ML20246D376

From kanterella
Jump to navigation Jump to search
Requests Addl Listed Info Re Util 881130 Response to Violations Noted in Insp Rept 50-482/88-200.Info Requested within 30 Days of Date of Ltr
ML20246D376
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 05/02/1989
From: Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Withers B
WOLF CREEK NUCLEAR OPERATING CORP.
References
GL-83-28, NUDOCS 8905100210
Download: ML20246D376 (3)


See also: IR 05000482/1988200

Text

-_ _ _

-

. i

-: i

. . . . , 'o

MAY - 2 1989

In Reply Refer To: . 'i

Docket
STN 50-482/88-200 (

L j

1

i

Wolf Creek Nuclear Operating Corporation

ATTN: Bart D. Withers

President and Chief Executive Officer >

P.O. Box 411 )

Burlington, Kansas 66839 i

i

Gentlemen:

f

This refers to your letter of November 30, 1988, which was in response to our

letter and Notice of Violation dated October 19, 1988. We have reviewed your

response and have held a telephone conference between your Messrs. O. L. Haynard,

C. E. Parry and others, and our Messrs J. E. Gagliardo and D. R. Hunter on

April 14, 1989. As discussed in the telephone conference, we have reached the

decisions or need additional information regarding your response to the

violations as delineated below:

'

Violation A (482/88200-01) Failure to Take Adequate Corrective Actions

Your' corrective actions appear to be acceptable and appropriate to correct

the conditions listed in the violation. We shall review the

implementation of your corrective actions for this violation during a

future inspection in order to determine that full compliance has been

achieved and will be maintained. We continue to believe that the examples

of failure to take corrective action were all valid; however, the scope of

your committed corrective actions makes further discussion of this

point moot.

Violation B (482/88200-03) Inadequate Procedure

We request that you provide additional information regarding the training

and qualifications standards which define " skill of the craft." We

l further request that you provide information on how planners, engineers or

others drafting work instructions are knowledgeable of what is encompassed

in " skill of the craft" for the various maintenance disciplines.

ViolationC(482/88200-04) Failure to Establish Procedure

The violation was written to state that you had failed to obtain three

Service Information Letters (SILs) affecting your Emergency Diesel

Generator (EDG) and that you had f ailed to review or evaluate five other

SILs affecting your EDGs. In your response, you state that your only

commitment is to review vendor information, not to obtain vendor

information. We reject this argument, for the intent of Generic

Letter (GL) 83-2P was to assure that pertinent information related to

RIV:0PS* C:0PS* D:DRS * D:DRPg RA Af

DRHunter/cjg JEGagliardo JLMilhoan LJCallan R ftin

/ /89 / /89 / /89 /v/89 /p/89 pl

  • previously concurred i l

8905100210 890502 2

ADOCK 0500

{DR . _ _ _ _ _ - _ _ _ _ _ __-_________i

__ . _ _ . _ - _ _ .___-

.

. . . , ,

Wolf Creek Nuclear Operating -2-

Corporation ,

maintaining safety-related equipment operable was identified and used. Your

position indicates that you may not have grasped the safety significance

of GL 83-28. We request that you provide us with a fuller description of

your corrective actions with regard to the review and use of vendor

information for safety-related equipment.

Violation D (482/88200-05) Failure to Provide Inspection

We are in full agreement that WCNOC, as licensee, has the ultimate

responsibility for the installation and operation of Wolf Creek. The

issue in this violation is not what responsibility lies with other

4

organizations such as vendors; rather the issue is whether or not the

diesel generators are installed so that they can reasonably be expected to.

remain operable under all design basis conditions.

Violation E (482/88200-06) Failure to Follow Procedures

We have reviewed your response to this item and find it responsive to the

concerns raised in our Notice of Violation. We shall review the

implementation of your corrective actions during a future inspection to

determine that full compliance has been achieved and shall be maintained.

Please provide the information requested above with 30 days of the date of this

letter.

Sincerely.

ORIGINAL SMEDW

ROBERT D. MAgg

-Robert D. Martin

Regional Administrator

cc:

Wolf Creek Nuclear Operating Corporation

ATTN: Otto Maynard, Manager

of Licensing '

P.O. Box 411

Burlington, Kansas 6b839

Wolf Creek Nuclear Operating Corporation

ATTN: Gary Boyer, Plant Manager

P.O. Box 411

Burlington, Kansas 66839

____________a

. _ - . ._.

- _ - _ _ - _ - - _ - _ - _ _ _ - ___

c- ~

..

~

.: . - .. ,

11

. Wolf Creek Nuclear' Operating -3- ,

Corporation

'

,

"

- Kansas, Corporation Commission;

ATTN: Robert D. Elliott, Chief Engineer

Fourth Floor. ' Docking. State 0ffice Building:

Topeka, Kansas ~ 66612-1571

'

Kansas Radiation Contro1' Program Director

bectoDMB(IE01)-DRS&DRP

'l

bcc distrib. by RIV: -

RRI .

R. D. Martin, RA

Section-Chief (DRP/D)' DRP

RPB-DRSS- R. DeFayette, RIII

RIV File SRI, Callaway, RIII

MIS System RSTS Operator

,ProjectEngineer(DRP/D) Lisa'Shea,RM/ALF

L' - DRS

'

D. V. Pickett, NRR Project Manager (MS: 13-D-18) ,

D. R. Hunter J. E. Gagliardo

,

.-

i

rz

--1 - _ -- - ._ a-wL---...-- - - - - - - -- - - - - - -- - - - - _ _ - _ - - - --x--_--

,

i

S

9

% * e

8

'

i

V

m i W4#LF CREEKwn: NUCLEAR OPERATING CORPORATIO 1

Bart D. Withers DEC -51988  !

