September 22, 1999 Mr. Otto L. Maynard President and Chief Executive Officer-1 Wolf Creek Nuclear Operating Corporation,

Post Office Box 411 Burlington, KA 66839 i

SUBJECT:

WITHDRAWAL OF AMENDMENT REQUEST REGARDING THE ULTIMATE HEAT SINK TEMPERATURE FOR WOLF CREEK GENERATING STATION (TAC NO MA4601)

Dear Mr. Maynard:

The Commission issued Amendment No.125 to the Wolf Creek Generating Station (WCGS) in its letter dated July 8,1999.- The amendment consisted of changes to Technical Specification (TS) 3.7.5 regarding the maximum allowed value of the ultimate heat sink temperature in response to your application dated January 12,1999, as supplemented by letters dated May 11 and June 30,1999. The' amendment is effective only through September 30,1999.

In the letter of June 30,1999, you proposed a maximum plant inlet water temperature of 95*F; however, the amendment only approved a maximum value of 94*F to allow the amendment to be within the scope of the no significant hazards considerations published in the Federal Register on February 24,1999 (64 FR 9203) and to be issued before the hot weather period of July and August 1999 in and around WCGS.

In the conference call of September 8,1999, your staff withdrew the request to raise the maximum plant inlet temperature from 94*F to 95*F because the hot weather period of 1999 has passed and the amendment will expire within about 3 weeks. The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with I

the Office of the Federal Register for publication.

ack N. Donohew, Project Manager, Section 2 roject Directorate IV and Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-482 DlSTRIBUTION:

Docket ii Enclosure; Notice PUBLIC i

PDIV-2 Reading

/Q

cc w/ encl: See next page SRichards h

OGC

  • For previous concurrences ACRS see attached ORC '

BJohnson, Region IV$;f)W. ]M p[* hh J

A' To receive a copy or Inis cocument, Indicate v in tne Dox 4

OFFICE PDl%2/Ph C PDIV-2/LA C PDIV-2/SC*

Jh EPhy^tdI NAME SDembek DATEL 9 / E/99 9 /5P199 9/20 /99

. DOCUMENT NAME: G:\\PDIV-2\\WolfCreek%MD-MA4601 withdrawal.wpd OFFICIAL RECORD COPY 9909270161 990922 PDR ADOCK 05000482 P

FDR L

Mr. Otto L. Maynard President and Chief Executive Officer l

Wolf Creek Nuclear Operating Corporation Post Office Box 411 Burlington, KA 66839

SUBJECT:

ISSUANCE OF AMENDMENT 125 REGARDING THE ULTIMATE NEAT SINK TEMPERATURE FOR WOLF CREEK GENERATING STATION'(TAC NO.

MA4601)

,/

/

Dear Mr. Maynard:

The Commission issued Amendment No.125 to the Wolf Creek Generating Station (WCGS) in its letter dated July 8,1999. The amendment consisted of changes to Technical Specification (TS) 3.7.5 regarding the maximum allowed value of the.uftimate heat sink temperature in response to your application dated January 12,1999, as supplemented by letters dated May 11 and June 30,1999. The amendment is effective only through September 30,1999.

In the letter of June 30,1999, you proposed a pa/

ximum plant inlet water temperature of 95'F; however, the amendment only approved a makimum value of 94*F to allow the amendment to be within the scope of the no significant hapfrds considerations published in the Federal Register on February 24,1999 (64 FR 9203) and to be issued before the hot weather period of July and August 1999 in and around WCGS.

In the conference call of September 8,1999, your staff withdrew the request to raise the

/

maximum plant inlet temperatureJ om 94'F to 95'F because the hot weather period of 1999 has past and the amendment will expire within about 3 weeks. The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.

/

Sincerely,

/

/

Jack N. Donohew, Project Manager, Section 2

/

Project Directorate IV and Decommissioning Division of Licensing Project Management

/

Office of Nuclear Reactor Regulation Docket No. 5 82 DISTRIBUTION:

Docket

Enclosure:

otice PUBLIC PDIV-2 Reading cc w/e See next page SRichards OGC ACRS BJohnson, Region IV To receive a copy of this document, indicate "G" in the box OFFICE PDIV-2/K C PDIV-2/LA C PDIV-2/SC NAME JDo M EP'ehhn SDembeM DATE 9 / 2 0/99 9 / \\$ /99 9 /.2o [99 DOCUMENT NAME: G:\\PDIV-2\\WolfC reek \\AM D-MA4601 wit hdrawal.wpd OFFICIAL RECORD COPY

  • %g g%

4 UNITED STATES NUCLEAR REGULATORY COMMISSION f

WASHINGTON, D.C. 20666-0001

%****+/

September 22, 1999 Mr. Otto L. Maynard President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation Post Office Box 411 Burlington, KA 66839

SUBJECT:

WITHDRAWAL OF AMENDMENT REQUEST REGARDING THE ULTIMATE HEAT SINK TEMPERATURE FOR WOLF CREEK GENERATING STATION (TAC NO. MA4601)

Dear Mr. Maynard:

The Commission issued Amendment No.125 to the Wolf Creek Generating Station (WCGS) in its letter dated July 8,1999. The amendment consisted of changes to Technical Specification (TS) 3.7.5 regarding the maximum allowed value of the ultimate heat sink temperature in response to your application dated January 12,1999, as supplemented by letters dated May 11 and June 30,1999. The amendment is effective only through September 30,1999.

In the letter of June 30,1999, you proposed a maximum plant inlet water temperature of 95'F; however, the amendment only approved a maximum value of 94*F to allow the amendment to be within the scope of the no significant hazards considerations published in the Federal Register on February 24,1999 (64 FR 9203) and to be issued before the hot weather period of July and Angust 1999 in and around WCGS.

In the conference call of September 8,1999, your staff withdrew the request to raise the maximum plant inlet temperature from 94*F to 95'F because the hot weather period of 1999 has passed and the amendment will expire within about 3 weeks. The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.

Sincerely, U

M

,, ack onohew, Project Manager, Section 2 roject Directorate IV and Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-482

Enclosure:

Notice cc w/enci: See next page l

FI ','

ii.

i Wolf Creek Generating Station cc:

Jay Silberg, Esq.

Vice President & Chief Operating Officer Shaw, Pittman, Potts & Trowbridge Wolf Creek Nuclear Operating Corporation l

2300 N Street, NW P. O. Box 411 Washington, D.C. 20037 Burlington, Kansas 66839 l

Regional Administrator, Region IV Superintendent Licensing U.S. Nuclear Regulatory Commission Wolf Creek Nuclear Operating Corporation 611 Ryan Plaza Drive, Suite 1000 P.O. Box 411 l

Arlington, Texas 76011 Burlington, Kansas 66839 l

Senior Resident inspector U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident inspectors Office l

P. O. Box 311 8201 NRC Road Burlington, Kansas 66839 Steedman, Missouri 65077-1032 l.

Chief Engineer Utilities Division Kansas Corporation Commission 1500 SW Arrowhead Road Topeka, Kansas 66604-4027 f

Office of the Governor State of Kansas Topeka, Kansas 66612 Attorney General Judicial Center 301 S.W.10th 2nd Floor Topeka, Kansas 66612 County Clerk Coffey County Courthouse Burlington, Kansas 66839 I

Vick L. Cooper, Chief Radiation Control Program Kansas Department of Health and Environment Bureau of Air and Radiation Forbes Field Building 283 Topeka, Kansas 66620