MONTHYEARML12125A1812012-05-15015 May 2012 Environmental Site Audit Regarding Callaway Plant, Unit 1 Project stage: Other ML12131A4732012-05-15015 May 2012 (Enclosure 4) Environmental Site Audit Regarding Callaway Plant, Unit 1, Project stage: Other ML12131A4512012-05-15015 May 2012 (Enclosure 2) Environmental Site Audit Regarding Callaway Plant, Unit 1 Project stage: Other ML12125A3322012-05-15015 May 2012 (Enclosure 3) Environmental Site Audit Regarding Callaway Plant, Unit 1 Project stage: Other ML12139A0582012-05-31031 May 2012 Project Manager Change for the License Renewal Project (Safety) for Callaway Plant, Unit 1 Project stage: Other ML12144A0352012-06-11011 June 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML12159A1542012-06-22022 June 2012 Summary of Site Audit Related to the Review of the License Renewal Application for Callaway Plant, Unit 1 (TAC Nos. ME7715 and ME7716) Project stage: Approval ML12157A0582012-06-22022 June 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application (TAC ME7708) 6 4 2012 Fmp Neutron Embrittlement and Rv Surveillance RAIs on Yee Chris Sydnor Project stage: RAI ML12164A9052012-07-0505 July 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1, LRA Project stage: RAI ML12172A1112012-07-0909 July 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 4, Project stage: RAI ML12179A4002012-07-18018 July 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ULNRC-05886, Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses2012-08-0606 August 2012 Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses Project stage: Other ML12220A1602012-08-0606 August 2012 Responses to RAI Set #3 and Amendment 5 to the Callaway License Renewal Application (LRA) Project stage: Response to RAI ML12206A2642012-08-0606 August 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 6 Project stage: RAI ML12180A0232012-08-0909 August 2012 Aging Management Programs Audit Report Regarding the Callaway Plant Unit 1 License Renewal Application Project stage: Other ML12271A4232012-08-13013 August 2012 Responses to Environmental RAI Set #1 to the Callaway LRA Project stage: Other ML12216A3382012-08-16016 August 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 7 Project stage: RAI ML12233A6132012-08-23023 August 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 8, Electrical Project stage: RAI ML12244A5712012-08-30030 August 2012 Responses to E-RAI Set 2 to the License Renewal Application Project stage: Other ML12233A5702012-09-0606 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 9 Project stage: RAI ML12284A4542012-09-12012 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 10, Public Version Project stage: RAI ML12240A1742012-09-18018 September 2012 Review of the 2011 Refueling Outage Steam Generator Tube Inservice Inspection Reports Project stage: Approval ML12244A4292012-09-18018 September 2012 Summary of Telephone Conference Call Held on August 29, 2012, Between the U.S. Nuclear Regulatory Commission and Union Electric Company, Concerning the Request for Additional Information Pertaining to the Callaway Plant, Unit 1, License Ren Project stage: RAI ML12250A7702012-09-20020 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 11 Project stage: RAI ML12256A8952012-09-25025 September 2012 RAI for the Review of the Callaway Plant, Unit 1, LRA, Set 12 Project stage: RAI ML12255A2872012-10-0101 October 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1, License Renewal Application, Set 13 Project stage: RAI ML12262A3112012-10-0202 October 2012 Summary of Telephone Conference Call Held on September 14, 2012, Between NRC and Union Electric Company, Concerning the SAMA RAI for the Callaway Plant, Unit 1, LRA Project stage: RAI ML12270A1472012-10-0303 October 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 14 Project stage: RAI ML12276A3732012-10-12012 October 2012 RAI for the Review of the Callaway Plant Unit 1, LRA Set 15 Project stage: RAI ML12299A2482012-10-24024 October 2012 Responses to RAI Set #11 & #12 and Amendment 13 to the Callaway LRA Project stage: Response to RAI ML12314A1412012-11-0808 November 2012 Responses to RAI Set #15 and Amendment 15 to the Callaway LRA Project stage: Response to RAI ULNRC-05928, Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates2012-11-0808 November 2012 Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates Project stage: Other ULNRC-05929, Responses to RAI Set 16 and Amendment 16 to the LRA2012-11-20020 November 2012 Responses to RAI Set #16 and Amendment 16 to the LRA Project stage: Response to RAI ML12321A1992012-11-29029 November 2012 9/27/12 - Summary of Telephone Conference Call Held Between the NRC and Union Electric Company (Ameren Missouri), Concerning RAIs Pertaining to the Callaway Plant, Unit 1, License Renewal Application Project stage: RAI ML12326A9152012-12-0707 December 2012 RAI for the Review of the Callaway Plant Unit 1, LRA, Set 18 Project stage: RAI ML12342A1722012-12-27027 December 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML13009A2112013-01-14014 January 2013 Request for Additional Information for the Review of the Callaway Plant 1 License Renewal