UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 26, 2013
. Mr. Adam* C. Heflin Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NOS. ME7715 AND ME7716)
Dear Mr. Heflin:
By letter dated December 15, 2011, Union Electric Company (Ameren) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew the Callaway Plant, Unit 1 (Callaway), operating license NPF-30, for review by the U.S.
Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the Callaway license renewal review.
Future milestones have been revised to reflect additional time needed to complete the severe accident mitigation alternatives review. The NRC staff will continue to follow established review procedures and the enclosed environmental review schedule to complete the reviews required by 10 CFR Part 51.
If you have any questions related to this revised schedule, please contact Ms. Carmen Fells, Project Manager for the environmental review of Callaway Plant, Unit 1, license renewal application by telephone at 301-415-6337 or bye-mail at C men.Felis nrc. ov.
Docket No. 50-483
Enclosure:
. ReVised Schedule cc w/encl: Listserv
CALLAWAY PLANT. UNIT 1 LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Receive license renewal application (LRA) 12/19/11 12/19/11 Publish Federal Register Notice (FRN) - LRA availability 01/2012 01103/12
. Publish FRN - acceptancelrejection and opportunity for hearing 02/2012 02/24/12 Publish FRN environmental scoping meeting 02/2012 02/24/12 Public Meeting - License Renewal Overview and Environmental 03/14/12 03/14/12 Scopingmeeting
.* Deadline for filing hearing requests and petitions for intervention 04/24/12 04/24/12 Environmental scoping period ends 04/24/12 04/24/12 Audit - Environmental 05/22/12 Ci5/22/12 Issue draft supplemental environmental impact statement (SEIS) 08/2013 Publish FRN - draft SEIS available for comments 08/2013 Public Meeting - draft SEIS meeting 09/2013
. End of draft SEIS comment period 09/2013 Issue final SEIS 04/2014 U.S. Environmental Protection Agency FRN Published - availability 04/2014 of final SEIS Decision - Director, Office of Nudear Reactor Regulation TBD*
Commission decision TBD
- To be determined (TBD)
ENCLOSURE
'.. ML12307A391
- via e-mail
- OFFICE NAME DATE PM:DLR/RPB2 CFelis 2/20/2013 LA: DLR/RPB2*
IKing 2/21/13 BC:DLR/RPB2 DWrona 2/25/2013 D:DLR JLubinski 2/26/2013
Letter to A. Heflin form J. Lubinski, dated February 26, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC NOS. ME7715 AND ME7716)
DISTRIBUTION:
HARD COPY:
DLR RF EMMAIL:
PUBLIC RidsNrrDlrResource RidsNrrDraApla Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource DWrona MWong DMorey TTate, ORA FLyon, DORL DMclntyre, OPA MSpencer, OGC AGhosh,OGC BMaier, RIV NO'Keefe, RIV THartman, RIV ZHolicraft, RIV VDricks, RIV LUselding, RIV SKovaleski@ameren.com