MONTHYEARML20248H4672020-09-0404 September 2020 RICT & 50.69 LARs - NRC Pre-Submittal Meeting Slides Project stage: Request ML20280A5632020-10-21021 October 2020 Summary of Teleconference Meeting with Union Electric Company (Dba Ameren Missouri) for Callaway Plant, Unit 1, on Pre-Application for LARs on TSTF-439, TSTF-505, and Title 10 CFR 50.69 Categorization Program (EPID L-2020-LRM-0072 Project stage: Meeting 2020-10-21
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML22259A1192022-10-12012 October 2022 Summary of Pre-Application Teleconference with Union Electric Company to Discuss Approval to Insert Framatome Gaia Fuel Assemblies in Its Core Reload Quantities for Callaway Plant, Unit No. 1 ML22181A0012022-07-22022 July 2022 Summary of June 29, 2022, Public Meeting - Union Electric Company, Dba Ameren Missouri to Discuss Upcoming License Amendment Request to Revise Technical Specifications to Reflect Revised Spent Fuel Pool Criticality Safety Analysis ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22089A2292022-04-0606 April 2022 February 28, 2022, Summary of Partially Closed Pre-Application Teleconference with Union Electric Company Regarding Approval to Insert Framatome Gaia Fuel Assemblies in Their Core in Reload Quantities for Callaway Plant, Unit No. 1 ML21308A0742021-11-17017 November 2021 Summary of Partially Closed Pre-Application Teleconference with Union Electric Company Regarding Approval to Insert Framatomes Gaia Fuel Assemblies in Its Core in Reload Quantities for Callaway Plant, Unit No. 1 ML21243A0042021-09-0707 September 2021 Summary of Teleconference Meeting with Union Electric Company Regarding Proposed License Amendment Request to Revise the Emergency Plan ML21216A2002021-08-11011 August 2021 Summary of Public Webinar with Ameren Missouri to Discuss the Nuclear Regulatory Commission 2020 Annual Assessment of Callaway Plant Docket No. 50-483 ML21168A0022021-07-0101 July 2021 Summary of Partially Closed Pre-Application Teleconference with Union Electric Company Regarding Approval to Insert Framatomes Gaia Fuel Assemblies in Their Core in Reload Quantities for Callaway Plant, Unit No. 1 ML21103A0032021-04-16016 April 2021 Summary of March 15, 2021, Teleconference Meeting with Union Electric Company Regarding Proposed License Amendment Request to Implement Alternative Source ML20280A5632020-10-21021 October 2020 Summary of Teleconference Meeting with Union Electric Company (Dba Ameren Missouri) for Callaway Plant, Unit 1, on Pre-Application for LARs on TSTF-439, TSTF-505, and Title 10 CFR 50.69 Categorization Program (EPID L-2020-LRM-0072 ML20189A1992020-07-13013 July 2020 Summary of (COVID-19) Presubmittal Public Teleconference W/Union Electric Company Postponement of Steam Generator Eddy Current Testing, by One Refueling Outage, for Callaway Plant, Unit No. 1 ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML19268A9772019-10-16016 October 2019 Summary of 9/12/2019 Meeting with Union Electric Company Related to Closure of Generic Letter 2004-02 for Callaway Plant, Unit 1 ML18215A3752018-08-21021 August 2018 Summary of Pre-Submittal Meeting with Union Electric Company to Discuss an Alternate Source Term License Amendment Request ML16243A5132016-09-0101 September 2016 Summary of August 25, 2016, Public Meeting with Wolf Creek Nuclear Operating Corporation and Amerenue Regarding a Proposed Application for a New Technical Specification for the Class 1E Electrical Equipment Air Conditioning System (MF8118 a ML16165A0042016-06-23023 June 2016 Summary of 6/1/2016 Public Meeting with Union Electric Company to Discuss Generic Safety Issue 191 and Callaway Plant Unit 1's Debris Testing Plan ML14281A3652015-02-23023 February 2015 May 2, 2014, Summary of Conference Call Held Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Pertaining to the Callaway Plant, Unit 1, License Renewal Application ML14223A6022014-08-20020 August 2014 Summary of Telephone Conference Call Held on December 18, 2013, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri) ML14223A5322014-08-20020 August 2014 November 26, 2013, Summary of Telephone Conference Call Held Between Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri) Concerning Requests for Additional Information Pertaining to Callaway, Unit 1, License Renewal A ML14177A5952014-07-0808 July 2014 Summary of Telephone