Letter Sequence RAI |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement
Results
Other: ML11349A005, ML12104A191, ML12139A058, ML12178A475, ML12180A023, ML13029A016, ML14035A575, ML14045A284, ML14052A230, ML14083A617, ML14084A319, ML14112A355, ML14125A199, ML14169A441, ML14169A604, ML14169A637, ML14223A602, ML14281A365, ML14302A238, ML14302A298, ML14302A302, ML14310A836, ML14328A006, ULNRC-05847, Calloway Plant, Unit 1 - License Renewal Application Online Lr Library, ULNRC-05886, Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses, ULNRC-05928, Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates, ULNRC-05950, Enclosure 1, License Renewal Application, RAI Set 19 & Set 20 Responses, Enclosure 2, Amendment 20, LRA Changes from RAI Responses and Commitment Updates, ULNRC-05957, Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses, ULNRC-05979, Enclosure 2 to ULNRC-05979, Amendment 23, LRA Changes from RAI Responses and Commitment Updates Enclosure 2 Summary Table, ULNRC-06120, Update to License Renewal Application Environmental Permits, ULNRC-06122, Update to License Renewal Application Environmental Permits
|
MONTHYEARML11349A0052011-12-15015 December 2011 Biweekly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations: Fr Publication Date December 27, 2011 Project stage: Other ULNRC-05847, Calloway Plant, Unit 1 - License Renewal Application Online Lr Library2012-03-28028 March 2012 Calloway Plant, Unit 1 - License Renewal Application Online Lr Library Project stage: Other ML12104A1912012-04-17017 April 2012 License Renewal Application Online Reference Portal (TAC No. ME7708) Callaway Portal Project stage: Other ML12139A0582012-05-31031 May 2012 Project Manager Change for the License Renewal Project (Safety) for Callaway Plant, Unit 1 Project stage: Other ML12144A0352012-06-11011 June 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML12157A0582012-06-22022 June 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application (TAC ME7708) 6 4 2012 Fmp Neutron Embrittlement and Rv Surveillance RAIs on Yee Chris Sydnor Project stage: RAI ML1218501682012-07-0202 July 2012 ULNRC-05877: Responses to RAI Set 1 and Amendment 4 to the Callaway LRA Project stage: Request ML12164A9052012-07-0505 July 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1, LRA Project stage: RAI ML12172A1112012-07-0909 July 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 4, Project stage: RAI ML12179A4002012-07-18018 July 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML12178A4752012-08-0606 August 2012 Scoping and Screening Methodology Audit Report Regarding the Callaway Plant, Unit 1, License Renewal Application Project stage: Other ML12206A2642012-08-0606 August 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 6 Project stage: RAI ML12220A1602012-08-0606 August 2012 Responses to RAI Set 3 and Amendment 5 to the Callaway License Renewal Application (LRA) Project stage: Response to RAI ULNRC-05886, Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses2012-08-0606 August 2012 Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses Project stage: Other ML12180A0232012-08-0909 August 2012 Aging Management Programs Audit Report Regarding the Callaway Plant Unit 1 License Renewal Application Project stage: Other ML12216A3382012-08-16016 August 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 7 Project stage: RAI ML12235A4672012-08-21021 August 2012 Responses to RAI Set 5 and Amendment 7 to the Callaway LRA (with Updates to Previous RAI Responses) Project stage: Request ML12233A6132012-08-23023 August 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 8, Electrical Project stage: RAI ML12233A5702012-09-0606 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 9 Project stage: RAI ML12284A4542012-09-12012 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 10, Public Version Project stage: RAI ML12240A1742012-09-18018 September 2012 Review of the 2011 Refueling Outage Steam Generator Tube Inservice Inspection Reports Project stage: Approval ML12250A7702012-09-20020 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 11 Project stage: RAI ML12256A8952012-09-25025 September 2012 RAI for the Review of the Callaway Plant, Unit 1, LRA, Set 12 Project stage: RAI ML12255A2872012-10-0101 October 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1, License Renewal Application, Set 13 Project stage: RAI ML12270A1472012-10-0303 October 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 14 Project stage: RAI ML12276A3732012-10-12012 October 2012 RAI for the Review of the Callaway Plant Unit 1, LRA Set 15 Project stage: RAI ML12299A2482012-10-24024 October 2012 Responses to RAI Set 11 & 12 and Amendment 13 to the Callaway LRA Project stage: Response to RAI ML12306A3312012-10-31031 October 2012 Responses to RAI Set 13 & 14 and Amendment 14 to the Callaway LRA, ULNRC-05923 (Cover Letter) Project stage: Request ULNRC-05928, Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates2012-11-0808 November 2012 Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates Project stage: Other ML12314A1412012-11-0808 November 2012 Responses to RAI Set 15 and Amendment 15 to