1

President and

Chief Executive Officer

i

"

j "'"*

.

/j )

. __ / l

November 30, 1988

WM 88-0312

U. S. Nuclear Regulatory Commission

ATTN: Document Control Desk

Mail Station P1-137

Washington, D. C. 20555

i

Reference: Letter dated October 19, 1988 from L. J. Callan, NRC to

B. D. Withers, WCNOC

Subject: Docket No. 50-482: Response to Violations 482/88200-01,

03, 04, 05 and 06

Gentlemen

This letter provides Wolf Creek Nuclear Operating Corporation's (WCNOC)

responce to the five violations documented in the Reference.

(]y

,

'-

involved failure to take adequate corrective

inadequate procedures (-03), failure to establish procedures (-04), failure

actions

The violations

(482/88200-01)

to provide inspection (-05) and failure to follow procedures (-06). The

Reference provided the NRC's enforcement assessment of the findings from the

Quality Verification Function Inspection (QVFI) conducted in June 1988. The

QVFI findings covered activities that were performed between 1984 and 1988.

It should be noted that some of these findings had been documented in

previous NRC Inspection Reports and corrective actions were taken or

initiated in 1987.

Attachment I provides WCNOC's response to the violations and Attachment II

provides detailed information on the examples associated with the violation j

involving failure to take adequate corrective action (482/88200-01).

Although WCNOC does not agree with all of the violations and examples,

Attachments I and II documents the corrective actions and/or program

enhancements for all of the identified concerns.

On November 18, 1988, in a telephone discussion between Mr. G. L. Constable,

NRC Region IV, and Mr. O. L. Maynard, WCNOC, the submittal response time was

extended until November 30, 1988.

[

v

P.O. Box 411/ Burhngton, KS 66839 / Phone: (316) 364 8831

.

] [ A 1 Equal opporturwty Employer MOHCNET '

_ __ - - -

_ _ - _ _ _ _ --__-___ ____ _ _ _

s

T

,

-

.

. . . . .

.

_ _

i

WM 88-0312 1

Page 2 of 2

November 30, 1988

If you have any questions concerning this matter, please contact me or

Mr. O. L. Maynard of my staff.

Very truly yours,

Bart D. Withers

President and

Chief Executive Officer

BDW/jad

Attachments (2)

cc: B. L. Bartlett (NRC), w/a

D. D. Chamberlain (NRC), w/a

R. D. Martin-(NRC), w/a

D. V. Pickett (NRC), w/a

O

l

l

4

...

_ _ - _ _ _ _ - _ _ _ _ _ _ - -

..

.. . ,--*

,' * -

'

, , . . .

I

[\ Attachment I'to WM 88-0312

Page 1 of 10

Violation (482/88200-01): Failure to Take Adeauate Corrective Actions

l

l

Finding: I

Appendix B, 10 CFR 50 Criterion XVI, requires that conditions adverse to

quality, such as equipment failure and malfunctions, are promptly identified

,

and corrected. It alsc states that the causes of significant conditions

E adverse to quality be detenmined and corrective actions taken to preclude

'

their repetition. The licensee's Updated Safety Analysis Report, Revision

0, paragraph 17.2.16.1, states in part that corrective action measures have

been established to ensure that conditions adverse to quality are promptly

identified, reported, and corrected to preclude recurrence. Significant

conditions adverse to quality may include a recurring condition for which

past corrective action has been ineffective. Contrary- to these

requirements:

1. The licensee had not taken the corrective actions specified in

engineering evaluation request EER 85-GK-08 (completed November 27,

1985) to resolve -the electrical breaker malfunctions of the heating,

ventilating, and air conditioning- (HVAC) system in the control.

__ building.

--

2. The licensee had not fully investigated the underlying causes of the

multiple HVAC damper failures in the control building.

3. The licensee had not promptly taken action to resolve a large number of

actuations in the control room ventilation isolation signal (CRVIS)

system that were attributed to the control room habitability system

chlorine monitor malfunctions that began in 1985.

4. The licensee had not taken actions to correct multiple fire protection

system failures that resulted from the apparent misapplication of valve

microswitches.

!

5. The licensee has not aggressively pursued the cause and taken action to i

resolve malfunctions in the emergency diesel engine's jacket water  !

pressure sensing system that began in 1986.

Reason for Violation:

Although WCNOC does not agree that all of the examples cited above represent

a violation of Appendix B, 10 CPR 50 Criterion XVI, WCNOC does agree that

.some of the identified problems could have been resolved more ,

expeditiously. The reason that some equipment failures and malfunctions i

. c' s . have not been corrected as promptly as desired is lack of overall

(' programmatic guidance to define and control a root cause evaluation process i

\s for hardware deficiencies.

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - - _ _ _ . _ _ - - - _ - - _ _ _ _ - _ - - - _ - _ - _ - _ - _ - _ - _ _ _ - _ _ - _ _ _ _ _ - - _ - _ _ _ - - _ _ _ _ _ - -

_ .. _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - - _ _

i

, .

  • '

,,

..