Conference Call Held on February 12, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Concerning Requests for Additional Information Pertaining to the Callaway Plant, Un ML14175B4992014-07-0808 July 2014 Summary of Telephone Conference Calls Held on October 2 and 3, 2013, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Concerning Requests for Additional Information Pertaining to the Callaway Plan ML14169A6372014-07-0303 July 2014 Summary of Telephone Conference Call Held on April 28, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri) Pertaining to the Callaway Plant, Unit 1, LRA ML14169A6042014-07-0303 July 2014 April 30, 2014, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Pertaining to the Callaway Plant, Unit 1, License Renewal Application ML14125A1992014-07-0303 July 2014 Summary of Telephone Conference Call Held on April 9, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Pertaining to the Callaway Plant, Unit 1, License Renewal Application (Tac. No. ME7708) ML14169A4412014-07-0303 July 2014 Summary of Telephone Conference Call Held on April 21, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Pertaining to the Callaway Plant, Unit 1, License Renewal Application (Tac. No. ME7708 ML14121A5532014-06-18018 June 2014 November 25, 2013, Summary of Telephone Conference Call Held Between NRC and Union Electric Co., (Ameren Missouri), Concerning Requests for Additional Information Pertaining to Callaway, Unit 1, License Renewal Application ML14093B3382014-04-14014 April 2014 01/30/2014, Summary of Telephone Conference Call Held Between NRC and Union Electric Co., (Ameren Missouri), Concerning Requests for Additional Information Pertaining to Callaway, Unit 1, License Renewal Application ML14087A2102014-04-0808 April 2014 Summary of 3/25/14 Verbal Relief Telephone Conference, Relief Request I3R-16, Temporary Non-Code Repair of the Train a Component Cooling Water Heat Exchanger to Control ESW Leakage, Third 10-Year Inservice Inspection Interval ML14070A0782014-04-0707 April 2014 02/27/2014 & 03/04/2014, Summary of Telephone Conference Call Held Between Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Pertaining to the Callaway Plant Unit 1, License Renewal Application RAI Set 31 ML14080A5442014-03-31031 March 2014 February 20, 2014, Summary of Meeting Held Between U.S. Nuclear Regulatory Commission Staff and Union Electric Company Representatives to Discuss the Callaway Plant, Unit 1, License Renewal Application ML14035A5752014-03-25025 March 2014 January 28, 2014, Summary of Telephone Conference Call Held Between NRC and Union Electric Company (Ameren Missouri), Pertaining to the Callaway Plant Unit 1, LRA ML13246A3072013-09-0909 September 2013 Memorandum to File - Verbal Authorization of Relief Request PR-07, Testing Frequency for Pumps and Valves, Third 10-year Inservice Testing Interval ML13126A3202013-05-0707 May 2013 Summary of Telephone Conference, Verbal Authorization of Relief Request I3R-14. Proposed Alternative to ASME Code Requirements for Leakage Testing of RPV Head Flange Leakoff Lines, Third 10-Year ISI Interval. ML13067A3162013-04-0101 April 2013 August 23, 2012, Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Concerning Requests for Additional Information Pertaining to Callaway Plant, Unit 1, License ML13029A0162013-02-12012 February 2013 Summary of Telephone Conference Call Held on January 22, 2013, Between the U.S. Nuclear Regulatory Commission ML13029A6592013-02-12012 February 2013 Summary of Telephone Conference Call Held on December 6, 2012, Between the NRC and Union Electric Company, Concerning Request for Additional Information Pertaining to the Callaway Plant Unit 1, LRA ML13042A1882013-02-11011 February 2013 01/31/2013 Summary of the Public Meeting to Discuss the Results of the Grand Gulf Nuclear Station License Renewal Inspection IR 05000483/20120092013-01-25025 January 2013 1/17/2013 - Summary of Public Meeting to Discuss the Results of the Callaway Nuclear Plant License Renewal Inspection (05000483-12-009) ML12321A1992012-11-29029 November 2012 9/27/12 - Summary of Telephone Conference Call Held Between the NRC and Union Electric Company (Ameren Missouri), Concerning RAIs Pertaining to the Callaway Plant, Unit 1, License Renewal Application ML12321A1882012-11-20020 November 2012 Summary of Preapplication Meeting with