the Callaway LRA Project stage: Response to RAI ULNRC-05929, Responses to RAI Set 16 and Amendment 16 to the LRA2012-11-20020 November 2012 Responses to RAI Set 16 and Amendment 16 to the LRA Project stage: Response to RAI ML12321A1992012-11-29029 November 2012 9/27/12 - Summary of Telephone Conference Call Held Between the NRC and Union Electric Company (Ameren Missouri), Concerning RAIs Pertaining to the Callaway Plant, Unit 1, License Renewal Application Project stage: RAI ML12326A9152012-12-0707 December 2012 RAI for the Review of the Callaway Plant Unit 1, LRA, Set 18 Project stage: RAI ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers Project stage: Request ML12356A0932012-12-19019 December 2012 Annual Update to the Callaway License Renewal Application Response to RAI Set 18 Project stage: Response to RAI ML12342A1722012-12-27027 December 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML13009A2112013-01-14014 January 2013 Request for Additional Information for the Review of the Callaway Plant 1 License Renewal Application Project stage: RAI ML13025A2282013-01-24024 January 2013 Annual Reporting Form for Drug and Alcohol Tests, for Period Ending 2012 Project stage: Request ULNRC-05950, Enclosure 1, License Renewal Application, RAI Set 19 & Set 20 Responses, Enclosure 2, Amendment 20, LRA Changes from RAI Responses and Commitment Updates2013-01-24024 January 2013 Enclosure 1, License Renewal Application, RAI Set 19 & Set 20 Responses, Enclosure 2, Amendment 20, LRA Changes from RAI Responses and Commitment Updates Project stage: Other ML13029A2432013-01-24024 January 2013 Responses to RAI Set 19 & Set 20 and Amendment 20 to the Callaway LRA Project stage: Response to RAI ML13025A0312013-01-30030 January 2013 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 21 Project stage: RAI ML13029A6592013-02-12012 February 2013 Summary of Telephone Conference Call Held on December 6, 2012, Between the NRC and Union Electric Company, Concerning Request for Additional Information Pertaining to the Callaway Plant Unit 1, LRA Project stage: RAI ML13029A0162013-02-12012 February 2013 Summary of Telephone Conference Call Held on January 22, 2013, Between the U.S. Nuclear Regulatory Commission Project stage: Other ULNRC-05957, Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses2013-02-14014 February 2013 Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses Project stage: Other ML13046A3072013-02-14014 February 2013 Enclosure 1 to ULNRC-05957, License Renewal Application, Request for Additional Information (RAI) Set 21 Responses Project stage: Request ML13046A3062013-02-14014 February 2013 Response to RAI Set 21 and Amendment 21 to the Callaway LRA Project stage: Response to RAI ML13038A3082013-02-21021 February 2013 RAI for the Review of the Callaway Plant Unit 1, LRA, Set 22 Project stage: RAI ML13063A4762013-02-28028 February 2013 Response to RAI Set 22 and Amendment 22 to the Callaway LRA Project stage: Response to RAI ML13042A0422013-03-26026 March 2013 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 23 Project stage: RAI ML13058A1242013-03-29029 March 2013 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 24 Project stage: RAI 2012-07-05
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 8, 2014 LICENSEE:
Union Electric Company (Ameren Missouri)
FACILITY:
Callaway Plant, Unit 1
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALLS HELD ON OCTOBER 2 AND 3, 2013, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI), CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO.
ME7708)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company (Ameren Missouri or the applicant) held telephone conference calls on October 2 and 3, 2013, to discuss and clarify the staffs draft requests for additional information (RAIs) concerning the Callaway Plant, Unit 1 (Callaway) license renewal application.
provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with the applicant. A brief description on the status of the items is also included.
The applicant had an opportunity to comment on this summary.
/RA/
John W. Daily, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483
Enclosures:
- 1. List of Participants
- 2. List of Requests for Additional Information cc w/encls: Listserv
ML14175B499
- concurred via email OFFICE LA:DLR*
PM:RPB1:DLR BC:RPB1:DLR PM:RPB1 :DLR NAME YEdmonds JDaily YDiaz-Sanabria JDaily DATE 7/2/14 7/7/14 7/7/14 7/8/14
ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS October 2 and 3, 2013 PARTICIPANTS AFFILIATIONS Samuel Cuadrado de Jesús U.S. Nuclear Regulatory Commission (NRC)
William (Bill) Holston NRC Sarah Kovaleski Callaway (Ameren Missouri)
Eric Blocher Callaway (Ameren Missouri)
Andrew Burgess Callaway (Ameren Missouri)
ENCLOSURE 2
SUMMARY
OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION October 2 and 3, 2013 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Union Electric Company (Ameren Missouri or the applicant) held telephone conference calls on October 2 and 3, 2013, to discuss and clarify the following draft requests for additional information (RAIs) concerning the Callaway license renewal application (LRA).
