is enclosed.

The licensee discussed the information provided as enclosures to the public meeting notice dated November 5, 2010 (ADAMS Accession No. ML103020279). The licensee 'first discussed its responses to the specific RAls dated October 20 and 25,2010, mentioned above. The licensee then reviewed, in detail, its proposed modifications to TS 3.3.2 as provided in the attachment to the public meeting notice enclosure.

The NRC staff questioned the proposed changes to TS 3.3.2. Specifically, the staff inquired about the licensee's basis for changing the "Required Channels" of TS 3.3.2, Table 3.3.2-1, Function 6.g, "Trip of All Main Feedwater Pumps" to "2 trains." The staff and licensee extensively discussed the proposal to change TS 3.3.2, Conditions J, M, and T to a single condition based on 4 required channels (versus 2 trains) with at least three, but no more than four, action statements.

The licensee expressed intention to review its proposed changes internally and the applicability of a pre-existing note for bypassing of channels during surveillance testing. The licensee indicated that it plans to perform additional review for TS applicability and impact for the situation when the second of two main feed pumps is in a "reset" condition during a plant start up. The licensee stated its intention to provide an additional supplement to its license amendment request.

-2 Two members of the public were in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-1476 or mohan.thadani@nrc.gov.

£~~L"- \ I..~ t"b ~v~ ,,~-v~

\ 1 Mohan C. Thadani, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-483

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

LIST OF ATTENDEES NOVEMBER 18, 2010, MEETING WITH UNION ELECTRIC COMPANY PLANNED RESPONSES TO THE U. S. NUCLEAR REGULATORY COMMISSION STAFF'S REQUESTS FOR ADDITIONAL INFORMATION (TAC 1\10. ME2822)

NRC

Participants:

Michael Markley, Chief, Plant Licensing Branch IV Greg Casto, Chief, Balance of Plant Branch Mohan Thadani, Senior Project Manager, Plant Licensing Branch IV Andrew Howe, Senior Reliability and Risk Analyst, PRA Licensing Branch Stanley Gardocki, Reactor Systems Engineer, Balance of Plant Branch Kristy Bucholtz, Reactor Systems Engineer, Technical Specifications Branch James Polickoski, Project Manager, Plant Licensing Branch IV Union Electric Company

Participants:

Scott Maglio, Manager, Regulatory Affairs Bert Yates, Principal Engineer, Regulatory Affairs Rich Eickelman, Operating Supervisor, Operations Members of the Public:

Kathleen Logan Smith, Executive Director, Missouri Coalition for the Environment Kay Drey, Missouri Coalition for the Environment Enclosure

-2 Two members of the public were in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-1476 or mohan.thadani@nrc.gov.

IRA by Balwant K. Singal fori Mohan C. Thadani, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-483

Enclosure:

List of Attendees cc wlencl: Distribution via Listserv DISTRIBUTION:

PUBLIC LPLIV r/f RidsAcrsAcnw_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl4 Resource RidsNrrDirsltsb Resource RidsNrrDraApla Resource RidsNrrDssSbpb resource RidsNrrDssSnpb Resource RidsNrrLAJ Burkhardt Resource RidsNrrPMCallaway Resource RidsOgcRp Resource RidsOpaMail Resource RidsRgn4MailCenter Resource KBucholtz, NRR/DIRS/lTSB AHowe, NRR/DRA/APLA GCasto, NRR/DSS/SBPB SGardocki, NRR/DSS/SNPB CSteger, NRR GMiller, EDO RIV VDricks, OPA RIV J. Polickoski, NRR ADAMS Accession No. Meetinq Notice IVIL 1030202 79 Meetlnq S ummarv M L103470147 OFFICE DORLlLPL4/PM DORLlLPL4/PM DORLlLPL4/LA DO RLlL PL4/BC DORLlLPL4/PM MThadani NAME JPolickoski MThadani JBurkhardt MMarkley (BSingal for)

DATE 12/13/2010 12/14/2010 12/13/10 12/16/10 12/16/10 OFFICIAL RECORD COpy