Attachment I to WM 88-0312

,, Page 2 of 10

(

L

Corrective Steps Which Have Been Taken and Results Achieved:

'

Specific responses and corrective actions for the examples of this violation

are discussed in Attachment II. Overall corrective actions taken which

address this violation include a restructuring of the daily planning

meetings to focus management attention on problems and corrective actions

rather than on work status. This forum allows work groups to identify

specific problems and get appropriate management attention. In addition,

selected personnel have been trained in root cause analysis. Another step

which has been taken is the addition of a person from Nuclear Plant

Engineering as a member of the on-site Plant Safety Review Committee.

Again, this provides a forum in which various issues can be discussed from

both the Engineering and Operations perspective relative to safety

significance and priorities. These steps have resulted in improvements in

the identification of problem areas and in the cooperation and coordination

among work groups.

Corrective Steps Which Will Be Taken to Avoid Further Violations:

WCNOC Senior Management continues to stress the need to identify the root

cause as problems arise. To strengthen this approach, WCNOC is developing a

formalized root cause analysis program for hardware deficiencies. This

program will include a detailed methodology for root cause analysis as well

p,$)h as requirements for training, documentation, and program interfaces. WCNOC

{

g,,,/ believes that integration of this root cause analysis program with existing

programs will result in a more effective and efficient process for

identifying and correcting conditions adverse to quality.

Date When Full Compliance Will Be Achieved: ,

i

The root cause analysis program will be initially implemented in March,

1989. The required training will be complete by the end of 1989.

Violation (482/88200-03): Inadeauate Procedure

Pinding:  !

Appendix B, of 10 CFR 50, Criterion V, requires that activities affecting

quality be accomplished in accordance with docunented instructions,

procedures, or drawings of a type appropriate to the circumstances.

Instructions, procedures, or drawings shall include appropriate quantitative

or qualitative acceptance criteria for determining that important activities

have been satisfactorily accomplished.

Contrary to the above, NRC inspectors observed during a component cooling

water pump maintenance activity that the licensee's procedures and

instructions provided to the maintenance personnel did not include

/ appropriate cautions or details for removal of the bearing.

'\

_ _ _ _ _ _ - _-_-_-_- __

. .

..

Attachment I to WM 88-0312 )

'

Page 3 of 10

,

,

i ~,k

LJ

Reason for Violation:

Although WCNOC does not agree that this specific event represents a

violation of Appendix B, 10 CFR 50, Criterion V, WCNOC does agree with the

factual information provided in the Inspection Report and acknowledges that

some work procedures could provide more detail to the crafts. However,

WCNOC craft workers do possess and are expected to utilize certain skills

and judgement in their work activities. This bearing removal activity falls

well within the range of ANSI N18.7, 1976 Section 5.2.7 as skills normally

possessed by qualified maintenance personnel. Procedures can never be

written in such detail that the crafts are relieved from recognizing

potential problem areas not identified in the procedure.

The reason the procedure did not contain the level of detail desired by the

NRC inspector is that WCNOC Maintenance work procedure writers rely on the

skill-of-the-craft in many cases and do not put a high level of detail in

the work procedure.

Corrective Steps Which Have Been Taken And Results Achieved:

Subsequent to concerns voiced by the NRC inspector, work was stopped, the

vendor was contacted, and heating limitations were added to the governing

work request by revision. It should be noted that after the limitations

f'"' were added to this work request and the work resumed, the shaft coupling hub

(' released at approximately 400 degrees F which is well below the 750 degree F

limit identified by the manufacturer. Therefore, for this particular work

activity, the reliance on skill-of-the-craft would have resulted in an

acceptable bearing removal.

WCNOC Maintenance supervision have discussed this event with the maintenance

work instruction writers and craft supervisors. Work instruction writers

have been instructed to not rely too heavily on skill-of-the-craft and use

" cautions" where appropriate. It has also been emphasized to the crafts to

request technical assistance when a work activity is not going as planned.

Corrective Steps Which Will Be Taken To Avoid Further Violations:

WCNOC believes the corrective actions discussed above should prevent

recurrence. It should be noted, however, that the degree of detail needed

in work procedures to comply with Appendix B, 10 CFR 50, Criterion V, is

very subjective and perceived compliance will vary between individuals

assessing specific situations. WCNOC strivos to meet the regulations as we

interpret them and as we get additional guidance.

Date When Full Complianca Will Be Achieved.

Full compliance has been achieved.

g

i <

\

- _ _ _ _ _ _ . _ _ _ _ _ _ ,

.

.

.

.

.

Attachment I to WM 88-0312

,_

Page 4 of 10

/ \

.

Violation (482/88200-04): Failure to Establish Procedures

Finding:

Appendix B, 10 CPR 50, Criterion V, requires that activities affecting

quality be accomplished in accordance with documented instructions,

procedures, or drawings.

Wolf Creek licensing condition 2.C(13) describes the licensee's vendor

interface program as part of their response to NRC Generic Letter 83-28.

Wolf Creek Nuclear Operating Corporation Procedure, KGP-1311, Revision 1,

specifies the function of the Industry Technical Information Program

(ITIP). Part of the ITIP requires that vendor reports be reviewed to

determine their applicability to Wolf Creek Generating Station (WCGS) and,

if necessary, a detailed evaluation is to be performed to determine the

effects on WCGS.

Contrary to the above, the licensee had not obtained three of the SILs that

were potentially applicable to the EDGs supplied to Wolf Creek. It was

further determined that the five EDG SILs that the licensee had received had

not been formally reviewed or evaluated.

l

Reason For Violations

/ \

( ,,/ Although procedure KGP-1311, " Industry Technical Information Program" (ITIP) l

requires vendor reports be reviewed for applicability, it does not require

WCNOC to establish a program for obtaining vendor information. This

procedure is consistent with WCNOC's letter to the NRC dated December 10,

1986 and the March, 1984 Nuclear Utility Task Action Committee response to ,

Generic Letter 83-28, Item 2.2.2. Therefore, the statement in the finding:  !