Internal surfaces and Coatings ISG Draft RAIs Discussion: On September 25, 2013, the staff provided the applicant with Draft RAIs 3.0.3-1, 3.0.3-2, 3.0.3-3, 3.0.3-4, 3.0.3-5, and 3.0.3-6. By request of the applicant, telephone conference calls were held on October 2 and 3, 2013, to discuss and clarify the Draft RAIs. The following is a summary of the discussion results in those two telephone conference calls.
Draft RAI 3.0.3-1 Request" revised. The following revision was made in response to the applicants suggestion to clearly state the environment for the aging effect. Added text is shown underlined and in italics.
Request:
Based on the results of a review of the past 10 years of plant-specific OE, if recurring internal corrosion has occurred in raw water or waste water environments, provide the following (MIC on the internal surfaces of fire water system piping need not be addressed in the response to this RAI).
Draft RAI 3.0.3-2 no longer necessary. Draft RAI 3.0.3-2 stated the following:
Draft RAI 3.0.3-2
Background:
Recent industry OE and questions raised during the staffs review of several LRAs has resulted in the staff concluding that several AMPs and AMR items in the LRA may not or do not account for this OE.
Issue: A representative minimum sample size for periodic inspections for the GALL Report AMP XI.M38, Inspection of Internal Surfaces in Miscellaneous Piping and Ducting Program GALL Report AMP XI.M38 recommends that inspections be performed during periodic system and component surveillances or during the performance of maintenance activities when the surfaces are made accessible for visual inspection. As stated in program element 4, detection of aging effects,, [v]isual and mechanical inspections conducted under this program are opportunistic in nature; they are conducted whenever piping or ducting is opened for any reason. It is possible that opportunistic inspections may not be available for one
or more material, environment, and aging effect combinations presented in the AMR line items where GALL Report AMP XI.M38 is referenced. With the exception of a few GALL Report AMR items where preventive actions alone are considered sufficient to manage aging effects, it is the staffs position that, to credit a GALL Report AMP for aging management, some assurance that a representative sample of all material, environment, and aging effect combinations will be inspected is necessary.
Request:
Justify why no changes to the program are necessary to ensure that each applicable material, environment, and aging effect will be appropriately managed during the period of extended operation. If necessary, provide revisions to LRA Section 3 Table 2s, Appendix A, and Appendix B.
The applicant stated that the information requested in this Draft RAI was provided previously in Sections A1.23 and B2.1.23 of LRA Amendment No. 3 dated June 5, 2012. The staff was able to review LRA Amendment No. 3 and noted that Amendment No. 3 revised LRA Sections A1.23 and B2.1.23 to include a representative minimum sample size for periodic inspections consistent with the issue identified in this Draft RAI, therefore, this Draft RAI will not be issued.
Draft RAI 3.0.3-3 Request a no longer necessary. The staff stated that Request a is not necessary because as draft LR-ISG-2013-01 has been continued to be developed, the issue of meeting manufacturer installation requirements has been removed.
Request:
If coatings have been installed on the internal surfaces of in-scope components (i.e.,
piping, piping subcomponents, heat exchangers, and tanks), state how loss of coating integrity due to blistering, cracking, flaking, peeling, or physical damage will be managed, including:
- a. for each installed coating application, whether installation records used to apply the coating included material manufacturer installation specifications Other Topics Discussion: The applicant stated that in several instances the Draft RAIs used the terminology in accordance and suggested the staff to consider revising the wording. The staff stated that it will consider revising the wording by replacing in accordance with consistent with.
The staff also had a question related to a gap in one of the proposed changes in LRA Amendment No. 25, dated August 2, 2013. The staff noted that LRA Table 3.3.2-20, page 9 of 31 of Enclosure 2 describes gray cast iron pump externally exposed to raw water managed for loss of material by the External Surfaces Monitoring of Mechanical Components Program. The staff asked the applicant whether this pump is accessible once every refueling outage interval for inspections. The applicant stated that the pumps were accessible for inspections during normal power operation. The staff found the statement adequate and has no concerns.
SUBJECT:
Summary of Telephone Conference Call Conducted on October 2 and 3, 2013 DISTRIBUTION: