ML071030053: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 3: Line 3:
| issue date = 04/27/2007
| issue date = 04/27/2007
| title = Summary of Conference Calls on April 2, 2007, with Entergy Nuclear Operations, Inc., Regarding the Pilgrim License Renewal Application
| title = Summary of Conference Calls on April 2, 2007, with Entergy Nuclear Operations, Inc., Regarding the Pilgrim License Renewal Application
| author name = Buckberg P H
| author name = Buckberg P
| author affiliation = NRC/NRR/ADRO/DLR/RLRA
| author affiliation = NRC/NRR/ADRO/DLR/RLRA
| addressee name =  
| addressee name =  

Latest revision as of 02:10, 13 July 2019

Summary of Conference Calls on April 2, 2007, with Entergy Nuclear Operations, Inc., Regarding the Pilgrim License Renewal Application
ML071030053
Person / Time
Site: Pilgrim
Issue date: 04/27/2007
From: Perry Buckberg
NRC/NRR/ADRO/DLR/RLRA
To:
Entergy Nuclear Operations
Buckberg, P., PM, RLRA, 415-1383
References
TAC MC9669
Download: ML071030053 (6)


Text

April 27, 2007LICENSEE: Entergy Nuclear Operations, Inc.FACILITY:Pilgrim Nuclear Power Station

SUBJECT:

SUMMARY

OF CONFERENCE CALLS ON APRIL 2, 2007, WITH ENTERGYNUCLEAR OPERATIONS, INC., REGARDING THE PILGRIM LICENSE RENEWAL APPLICATION (TAC NO. MC9669)The U.S. Nuclear Regulatory Commission (NRC) staff conducted a series of conference callswith Entergy Nuclear Operations, Inc., (Entergy) regarding the Pilgrim license renewal application (LRA) to discuss Pilgrim Safety Evaluation Report (SER) Open Item (OI) 3.0.3.3.2.

The conference calls were conducted on Monday, April 2, 2007, between 10:30 a.m. and 3:30 p.m. at 11555 Rockville Pike, Rockville, MD 20852. The list of participants is shown in the enclosure. The following is a summary of the conference calls.The NRC Pilgrim Project Manager provided a brief introduction and then the staff was able todiscuss with Entergy remaining questions regarding the possibility of refueling pool water leaking onto the reactor drywell shell. The staff and Entergy also discussed the need for commitments to evaluate torus anchor bolts and grout, and the need to confirm the 50 and 100 year flood plans do not impact the torus and surrounding equipment. Entergy described the inspections performed during outages that ensure any water leakage is documented. Entergy stated that no leakage has ever been documented. Entergy also discussed the welded construction of the refueling bellows. Entergy agreed that commitments should be made consistent with their recent Torus Base Mat Performance Evaluation recommendations and that they will confirm the flood plan impact on the plant. The applicant had an opportunity to comment on the meeting summary./RA/Perry Buckberg, Project ManagerLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket No. 50-293

Enclosure:

List of Participantscc w/encl: See next page

ML071030053OFFICEPM:RLRA:DLRLA:DLROGCBC:RLRA:DLRNAMEPBuckbergSFigueroaSUttalLLund DATE4/19/074/18/074/27/074/25/07 Note to Entergy Nuclear Operations, Inc., from P. Buckberg Dated April 27, 2007

SUBJECT:

SUMMARY

OF CONFERENCE CALLS ON APRIL 2, 2007, WITH ENTERGYNUCLEAR OPERATIONS, INC., REGARDING THE PILGRIM LICENSE RENEWAL APPLICATION (TAC NO. MC9669)HARD COPYDLR R/FE-MAIL: JFairRWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDeEqva

RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes DLR Staff


PBuckberg SHoffman SUttal JShea JDavis CAnderson, Region 1 WRaymond, Region 1 NSheehan, Region 1 Pilgrim Nuclear Power Station cc:Regional Administrator, Region IU. S. Nuclear Regulatory Commission

475 Allendale Road King of Prussia, PA 19406-1415Senior Resident InspectorU. S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station P.O. Box 867 Plymouth, MA 02360Chairman, Board of Selectmen11 Lincoln Street Plymouth, MA 02360ChairmanNuclear Matters Committee Town Hall 11 Lincoln Street Plymouth, MA 02360Chairman, Duxbury Board of SelectmenTown Hall 878 Tremont Street Duxbury, MA 02332Office of the CommissionerMassachusetts Department of Environmental Protection One Winter Street Boston, MA 02108Office of the Attorney GeneralOne Ashburton Place 20th Floor Boston, MA 02108MA Department of Public HealthRadiation Control Program Schrafft Center, Suite 1M2A 529 Main Street Charlestown, MA 02129Secretary of Public SafetyExecutive Office of Public Safety One Ashburton Place Boston, MA 02108 Director, Massachusetts Emergency Management Agency Attn: James Muckerheide 400 Worcester Road Framingham, MA 01702-5399Mr. William D. MeinertNuclear Engineer Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056-0426Mr. Michael A. BalduzziSite Vice President Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508Mr. Stephen J. BethayDirector, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508Mr. Bryan S. FordManager, Licensing Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213Mr. John T. HerronSr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Pilgrim Nuclear Power Station cc:-2-Mr. Oscar LimpiasVice President, Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Christopher SchwarzVice President, Operations Support Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. John F. McCannDirector, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Ms. Charlene D. FaisonManager, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. Michael D. Lyster5931 Barclay Lane Naples, FL 34110-7306Mr. Michael J. ColombDirector of Oversight Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Ms. Stacey LousteauTreasury Department Entergy Services, Inc.

639 Loyola Avenue New Orleans, LA 70113Mr. James Sniezek5486 Nithsdale Drive Salisbury, MD 21801Mr. Travis C. McCulloughAssistant General Counsel Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601Mr. James RossNuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708Plymouth Public LibraryAttn: Dinah O'Brien 132 South Street Plymouth, MA 02360Duxbury Free LibraryATTN: Ms. Elaine Winquist 77 Alden Street Duxbury, MA 02332

Kingston Public Library ATTN: Reference Librarian 6 Green Street Kingston, MA 02364Ms. Mary LampertDuxbury Nuclear Advisory, Chair Pilgrim Watch, Director 148 Washington Street Duxbury, MA 02332 ENCLOSURELIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE PILGRIM NUCLEAR POWER STATION LICENSE RENEWAL APPLICATIONApril2, 2007PARTICIPANTSAFFILIATIONPerry Buckberg U.S. Nuclear Regulatory Commission (NRC)Robert Schaaf NRC Dan HoangNRC Ken Chang NRC Peter Wen NRC Richard Conte NRC Glenn Meyer NRC Tim O'Hara NRC Bryan FordEntergy Nuclear Operations, Inc. (Entergy)