' Contrary to the above, the licensee had not obtained three of the SILs that

were potentially applicable to the EDG's supplied to Wolf Creek', appears to

be inappropriate and WCNOC does not agree that this item is a violation of

Appendix B, 10 CFR 50, Criterion V.

I

Prior to November 1986, the emergency diesel generator (EDG) Service

'

Information Letters (SILs) were being received by an individual employed by

Wolf Creek's architect / engineering firm. Upon leaving the Wolf Creek

project in November, 1986, the individual contacted the vendor and had his

name removed from the list of receivers. It is believed the above

individual assumed other personnel on site were receiving the SILs. This

resulted in no SILs being received by WCGS.

O

I I

C'

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ - - _ _ _ _ - _ _ _

_ . - _ _ _ _ _ _ __

-

,

..

,

Attachment I to WM 88-0312

Page 5 of 10

{A)

Q,)

This deficiency was discovered in November, 1987, at which time the vendor

was contacted and requested to provide all previous SILs that pertained to

WCGS. The vendor indicated that five SILs pertained to WCGS's model of

diesel engines. Numerous delays were encountered in receiving the SILs and

the vendor was contacted four additional times in an attempt to obtain the

SILs. The vendor indicated they were reluctant to provide the SILs because

the SILs were out of date and were in the process of being revised. After

emphasizing to the vendor WCNOC's strong desire to obtain the SILs due to

the potential safety significance of such information, five SILs were

received in March, 1988, with the understanding from the vendor that up-to-

date revisions would be received in approximately four to six weeks.

Since it was believed that the SILs would soon be revised, the ITIP

Coordinator sent the SILs to the appropriate organizations for an informal

review. The review determined that the SILs had no immediate affect on the

operability of the diesel engines. Therefore, it was determined that the

detailed evaluation required by procedure KGP-1311 could be delayed pending

the receipt of revisions to the SILs.

Corrective Steps Which Have Been Taken and Results Achieved: ,

The five SILs received from the vendor and three additional SILs received

from the NRC inspector were reviewed in accordance with procedure KGP-1311

- on June 16, 1988 after discussions with the NRC inspector. The evaluation of

, the SILs did not identify any substantial safety concerns. However,

(__,/ additional preventative maintenance activities have been incorporated into

the Preventative Maintenance Data Base as a result of the SILs.

A Programmatic Deficiency Report was initiated to determine if additional

EDG SILs applicable to WCGS were not provided by the vendor. The Supplier

Quality organization performed a surveillance at the vendor's offices on

July 21, 1988, and identified two additional SILs which had not been

provided by the vendor. These two SILs were subsequently reviewed and

evaluated in accordance with procedure KGP-1311. Additionally, the

surveillance verified the appropriate contacts were in place on the vendor's

list of receiver's for SILs and that an adequate system exists for

transmittal of future SILs.

Corrective Steps Which Will Be Taken To Avoid Further Violations:

The vendor EDG SIL program will be audited on a regular frequency to verify

that an adequate system exists for transmittal of SILs. Although, as

explained above, WCNOC's vendor interface program is currently in

compliance with commitments associated with NRC Generic Letter 83-26, a

program is currently under development to enhance the vendor interface

process at WCGS. A procedure is being developed to provide a method for

contacting certain hardware suppliers to determine if they have issued

letters or bulletins which could impact components or systems at WCGS. This

fs program will be implemented by July 31, 1989.

(

v)

- _ _ _ _ _ - _ - _ . _ - _ _ - _ - _ _ - _ _

_ _ _ _ _ _ _ - _ - _

,

  • '

.

,

Attachment I to WM 88-0312

[]

e

Page 6 of 10

Nj

Date When Full Compliance Will Be Achieved:

WCNOC believes that the decision not to perform the detailed evaluation of

the SILs was appropriate based on the informal review and because the vendor

had indicated that these SILs were in the process of being revised. Full

compliance has been achieved.

I

Violation (482/88200-05): Failure to Provide Inspection

Finding l

Criterion X of Appendix B to 10 CFR 50 requires that a program for

inspection of activities affecting quality be established and executed by or

for the organization performing the activity to verify conformance with the

documented instructions, procedures, and drawings for accomplishing the

activity.

Contrary to the above, NRC inspectors found that during construction of the

EDGs, the licensee had not verified that the safety-related seismic and

vibration control emergency diesel turbocharger cooling water pipe supports

had been installed as required by the vendor's design drawing.

O Reason For Violation

/

!

\~ # WCNOC recognizes that it has the ultimate responsibility for assuring that

the installed systems are capable of performing its safety function.

Although it is true that Wolf Creek Generating Station (WCGS) had not

verified that the safety-related seismic and vibration control supports were

installed, Wolf Creek Nuclear Operating Corporation (WCNOC) believes that

this is not a violation of 10 CFR 50, Appendix B, Criterion X requirements.

As explained below, the receipt inspection program which was in place when

the Emergency Diesel Generators (EDG) were shipped to WCGS complied with 10

CFR 50 Appendix B, Criterion X requirements and did not require inspection

of these supports. Rather, verification of the installation of the required

components was the responsibility of the vendor. WCNOC believes that it is

not appropriate to cite activities under the control of a vendor's quality

program as a violation of WCNOC's Criterion X requirements unless this

results in a degradation of the ability of the EDG to perform its safety

function. WCNOC believes that the Quality programs in place were adequate

for providing assurance of EDG functionality. The vendor activities

identified in this particular case did not invalidate the EDG's ability to

perform its safety function during the design basis accidents.

