June 2, 2015 MEMORANDUM TO:
Patricia A. Silva, Chief Inspections and Operations Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards FROM:
Sandra Wastler, Branch Chief
/RA/
Materials Waste Security Branch Division of Security Policy Office of Nuclear Security and Incident Response
SUBJECT:
STAFF REVIEW OF CALLAWAY PLANT UNIT 1 PHYSICAL SECURITY PLAN REVISION 12 FOR THE VERFICATION OF ASM (EA-13-237) INCORPORATION (TAC NO. L25009)
The staff has completed its review of Callaway Plant Unit 1 Physical Security Plan (PSP)
Rev.12 which was submitted by the Union Electric Company to the U.S. Nuclear Regulatory Commission (NRC) by letter dated April 16, 2015.
Based on our review, we find the submitted PSP to be acceptable and the Callaway Plant PSP has met the applicable performance objectives and general requirements outlined in Title 10 of the Code of Federal Regulation (10 CFR), Section 73.55, and the Additional Security Measures imposed by NRC Order EA-13-137.
A physical security inspection (IR Nos. 05000483/2015401 AND 07201045/2015401) was completed on April 30, 2015 which verified the PSP successfully meets the objectives outlined in IP 81311. Based on staffs observations, the Callaway Plant PSP has met the performance objectives and general requirements outlined in 10 CFR Section 73.55 and the Additional Security measures (ASMs) imposed by the NRC.
Docket Nos. 50-438, 72-1045 CONTACT: Douglas Garner (301) 287-0929
MEMORANDUM TO:
Patricia A. Silva, Chief Inspections and Operations Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards FROM:
Sandra Wastler, Branch Chief
/RA/
Materials Waste Security Branch Division of Security Policy Office of Nuclear Security and Incident Response
SUBJECT:
STAFF REVIEW OF CALLAWAY PLANT UNIT 1 PHYSICAL SECURITY PLAN REVISION 12 FOR THE VERFICATION OF ASM (EA-13-237) INCORPORATION (TAC NO. L25009)
The staff has completed its review of Callaway Plant Unit 1 Physical Security Plan (PSP)
Rev.12 which was submitted by the Union Electric Company to the U.S. Nuclear Regulatory Commission (NRC) by letter dated April 16, 2015.
Based on our review, we find the submitted PSP to be acceptable and the Callaway Plant PSP has met the applicable performance objectives and general requirements outlined in Title 10 of the Code of Federal Regulation (10 CFR), Section 73.55, and the Additional Security Measures imposed by NRC Order EA-13-137.
A physical security inspection (IR Nos. 05000483/2015401 AND 07201045/2015401) was completed on April 30, 2015 which verified the PSP successfully meets the objectives outlined in IP 81311. Based on staffs observations, the Callaway Plant PSP has met the performance objectives and general requirements outlined in 10 CFR Section 73.55 and the Additional Security measures (ASMs) imposed by the NRC.
Docket Nos. 50-438, 72-1045 CONTACT: Douglas Garner (301) 287-0929 DISTRIBUTION:
DSP r/f Adams Accession No.: ML15139A484 OFFICE DSP/MWSB MWSB/BC NAME D. Garner S. Wastler DATE 06/01/15 06/01/15 OFFICIAL RECORD COPY