Corrected Summary Page & Page 1 to IE Insp Rept 50-261/82-04 on 820111-0210
ML20052C165
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 03/12/1982
From: Burger C, Weise S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20052C159 List:
References
50-261-82-04, 50-261-82-4, NUDOCS 8205040448
Download: ML20052C165 (2)


See also: IR 05000261/1982004

Text

'o,,

UNITED STATES

8

NUCLEAR REGULATORY COMMISSION

o

g

a

REGION 11

o,

8

101 MARIETTA ST., N.W., SUITE 3100

ATLANTA, GEORGIA 30303

Report No. 50-261/82-04

Licensee: Carolina Power & Light Company

411 Fayetteville Street

Raleigh, NC 27602

Facility Name:

H. B. Robinson

Docket No. 50-261

License No. DPR-23

Inspection at II. B. Robinson site near Raleigh, North Carolina

b

hv

2N1 M

Inspector:

%

S. Weise "

Date Signed

'

Approved by:

Chb

d&

3./M M L

7

C. Burger 6 Section ChieM Division of Project

Date Signed

and Resident Programs

SUMiiARY

Inspection on January 11 - February 10, 1982

Areas Inspected

This routine, announced inspection involved 130 resident inspector-hours on site

in the areas of technical specification compliance, plant tour, operations

performance, reportable occurrences, housekeeping, site security, surveillance

activities, maintenance activities, quality assurance practices, radiation

control activities, outstanding items review, IE Bulletin, and Notice followup,

emergency preparedness, and Till Action Item review.

Resul ts

Of the 14 areas inspected, no violations or deviations were identified in 12

areas; three violations were found in two areas (Failure to implement administra-

tive policies, paragraph 8.d; inadequate annunicator procedure, paragraph 8.c;

and failure to implement administrative policies, paragraph 7.b.).

8205040448 820422

PDR ADOCK 05000261

O

PDR

'

g

..

,

.

'.

.

DETAILS

1.

Persons Contacted

Licensee Employees

q

,

  • R. B. Starkey, Plant General Manager
  • J. Curley, Manager Technical Support
  • F. Gilman, Senior Specialist, Regulatory Compliance
  • F. Lowery, Unit 2 Operations Supervisor

R. Chambers, Unit 2 Maintenance Supervisor

  • C. Wright, Specialist, Regulatory Compliance

W. Flanagan, Project Engineer

>

'

D. Gainey, Senior Specialist, Emergency Planning

R. Black, Corporate Emergency Planning Director

Other licensee employees contacted included technicians, operators,

mechanics, security force members, and office personnel.

Other Organizations

D. Payne, Westinghouse

,

i

  • Attended exit interview

2.

Exit Interview

'

The inspection scope and findings were summarized on February 10, 1982, with

-l

those persons indicated in paragraph 1 above.

The licensee acknowledged the

inspector's findings and violations.

l

3.

Licensee Action on Previous' Inspection Findings

.

e

Not Inspected.

!'

4.

Unresolved Items

!

Unresolved items were not identified during this inspection.

-