The EDGs were originally furnished by Colt Industries during the

construction phase of WCGS as skid mounted subcomponent systems due to the

size and complexity of the EDGs. Each EDG was manufactured and furnished I

under Colt's Quality Program. This program was reviewed and accepted by l

}

j\

(} ,/

three separate organizations, the ASME,

(Bechtel Power Corporation), and Wolf Creek.

the organization procuring the EDGs l

j

1 i

i

i

1

!

l

1

_ _ _ _ - - _ - _

_ _ _ _ _ - _ - _ _ _ _ _ - - - _ - _ _ _

, .

.

  • '

Att chm'ent I to WH 88-0312

Page 7 of 10

%sl In addition, Bechtel established and executed a program which encompassed

the review of EDG documents (e.g., drawings, procedures, reports, etc.),

surveillance of manufacturing processes and final shop inspection of the

EDGs including skid mounted subsystems prior to their release for shipment.

These activities were in addition to those performed by the Authorized i

Nuclear Inspection agency engaged by Colt. I

At WCGS, a receipt inspection program, QCP-I-01, " Receipt, Storage, and

Preservation of Quality Related Material and Items' was established and

executed by the constructor acting on behalf of KG&E. Under this program, i

for the material / items which were procured by another organization, such as !

Bechtel, and also had a final ship inspection report (or equivalent release

document) indicating that the procuring organization had performed a final

shop inspection, receipt inspection was restricted to the following

elements:

a) review of documents submitted with the material / items for

completeness, legitability, and the correct number and type of

documents.

b) inspection for evidence of shipping / handling damage.

c) an accountability review for correct material / items and number of

material / items.

\s_/ d) a general configuration review, as appropriate, to verify size,

length, finish', etc.

Inspection to the level of detail necessary to verify each and every

component, subcomponent, and sub subcomponent on a complex piece of vendor

furnished equipment, such as the EDGs, was the responsibility of the vendor

and their ANI as applicable under the vendor's Quality Program.

Corrective Steos Which Have Been Taken and Results Achieved:

,

When it was discovered that the seismic and vibration control supports were

missing, WCNOC contacted Colt to determine if the turbocharger cooling pipe j'

could perform its intended function without the supports and whether the

turbocharger cooling pipe would experience cracking or the flange bolts

would loosen as a result of excessive vibration.

Colt refered to Colt Industries' Engineering Report No. M-018-0367-02,

l " Seismic Calculations for Skid Mounted Piping." A tchle in this report

indicated that the support bracket would be required for the turbocharger

cooling piping in a seismic event if the length of the piping was greater

than 60.7 inches.

,-~~

\'

1

N--

i

, 1

-_ _ - _ _ _ - _ _ _

.

. .

. -

Attachment I to WM 88-0312

Page 8 of 10

l \

kj

The subject piping was measured and found to be 56 inches in length; thus it

was concluded that the turbocharger cooling pipe would perform its intended

function during a seismic event without the support brackets. WCNOC also

performed a confirmatory seismic calculation, which also indicated that the

pipe did not require the support to withstand seismic loading. .

1

Even though the available engineering data did not support installation of

the supports for seismic reasons, Colt recommended WCNOC install the four

missing supports to ensure that vibraticns from the operating diesel engine

would not cause degradation of engine components. In additi.on, Colt

recommended that WCNOC visually inspect the pipes for cracking and a loss of

jacket cooling water and perform a torque inspection for all associated pipe

flange bolts.

WCNOC took immediate actions to fabricate and install the four pipe supports

and performed the inspections recommended by Colt. In addition WCNOC

performed nondestructive examinations on all four turbocharger cooling water

pipes and a vibration test and analysis to determine if there were any

additional adverse effects on the cooling pipe caused by operating the EDGs

without the supports. No adverse effects of the missing supports were

revealed.

Following these immediate corrective actions, the investigation focused on

the reasons that the "as installed" configuration was different than the

f]

'- j configuration depicted in the Colt Instruction Manual M-018-00309. Working

with Colt, it has been determined that while the drawings contained in the

instruction manual may show the installation of components such as supports,

the drawings are included for the purpose of identifying parts, and are not

intended as the final as built configuration drawings. Thus the fact that

the parts drawings in Manual M-018-00309 may show the vibration control

supports does not mean that these supports are required in order for the

EDGs to fulfill their design function.

In early September 1988 WCNOC performed a walkdown of tubing and pipe

supports on the Lube 011, Fuel Oil. Injection Cooling and Air Start systems

of both EDGs. This walkdown involved personnel from NFE, Maintenance and

Quality Control utilizing Colt Manual M-018-00309. As a result of the

walkdown, deviations from the vendor manual were discovered on both EDGs.

Appropriate documentation has been issued for evaluation and updating of the

applicable drawings in M-018-00309 to more accurately reflect the existing

configuration of the EDGs. NPE is currently working with Maintenance and

Colt in response to these items. No adverse affects on the proper

functioning of the EDGs has been identified to date.

m

  • w/

__ ____ _____

'

I

l

Atta'chment I to WM 88-0312

'

Page 9 of 10

,/ m

k

\ Corrective Steps Which Will Be Taken To Avoid Further Violations:

The actions discussed above should avoid further instances of vendor

nonconformances relative to seismic and vibration control supports on the

EDGs. In addition, actions discussed in response to violation 482/88200-04

relative to the vendor interface program should help reduce further problems

in this area.

