Advises That SAIC-85/1519-2, Review of Licensee & Applicant Responses to NRC Generic Ltr 83-28, Technical Evaluation Rept Incomplete in Four Areas Evaluated.Requests Cooperation in Obtaining Addl Info to Complete Review
ML20127N608
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 05/03/1985
From: Stolz J
Office of Nuclear Reactor Regulation
To: Beckham J
GEORGIA POWER CO.
Shared Package
ML20127N613 List:
References
GL-83-28, NUDOCS 8505230589
Download: ML20127N608 (2)


Text

Q ,"

f. ,

l' May 3,'1985 3 0lb 4 .

Deckets'Nos. 50-321' )ISTRTRtlTTON and.50-366 e wk,+ r1W' ACRS-10 NRC PDR' ' GRivenbark

.L^PDR RIngram

, ORB #4 Rdg Gray' File Mr. 'J. T. Beckham, Jr. ~HThompson TBournia Vice: President - Nuclear Generation "

OELD JPartlow Georgia Power Company- -

EJordan _-

'P. 0. Box 4545 BGrimes -

Atlanta, Georgia 30302

Dear.Mr. Beckham:

SUBJECT:

. DRAFT TECHNICAL EVALUATION REPORT'(TER) FOR' SALEM ATWS ITEM 1.2 (GENERIC LETTER 83-28)

The staff has completed a preliminary review to assess the completeness and adequacy of' licensee responses to Generic Letter 83-28 Item 1.2. For Hatch

~ Units 1 and 2, your response was found to be incomplete in four of the areas evaluated.

The enclosed TER provides a technical evaluation representing the staff's initial judgment of the areas evaluated. Pen and ink changes have been made to.the TER by your project manager to make the wording consistent with our approach.

In. order to preserve our present review schedule, we would appreciate your cooperation in obtaining additional information that will permit us to complete our review. It would appear that the needed information your facility could be obtained by telephone conference within one week of your receipt of the DRAFT TER. Your project manager will be working with you to arrange an acceptable' time to conduct the necessary conference calls.

Sincerely,

% MAAL 31su:D g dEd.830E45>'

John F. Stolz, Chief Operating Reactors Branch #4 Division of Licensing

Enclosure:

Draft TER on Salem ATWS Item 1.2 cc w/ enclosure:

See next page O

ORBi LB:#2:DL 0 .

GRiv ark;cf TBournia JStj 5/$/85 5/J/85 5/ 8 8505230589 DR 850 3 p ADOCK 0500 21 PDR

L ,

.c _

Hatch 1/2 50-321 and 50-366

Georgia Power Company ccw/ enclosure (s):

G. F. Trowbridge, Esq. Regional Radiation Representative Shaw, Pittman, Potts and Trowbridge EPA Region IV 1800 M Street, N. W. 345 Courtland Street, N. E.

Washington, D. C. 20036 Atlanta, Georgia 30308 Ruble A. Thomas Resident. Inspector Vice President- U. S. Nuclear Regulatory Comission P. O. Box 2625 Route 1, P. O. Box 279 Southern Company Services. Inc. Baxley, Georgia 31513

Birmingham, Alabama 35202

. _ Dr. J. Nelson Grace, Regional Louis B. Long Administrator Southern Company Services, Inc. U. S.-Nuclear Regulatory Commission P. O. Pox 2625 . Region II Rimingham, Alabama 35202 101 Marietta Street, Suite 2900 Atlanta, Georgia 30303

' Chairman Appling County Commissioners County Courthouse Charles H. Badger Raxley, Georgia 31513 Office of Planning and Budget Doom 610 270 Washington Street, S. W.

Mr. L. T. Gucwa Atlanta, Georgia 30334 Georgia Power Company Engineering Department P. D. Box 4545 J. Leonard Ledbetter, Commissioner Atlanta, Georgia 30302 Department of Natural Resources 270 Washington Street, N.,W.

Atlanta, Georgia 30334 Mr. H. C. Nix, Jr. General Manager Edwin I. Hatch Nuclear Plant Georgia Power Company P. O. Box 442 Baxley, Georgia 31513

.