Union Electric Company to Discuss Callaway Plant, Unit 1, License Amendment Request to Change Licensing Basis and Analysis of Integrated Head Assembly Consistent with Regulatory Guide 1.61 Revision 1 ML12262A3112012-10-0202 October 2012 Summary of Telephone Conference Call Held on September 14, 2012, Between NRC and Union Electric Company, Concerning the SAMA RAI for the Callaway Plant, Unit 1, LRA ML12243A3922012-09-18018 September 2012 Meeting Summary with Union Electric Company to Discuss Request for New Technical Specification Related to Class 1E Electrical Equipment Air Conditioning System at Callaway Plant, Unit 1 ML12243A3762012-09-18018 September 2012 8/29/2012 Summary of Preapplication Meeting with Union Electric Company to Discuss Request to Revise Technical Specification 3.7.9, Ultimate Heat Sink SR 3.7.9.1 and 3.7.9.2 at Callaway Plant, Unit 1 ML12244A4292012-09-18018 September 2012 Summary of Telephone Conference Call Held on August 29, 2012, Between the U.S. Nuclear Regulatory Commission and Union Electric Company, Concerning the Request for Additional Information Pertaining to the Callaway Plant, Unit 1, License Ren ML1116002282011-06-21021 June 2011 Summary of Meeting with Union Electric Company to Discuss Callaway Plant, Unit 1's Proposed Request to Adopt Risk-informed, Performance-based Alternative Described in National Fire Protection Association Standard (NFPA) 805 ML1115400922011-06-0303 June 2011 Summary of Annual Performance Assessment Meeting with Union Electric Company to Discuss the Callaway Plant Performance for the NRC Inspection Period Ending December 31, 2010 ML1104001662011-02-22022 February 2011 Summary of Meeting with Union Electric Company to Discuss Licensee'S Planned Responses to Staff Requests for Additional Information Callaway Plant'S Request to Revise TS 3.3.2, ESFAS Instrumentation Functions ML1034701472010-12-16016 December 2010 Summary of Meeting with Union Electric Company to Discuss Licensee'S Planned Responses to Staff Requests for Additional Information Related to Callaway Plant'S Request to Revise TS 3.3.2, ESFAS Instrumentation Functions ML1008804162010-03-31031 March 2010 Meeting Summary of Conference Call with Union Electric Company to Discuss Proposed Application for Relocation of Surveillance Frequencies from Callaway Plant Technical Specifications (Risk-Managed TS Initiative 5b) 2024-01-12
[Table view] |
Text
October 21, 2020 LICENSEE:
Union Electric Company FACILITY:
Callaway Plant, Unit No. 1
SUBJECT:
SUMMARY
OF SEPTEMBER 8, 2020, TELECONFERENCE MEETING WITH UNION ELECTRIC COMPANY REGARDING PROPOSED LICENSE AMENDMENT REQUESTS TO ADOPT TECHNICAL SPECIFICATIONS TASK FORCE (TSTF-439), TSTF-505, AND 10 CFR 50.69 CATEGORIZATION PROGRAM FOR CALLAWAY PLANT, UNIT No. 1 (EPID L-2020-LRM-0072)
On September 8, 2020, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Union Electric Company dba Ameren Missouri (the licensee). The purpose of this meeting was to discuss the licensees plans and schedule for the following two proposed license amendment requests (LARs) for Callaway Plant, Unit No. 1: (1) to adopt Technical Specifications Task Force (TSTF) Travelers TSTF-439, Eliminate Second Completion Times Limiting Times from Discovery of Failure to Meet and LCO
[Limiting Condition for Operation] and TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF [Risk-Informed TSTF] Initiative 4b; and (2) to adopt Title 10 of the Code of Federal Regulations Section 50.69 (10 CFR 50.69), Risk-informed categorization and treatment of structures, systems, and components for nuclear power reactors.
The meeting notice and agenda, dated August 13, 2020, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML20240A344. A list of attendees is enclosed.
The licensee presented meeting slides, which can be found in ADAMS at Accession No. ML20248H467. The meeting slides included the scope of the LARs, optional variations from TSTF-505 license amendment development, probabilistic risk assessment (PRA) model technical adequacy, open findings and observations, PRA model uncertainties and assumptions, external hazards, potential review efficiencies, and timeline for submissions. The licensee also stated that the 10 CFR 50.69 LAR is expected to be submitted in the late third quarter of 2020, and TSTF-505 is expected to be submitted in the fourth quarter of 2020.
