UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001

SUBJECT:

CY 2023 - RESULTS OF THE U.S. NUCLEAR REGULATORY COMMISSION ANALYSIS OF THE DECOMMISSIONING FUNDING STATUS REPORTS FOR VARIOUS DECOMMISSIONING REACTORS To All Nuclear Reactor Licensees in Decommissioning:

As required by its regulations, the U.S. Nuclear Regulatory Commission (NRC) received the annual decommissioning funding status (DFS) reports for the various decommissioning nuclear power reactors and non-power reactors listed in the enclosed table.

The NRC has reviewed and analyzed the decommissioning cost estimates provided for these facilities, as required by Section 50.82, Termination of license, of Title 10 of the Code of Federal Regulations (10 CFR). Considering the information provided by the licensees, including the reported decommissioning trust fund balances, as well as earnings assumptions, the NRC has determined that the licensees listed in the enclosed table have satisfied the decommissioning funding assurance requirements of 10 CFR 50.82.

This letter confirms the correspondence, noted in the enclosed table, regarding DFS reports for permanently shutdown power reactors as required under 10 CFR 50.82(a)(8)(v)-(vii). As of the date of this letter, considering the information provided by the licensees, the NRC has determined that the licensees responsible for the various facilities listed in the enclosed table have satisfied the decommissioning funding assurance requirements of 10 CFR 50.82 for these power and non-power reactors as of December 31, 2023. This assessment was conducted in accordance with NRC Procedure REFS 70-15-00, Revision 0, Procedures for NRCs Independent Analysis of Decommissioning Funding Assurance for Operating Nuclear Power Reactors and Power Reactors in Decommissioning, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23129A781; dated May 11, 2023).

In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC website at https://www.nrc.gov/reading-rm/adams.html.

September 18, 2024 If you have any questions concerning this matter, please contact the respective project manager, as identified at ML24151A648 for the identified facility or contact me at 610-337-6954.

Sincerely, Nikki S. Warnek, Acting Chief Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery, and Waste Programs Office of Nuclear Material Safety and Safeguards

Enclosure:

Table of Decommissioning Funding Status Report Submittals for Decommissioning Licensees Covering CY 2023 Docket Nos.:

50-302; 50-10; 50-331; 50-16; 50-285; 50-183; 50-18; 50-3; 50-247; 50-286; 50-305; 50-245; 50-238; 50-219; 50-255; 50-171; 50-293; 50-206; 50-361; 50-362; 50-289; 50-320; and 50-271 License Nos.: DPR-72; DPR-2; DPR-49; DPR-9; DPR-40; DR-10; DPR-1; DPR-5; DPR-26; DPR-64; DPR-43; DPR-21; NS-1; DPR-16; DPR-20; DPR-12; DPR-35; DPR-13; NPF-10; NPF-15; DPR-50; DPR-73; and DPR-28 Signed by Warnek, Nicole on 09/18/24

ML24240A169; Ltr ML24240A169 OFFICE NMSS/DUWP/RDB NMSS/REFS/FAB R-I/EAGLT NAME MDoell MD RTurtil RT NWarnek NW DATE Aug 27, 2024 Sep 17, 2024 Sep 18, 2024

Enclosure Decommissioning Funding Status Report Submittals for Decommissioning Licensees Covering CY 2023 Reactor Licensee ADAMS Accession Number Date Submitted Crystal River Nuclear Generating Plant, Unit 3 ADP (Northstar and Orano) CR3, LLC ML24087A205 3/27/2024 Dresden Nuclear Power Station, Unit 1 Constellation Energy Generation, LLC ML24082A195 3/22/2024 Duane Arnold Energy Center FPL Energy Duane Arnold, LLC ML24071A056 3/6/2024 Enrico Fermi Atomic Power Plant, Unit 1 DTE Electric Company ML24091A001 3/31/2024 Fort Calhoun Station Omaha Public Power District ML24067A209 3/1/2024 ESADA Vallecitos Experimental Superheat Reactor (EVESR)

GEH Hitachi Energy, LLC ML24088A292 3/28/2024 Vallecitos Boiling Water Reactor (VBWR)

GEH Hitachi Energy, LLC ML24088A292 3/28/2024 Indian Point Nuclear Generating Station, Units 1, 2, and 3 Holtec Decommissioning International, LLC ML24089A117 3/29/2024 Kewaunee Power Station Kewaunee Solutions, Inc.

ML24080A070 3/20/2024 Millstone Power Station, Unit 1 Dominion Energy Nuclear Connecticut, Inc.

ML24088A235 3/26/2024 Nuclear Ship Savannah US Maritime Administration ML24094A050 3/27/2024 Oyster Creek Nuclear Generating Station Holtec Decommissioning International, LLC ML24089A117 3/29/2024 Palisades Nuclear Plant Holtec Decommissioning International, LLC ML24089A117 3/29/2024 Peach Bottom Atomic Power Station, Unit 1*

Constellation Energy Generation, LLC ML24082A195 3/22/2024 Pilgrim Nuclear Power Station Holtec Decommissioning International, LLC ML24089A117 3/29/2024 San Onofre Nuclear Generating Station, Units 1, 2, and 3 Southern California Edison ML24094A064 3/27/2024 Three Mile Island Nuclear Station, Unit 1 Constellation Energy Generation, LLC ML24082A195 3/22/2024 Three Mile Island Nuclear Station, Unit 2 TMI-2 Solutions ML24092A001 3/28/2024 Vermont Yankee Nuclear Power Station NorthStar Vermont Yankee, LLC ML24087A223 3/27/2024 Peach Bottom Atomic Power Station, Unit 1* - A shortfall in decommissioning funding was identified; however, staff determined that the licensee provided an acceptable means to address the shortfall. A separate letter will be issued to the licensee providing details of staffs review.