Date When Full Compliance Will Be Achieved:

Evaluation of the deviations identified during the September 1988 walkdown

of the EDGs will be complete by 12/31/88.

Violation (482/88200-06): Failure to Follow Procedures

Finding:

Technical Specification 6.8.1 requires that written procedures be

established, implemented, and maintained for the fire protection program.

Procedure ADM 13-103, Revision 5 " Fire Protection: Impairment Control,"

implements procedures for impaired fire protection equipment.  ;

i

,_s

Wolf Creek Updated Safety Analysis Report, Section 9.5, Table 9.5.1-3 (sheet l

/ s 4), requires that all fire barriers and their penetrations separating '

( , ) safety-related areas from those that are not safety-related or separating

portions of redundant systems important to safe shutdown shall be operable

at all times. Should one or more be found to be inoperable, within one hour l

a continuous fire watch must be established on one side of the affected

barrier or an hourly fire watch patrol must be established.

Contrary to the above, the licensee failed to establish the required fire

watch for penetration OP 142S1099 after an engineering disposition, did not

establish that the penetration would meet fire protection requirements. The  !

engineering disposition was completed on May 3, 1988; the licensee posted

the fire watch on June 14, 1988.

Reason for Violation:

The engineering disposition for Corrective Work Request (CWR) 00688-88 was

approved on May 16, 1988. The disposition could not establish that

penetration OP 142S1099 would meet the fire qualification testing

requirements. Procedure KPN E-314 " Disposition of Field Change Documents",

requires notification of Operations when the disposition of special-scope

nonconformances result in an inability to accept an unconditional "USE-AS-

IS" request. For those nonconformances where the impact should not be

allowed to exist without compensatory provisions, verbal notification to the

Control Room Shift Supervisor is made. The engineering personnel involved

,__ did not recognize that compensatory measures were required based upon the

/

) results of the disposition, therefore no priority was placed on

( _,/ dissemination of the disposition.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ - _ - _ _ _ _ _ _

-

,

<

,

,

... .

,

Attachment I to UM 88-0312 ]

1

Page 10 of 10 ]

ys

(v i

Similarly, procedure ADM 13-103 " Fire Projections impairment Control", )

l

.

Section 4.3 requires the reporting of emergency impairments (equipment '

degradation or failure) to the Fire Protection Coordinator as soon as

possible after discovery. When the disposition was received by Maintenance

personnel, it was not recognized that a fire impairment was required.

Therefore the Fire Protection Coordinator was not noti fied and the work

request was not handled in an expeditious manner.

Corrective Steps Which Have Been Taken And Results Achieved:

On June 14, 1988 Fire Protection Impairment Control Permit No.88-244 was

issued and an hourly firewatch patrol established. The existing type RB-9

penetration closure material (Radflex) was replaced with an M-9 penetration

closure material (RTV foam) on June 17, 1988.

Corrective Steos Which Will Be Taken To Avoid Further Violations:

This violation will be discussed with the Nuclear Plant Engineering l

personnel involved and placed in Maintenance required reading.

Additionally, strict adherence to procedures will be stressed to Nuclear

Plant Engineering and Maintenance personnel.

Date When Full Compliance Will Be Achieved:

Full compliance will be achieved by December 30, 1988.

I

C

(

,__.____,________-____-_m____-____-_____m_ - _ _ _ _ . _ _ _ _ _ ._

- - - - _ _ - _ _ - - - - _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ - - _ _ ._ - - - - _ _ _ _ - _ _ _ _ _ _ _ _ . - _

_ _ - - - _ _ _ - _ _ - - - - _

.

. .

,

4

. ..

Attachment II to WM 88-0312

Page 1 of 6

N

[G Responses to Examples Cited In Violation 482/88200-01

Example:

1. The licensee had not taken the corrective actions specified in

engineering evaluation request EER 85-GK-08 (completed November 27,

1985) to resolve the electrical breaker malfunctions of the heating,

ventilating, and air conditioning (HVAC) system in the control

building.

Responses

A review of maintenance history for the circuit breakers for control room

air conditioning unit SGK05B identified that nuisance tripping of the

breakers was occurring between December 31, 1984 and February 10, 1985.

This review identified that this same problem was not occurring on the

opposite train, SGK05A. During this time frame, WCGS was in pre-licensing

start-ups and system testing. As part of the system testing phase,

adjustments were made to the operation of the HVAC system such that the'

nuisance tripping of the breakers was no longer occurring.

Engineering ? valuation Request (EER) 85-GK-08 was initiated on July 22,

j -~ 1985, as a precautionary measure in the event the adjustments had not

i

corrected the problem and nuisance tripping reoccurred. The engineering

, \s disposition to the EER,- was issued on December 3, 1985 recommending the

installation of new breakers with higher instantaneous trip

characteristics. Subsequently, Plant Modification Request (PMR) 1441 was

initiated to replace the breakers if needed. During the period of February

10, 1985 to December 3, 1985, no problems were experienced with the breaker

for SGK05B tripping. Additionally, maintenance history indicates no further

problema with nuisance tripping of the breaker. Therefore, the actions

teken during plant start-up and system testing had resolved the problem and

implementation of the PMR was not appropriate.