TSTF-439 will be submitted in conjunction with TSTF-505.
The NRC staff discussed with the licensee that the future LARs should consider the following items as part of the upcoming submittals; As shown on Slide 5 of the licensees presentation, ensure all aspects of the methodology are addressed.
As shown on Slide 14 of the licensees presentation, it is stated that Callaway implemented the methodology provided in PWROG [Pressurized-Water Reactor Owners
Group]-18027-NP for assessing the loss of room cooling in PRA modelling. During the meeting, the licensee also mentioned that it is using a non-standard LCO 3.7.5 (concerning the auxiliary feedwater system), which was not in the licensees presentation slides. The NRC staff would like this to be addressed in the LAR.
PRA Technical Adequacy Provide a high-level summary in the LAR for the NRC staff to assess information related to facts and observations closure consistent with the Appendix X guidance and the staff conditions of acceptance were considered.
For fire probabilistic risk assessment, address any outstanding or open commitments stemming from the National Fire Protection Association (NFPA)-805 that overlap and potentially impact the PRA acceptability for the risk-informed applications.
Include any credit for Diverse and Flexible Mitigation Strategy (FLEX). Describe if and how the permanent or portable equipment is considered (i.e., consistency with staff memo).
NFPA-805 was approved in 2014, and the licensee has completed its transition process. It would be prudent to ensure that any methodologies that have been further addressed via frequently asked questions or updated guidance documents are considered in preparation of the subject LARs.
PRA Model Uncertainties and Assumptions In disposition of crediting applicable sensitivities prescribed in guidance, be clear and provide the basis of its applicability.
It will be prudent to review applicable precedent safety evaluations addressing seismic PRA assumptions and sources of uncertainty.
Combined TSTF-439 and TSTF-505 It would be helpful if separate evaluations are provided for each TSTF.
Provide a discussion that describes the overall loss-of-function assessment for all LCOs that are included in the scope of the LAR and any criteria (i.e., design success criteria, PRA success criteria) used to determine the loss-of-function.
Per Slide 10 of the licensees presentation, provide the basis for use of surrogate and why it is sufficient for the function being assessed.
The licensee stated that the LARs would address the comments and concerns raised by the NRC staff in this teleconference.
No regulatory decisions were made as a result of this teleconference.
Members of the public were in attendance. Public Meeting Feedback forms were not received.
Please direct any inquiries to Mahesh.Chawla@nrc.gov or contact me at 301-415-8371.
/RA/
Mahesh L. Chawla, Project Manager Plant Licensing Branch III Division Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-483
Enclosure:
List of Attendees cc: Listserv
LIST OF ATTENDEES SEPTEMBER 8, 2020 PRE-SUBMITTAL TELECONFERENCE WITH UNION ELECTRIC COMPANY REGARDING PROPOSED LICENSE AMENDMENT REQUESTS TO ADOPT TECHNICAL SPECIFICATIONS TASK FORCE (TSTF)-439, TSTF-505 AND 10 CFR 50.69 FOR CALLAWAY PLANT, UNIT NO. 1 U.S. Nuclear Regulatory Commission M. Benson A. Brown M. Chawla J. Circle A. Foli B. Fu B. Grenier J. Huang C. Li M. Li E. Miller K. Nguyen R. Pascarelli J. Robinson T. Scarbrough G. Singh K. Tetter B. Titus S. Vasavada K. West D. Woodyatt D. Wu Union Electric Company N. Allen S. Banker A. Burgess N. Casey M. Degonish J. Doughty T. Elwood J. Hiller B. Hryciw B. Huhmann J. Kosky J. Kovar E. Matthews S. Meyer I. Mulhern R. Orr T. Schmidt R. Wink Pacific Northwest National Laboratory S. Short Public R. Burg (Engineering Planning and Management (EPM), Inc.
Meeting Notice, ML20240A344 Meeting Summary, ML20280A563
- via e-mail OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA*
NRR/DRA/APLA/BC*
NAME MChawla PBlechman RPascarelli DATE 10/21/2020 10/21/2020 10/06/2020 OFFICE NRR/DORL/LPL4/BC*
NRR/DORL/LPL4/PM*
NAME JDixon-Herrity MChawla DATE 10/21/2020 10/21/2020