Application Project stage: RAI ULNRC-05950, Responses to RAI Set 19 & Set 20 and Amendment 20 to the Callaway LRA2013-01-24024 January 2013 Responses to RAI Set 19 & Set 20 and Amendment 20 to the Callaway LRA Project stage: Response to RAI ML13025A0312013-01-30030 January 2013 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 21 Project stage: RAI ML13029A6592013-02-12012 February 2013 Summary of Telephone Conference Call Held on December 6, 2012, Between the NRC and Union Electric Company, Concerning Request for Additional Information Pertaining to the Callaway Plant Unit 1, LRA Project stage: RAI ML13029A0162013-02-12012 February 2013 Summary of Telephone Conference Call Held on January 22, 2013, Between the U.S. Nuclear Regulatory Commission Project stage: Other ML13046A3072013-02-14014 February 2013 Enclosure 1 to ULNRC-05957, License Renewal Application, Request for Additional Information (RAI) Set #21 Responses Project stage: Request ML13046A3062013-02-14014 February 2013 Response to RAI Set #21 and Amendment 21 to the Callaway LRA Project stage: Response to RAI ULNRC-05957, Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses2013-02-14014 February 2013 Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses Project stage: Other ML13038A3082013-02-21021 February 2013 RAI for the Review of the Callaway Plant Unit 1, LRA, Set 22 Project stage: RAI ML12307A3912013-02-26026 February 2013 Schedule Revision for the Environmental Review of the Callaway Plant, Unit 1 License Renewal Application (TAC Nos. ME7715 and ME7716) Project stage: Approval ML13063A4762013-02-28028 February 2013 Response to RAI Set #22 and Amendment 22 to the Callaway LRA Project stage: Response to RAI ML13059A8002013-03-11011 March 2013 Summary of Telephone Call Held on 11/5/12, Between NRC and Union Electric Company, Regarding Request for Clarification of Responses to the SAMA RAI Concerning Callaway Plant, Unit 1, LRA Project stage: RAI ML13042A0422013-03-26026 March 2013 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 23 Project stage: RAI ML13058A1242013-03-29029 March 2013 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 24 Project stage: RAI 2012-08-23
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) IR 05000483/20230042024-01-19019 January 2024 – Integrated Inspection Report 05000483/2023004 ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 2024-09-11
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 26, 2013
. Mr. Adam* C. Heflin Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NOS. ME7715 AND ME7716)
Dear Mr. Heflin:
By letter dated December 15, 2011, Union Electric Company (Ameren) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew the Callaway Plant, Unit 1 (Callaway), operating license NPF-30, for review by the U.S.
Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the Callaway license renewal review.
Future milestones have been revised to reflect additional time needed to complete the severe accident mitigation alternatives review. The NRC staff will continue to follow established review procedures and the enclosed environmental review schedule to complete the reviews required by 10 CFR Part 51.
If you have any questions related to this revised schedule, please contact Ms. Carmen Fells, Project Manager for the environmental review of Callaway Plant, Unit 1, license renewal application by telephone at 301-415-6337 or bye-mail at C men.Felis nrc. ov.
Docket No. 50-483
Enclosure:
. ReVised Schedule cc w/encl: Listserv
CALLAWAY PLANT. UNIT 1 LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Receive license renewal application (LRA) 12/19/11 12/19/11 Publish Federal Register Notice (FRN) - LRA availability 01/2012 01103/12
. Publish FRN - acceptancelrejection and opportunity for hearing 02/2012 02/24/12 Publish FRN environmental scoping meeting 02/2012 02/24/12 Public Meeting - License Renewal Overview and Environmental 03/14/12 03/14/12 Scopingmeeting
.* Deadline for filing hearing requests and petitions for intervention 04/24/12 04/24/12 Environmental scoping period ends 04/24/12 04/24/12 Audit - Environmental 05/22/12 Ci5/22/12 Issue draft supplemental environmental impact statement (SEIS) 08/2013 Publish FRN - draft SEIS available for comments 08/2013 Public Meeting - draft SEIS meeting 09/2013
. End of draft SEIS comment period 09/2013 Issue final SEIS 04/2014 U.S. Environmental Protection Agency FRN Published - availability 04/2014 of final SEIS Decision - Director, Office of Nudear Reactor Regulation TBD*
Commission decision TBD
ENCLOSURE
'.. ML12307A391 *via e-mail
- OFFICE PM:DLR/RPB2 LA: DLR/RPB2* BC:DLR/RPB2 D:DLR NAME CFelis IKing DWrona JLubinski DATE 2/20/2013 2/21/13 2/25/2013 2/26/2013
Letter to A. Heflin form J. Lubinski, dated February 26, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NOS. ME7715 AND ME7716)
DISTRIBUTION:
HARD COPY:
DLR RF EMMAIL:
PUBLIC RidsNrrDlrResource RidsNrrDraApla Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource DWrona MWong DMorey TTate, ORA FLyon, DORL DMclntyre, OPA MSpencer, OGC AGhosh,OGC BMaier, RIV NO'Keefe, RIV THartman, RIV ZHolicraft, RIV VDricks, RIV LUselding, RIV SKovaleski@ameren.com