WCNOC has initiated the actions necessary to cancel the PMR. Additionally,

l WCNOC will evaluate existing engineering evaluation request tracking system

l relative to this issue.

Example:

2. The licensee had not fully investigated the underlying causes of the

multiple HVAC damper failures in the control building.

!

!

L_____ _ _ _. _ _ _ . _

'

. _ _ _ _ _ _ _ - _ .

. ,

t

  • ^

Attachment II to WM 88-0312

Page 2 of 6

!

)

\s_ / l

Response:

1

During November 1987, a Safety Systems Outage Modifications Inspection j

(SSOMI) identified that appropriate corrective action in preventing repeated

damper failures was not taken when five CRVIS damper failures were

experienced during the period of June 25 to November 3, 1987. As a result i

of the SSOMI finding, a review of the maintenance work requests for

dampers / actuators OK-D-085/GK-HZ-29A, GK-D-081/GK-HZ-029B. GK-D-084/GK-HZ-

40A, GK-D-085/GK-HZ-40B was conducted. This review identified that the

actuators were reworked during 1984 with some machining being conducted on

the couplings. In 1985, GK-HZ-40A and B were replaced due to the actuators

being jonned. In 1987, failures of GK-HZ-29A, 40A and 40B, occurred which

required replacement of the actuators. During the previous refueling

outage, the vendor was brought on site to assist in identifying the cause of

the failures. Discussions with the vendor indicated that these failures,

could be attributed to a udsalignment of the coupling and the saddle because

of previous maintenance and the method of clamping the dampers when blocking

them open or closed. It was then determined that WCGS did not have the

appropriate vendor shop drawings identifying strict coupling tolerances and

clearances.

The appropriate tolerances and coupling clearances were obtained from the

vendor and an alignment jig was fabricated to assist in alignment of the

f ~sg saddle and the coupling. The vendor shop drawings were obtained and issued

( ) as controlled drawings. Three of the above dampers were realigned. The

\s_/ fourth damper was inspected and determined to be within the tolerances

provided.

Example:

3. The licensee had not promptly taken action to resolve a large number of

actuations in the control room ventilation isolation signal (CRVIS)

system that were attributed to the control room habitability system '

chlorine monitor malfunctions that began in 1985.

Response

While WCNOC agrees that resolution of the chlorine monitor malfunctions has

taken longer than desired, the actions that have been taken have been

extensive and thorough. The root cause of the monitor malfunctions has been

determined to be poor design of the monitors. The poor design has caused

tape breakage, bunching, and spurious spikes, which has resulted in high

maintenance required to keep the monitors operational.

As a result of the frequent actuations of CRVISs due to apparent chlorine

monitor malfunctions, plant staff personnel surveyed the equipment on a

daily shift basis for indications of possible malfunctions. Plant

Modification Request (PMR) 1207 was issued on June 12, 1985 to confirm that

~g the monitors were the source of the erroneous CRVISs.

'

l

_ _ - _ _ _ _ _ - - _ _ - _ _ . - _ -

_ . _ - _ - _ - . _ _ - _ _.

__ _ _ _ _ . . _ _ _ ,

.

^

Attachment II to WM 88-0312

Page 3 of 6

isp \,

V

In January,1986 a study was undertaken to add additional chlorine monitors

in order to implement a 2 out of 3 CRVIS logic. In March, 1986, a letter

was sent to MDA Scientific, manufacturer of the monitors, which pointed out

the various problems WCGS was having and requested them to evaluate the

situation and respond. Approximately one week later, MDA did respond with

the steps they were going to undertake.

On May 21, 1986, a second letter was sent to MDA requesting additional

actions. MDA again responded with suggested improvements. During this time

frame, Requests for Quotation were sent to MDA, Consolidated Controls

Corporation (CCC), and Anacon to support a study being performed by

engineering to either add additional MDA monitors to allow a 2/3 logic or

replace the monitors with Anacon or CCC monitors. The study, which was

submitted on December 9, 1986 recommended replacing the MDA monitors with

Anacon monitors.

During the latter part of 1986, WCNOC began investigating the change from

our present chlorination system (liquid) to a solid sedium hypochloride

system, thereby eliminating the accident scenario which necessitated having

chlorine monitors. Since the results of this study could eliminate the need

for chlorine monitors, the replacement study was directly impacted and

subsequently placed on hold.

f'~'s By late 1987, the sodium hypochloride proposal had been rejected and the

( monitor replacement study had been reinitiated. Monitors with a 2/2 logic

'-- configuration manufactured by Anacon were chosen to replace the MDA

monitors.

In the meantime, a representative of the WCGS Supplier Quality organization

visited MDA and an HDA representative in turn came to Wolf Creek and

inspected the existing chlorine monitors. The MDA representative made

several recommendations which have been carried out as an interim measure

until new monitors can be installed.

Unfortunately, the very week that Anacon was being recommended, they went

out of business (May 2, 1988). As a result, Sensidyne chlorine monitors

were selected pending investigation on their suitability. This selection

was based partially on conversations other utilities. In conjunction with

the Sensidyne investigation, WCNOC also began the task of looking at other

available monitors. This review identified Delta as another possible

supplier.

WCNOC decided that due to the importance of resolving the chlorine monitor

issue, monitors from both Delta and Sensidyne would be purchased and

processed through a program which included seismic and environmental

qualifications.

/m s

v

- - _ _ _ - _ - _ _ _ - _ _ _ _ _

- - _ - _ _ - - - - _

.

. .

.

'

  • *

..

Attachment II to WM 88-0312 1

Page 4 of 6

.I

On October 10, 1988, NPE issued PMR 2068 to replace the existing MDA 1

monitors with qualified monitors. WCNOC is implementing PMR 2068 during the l

current refueling outage.  !

While WCNOC agrees that resolution of the chlorine monitor malfunction took

longer than desired. WCNOC feels that resolution of the chlorine monitor

issue was pursued with perseverance and in a manner which reflected sound

engineering and management judgement. It became increasingly apparent to

Wolf Creek during 1985 as a result of 15 LERs associated with CRVIS that the

chlorine monitor issue required not only the attention of plant operating

groups but also that of plant support groups and management.

Wolf Creek pursued resolution of the chlorine monitor issue in a logical

sequence, first working with MDA, manufacturer of the monitors, to determine

the root cause of the monitor malfunctions and a resolution, and second, the

effort undertaken to determine the feasibility of using an alternate method

of chlorination and thereby eliminating the need for chlorine monitors, and

finally, supplementing or replacing the existing chlorine monitoring system

through a program which included seismic and environmental qualification of

needed equipment.

In retrospect, while this approach may have been somewhat time consuming, it

does represent what Wolf Creek feels was the best approach based on

['~' available data, suitable equipment capable of meeting the stringent

environmental and seismic qualification requirements. The inability of MDA

(_

to provide a satisfactory resolution and CRVIS related LERs is being

experienced by the industry on whole.

A primary strength identified during the investigation of this issue was the

fact that the plant staff, engineering, and management worked together to

resolve this issue. No single Wolf Creek organization or group acted

independently, but each performed independent functions to support one

another. Function group meetings were held as a part of the decision

process and key decisions were made based on input from the responsible

groups.

Example:

4. The licensee had not taken actions to correct multiple fire protection

system failures that resulted from the apparent misapplication of valve

microswitches.

Response:

Wolf Creek has experienced a high instance of alarms activating as a result

of the malfunction of a specific type of microswitch used in the 11re

protection system. These micropwitches are installed on various outdoor

valves that are located above and below grade level. FER 87-FP-06 was

[ 'h issued on May 8, 1987, which stated that the present microswitches, Type

( ,/ PIVS-B, are routinely found corroded and appear being used in applications

,

for which they were not designed.

-- _ _ - _ _ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

_ - - _ _

. .

Page 5 of 6

\ )

%/

Nuclear Plant Engineering (NPE) reviewed vendor catalog information but was

unable to find an Underwriters Laboratory (UL) listed and Factory Mutual

(FM) approved replacement limit switch. The vender, Fotter Electric Signal

Company, was contacted to find out if there was a replacement switch for the

UL listed and FM approved PIVS-B limit switch presently in use. The vendor

indicated that the only waterproof supervisory switch they carried was a

" Plug Magnetic Switch" which can be used on a valve with a hand wheel;

however, this switch would not work on the valves installed at WCGS.

Another vendor, Federal Signal, was contacted to see if they offered a

waterproof limit switch. However, they also used Potter for limit switch

applications. They indicated that they had some success in delaying

moisture problems by treating the switches with a coating.

Maintenance and NPE representatives met to resolve the limit switch

problem. The mutually agreeable solution was to seal the switch openings

with a clear flexible silicon sealer which is commonly available, such as

G.E. clear silicon sealer. The purpose of the sealer is to prevent moisture

from reaching the microswitch inside the limit switch housing. This in turn

would prevent false alarm indication.

The prioritization for responding to EER's is based on the following

categories: mandatory, life / safety, ALARA, or discretionary. This EER was

designated as discretionary during meetings between NPE and Maintenance

y personnel. Based upon the discretionary prioritization, the evaluation and

( i subsequent disposition was not completed until July 29, 1988. As a result

'x _- of the EER disposition, Plant Modification Request (PMR) 2650 will be issued

by December 30, 1988 to identify the locations on the limit switch where the

clear silicon sealer should be applied and to indirste which switches should

be repaired. The information provided in PMR 2659 will allow for the

sealing of existing switches as well as th'e sealing of new switches to

eliminate moisture within the switch housing.

Example:

5. The licensee has not aggressively pursued the cause and taken action to

resolve m'lfunctions

a in the emergency diesel engine's jacket water

pressure sensing system that began in 1986.

Response:

The malfunctions in question deal with problems with the proper functioning

of the pressure transmitters due to pulsations in process pressure. As a

result of Engineering Evaluation Request (EER) 87-KJ-01 which described the

pulsation problem, Plant Modification Request (PMR) 2183 was issued on

6/9/87 to install snubbers in the process sensing lines to reduce pressure

transmitter pulsations due to pulsations in the process pressure. WCNOC has

determined that the cause of the pulsations is integral to system design and

equipment characteristics. Pulsations to some extent are a natural

phenomenon associated with pumps in general. The magnitude to which

(y- g) pulsations occur is dependent on the pump (size and type), its use, and the

's ' configuration of overall system associated with the pump.

- - _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ - . _ _ _ _

.,

6

'

~

. *

'

Page 6 of 6

\

(

'v

The required parts were then ordered and the PMR was scheduled for

installation during the current refueling outage. However, all the parts

could not be shipped in time for installation during the outage. It was

determined that the pressure transmitter pulsation problems did not affect

the ability of the EDG to fulfill its safety function, therefore PHR 2183

will be implemented after'the parts arrive and at the next available EDG

outage of sufficient duration to accomplish the process line snubber j

installation, but in any case no later than the end of the next refueling j

cutage. l

-