IR 05000261/2024003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000261/2024003
ML24303A343
Person / Time
Site: Robinson 
Issue date: 10/30/2024
From: Matthew Fannon
NRC/RGN-II/DORS/PB2
To: Basta L
Duke Energy Progress
References
IR 2024003
Download: ML24303A343 (1)


Text

SUBJECT:

H.B. ROBINSON STEAM ELECTRIC PLANT - INTEGRATED INSPECTION REPORT 05000261/2024003

Dear Laura Basta:

On September 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at H.B. Robinson Steam Electric Plant. On October 17, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Matthew S. Fannon, Chief Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000261 License No. DPR-23

Enclosure:

As stated

Inspection Report

Docket Number:

05000261

License Number:

DPR-23

Report Number:

05000261/2024003

Enterprise Identifier:

I-2024-003-0026

Licensee:

Duke Energy Progress, LLC

Facility:

H.B. Robinson Steam Electric Plant

Location:

Hartsville, SC

Inspection Dates:

July 01, 2024 to September 30, 2024

Inspectors:

V. Gaffney, Resident Inspector

J. Zeiler, Senior Resident Inspector

Approved By:

Matthew S. Fannon, Chief

Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at H.B. Robinson Steam Electric Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 2 operated at or near rated thermal power (RTP) for the entire duration of the period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (3 Samples)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather for Tropical Storm Debby on August 5-8, 2024.
(2) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather for tropical cyclone #8 on September 16, 2024.
(3) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather for Tropical Storm Helene on September 26-27, 2024.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)

'B' motor driven auxiliary feedwater (MDAFW) pump and steam driven auxiliary feedwater (SDAFW) pump while 'A' MDAFW pump was out of service for preventive maintenance on July 30, 2024 (2)

'B' spent fuel pool cooling (SFPC) pump while 'A' SFPC pump was out of service due to emergent loss of oil from the pump drive on August 4, 2024 (3)

'A' and 'B' chemical and volume control system (CVCS) charging pumps while the 'C' CVCS charging pump was out of service for emergent failure to start on August 20, 2024 (4)

'A' MDAFW pump and 'C' diesel driven AFW pump while the SDAFW pump was out of service for preventive maintenance on September 3, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)spent fuel pool storage area on fuel handling building elevation 275 (fire zone 28A) on July 21, 2024 (2)

'A' and 'B' vital battery room (fire zone 16) on July 25, 2024

(3) SDAFW pump area on turbine building elevation 226 (fire zone 25B) on July 30, 2024 (4)

'A' emergency diesel generator (EDG) room (fire zone 2) on August 7, 2024 (5)control room heating, ventilation, and air conditioning equipment room (fire zone 17)on September 12, 2024

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on September 12, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (2 Samples)

(1) The inspectors evaluated external flooding mitigation protections in manhole cable vaults M-50A and M-50B for the service water pump motors on July 8, 2024.
(2) The inspectors evaluated external flooding mitigation protections associated with the Lake Robinson Dam spillway (Tainter) gates and post-modification testing of the 'B' Tainter gate and hoist system following replacement on August 21, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during a planned reactor down power to 98.5% RTP and restoration to full power to conduct 'A' MDAFW pump testing on July 30, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator requalification simulator training scenario on July 24, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)

'A' CVCS charging pump failure due to faulted motor on June 13, 2024 [nuclear condition report (NCR) 2519275]

(2)

'A' SFPC pump motor breaker found tripped on electrical overload fault on July 18, 2024 (NCR 2522791)

Aging Management (IP Section 03.03) (1 Sample)

The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:

(1)degraded wall penetration insulation due to fire/heat in 'A' EDG exhaust piping (NCR

===2520936)

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01)===

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated risk (Green) during planned corrective maintenance to replace suspected broken pump valve spring on the 'A' CVCS charging pump on July 9-10, 2024 (2)elevated risk (Green) during planned preventive maintenance on 'A' MDAFW pump and valves on July 30, 2024 (3)elevated risk (Green) during emergent troubleshooting to repair the 'C' CVCS charging pump due to failure to start on August 20, 2024 (4)elevated risk (Green) during planned pump and valve preventive maintenance on the SDAFW pump on September 3, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) NCR 2518201, 'A' reactor coolant pump excessive #3 seal leak-by causing frequent standpipe low level alarms beginning mid-June, 2024
(2) NCR 2522219, 'A' EDG electrical metal junction box containing governor control wiring contacting bare engine exhaust manifold, review completed July 22, 2024
(3) NCR 2524500, 'A' SFPC pump significant decrease in oil level identified following pump rebuild maintenance on August 4, 2024
(4) NCR 2527908, minor reactor coolant system pressure control perturbations exhibited on September 6, 2024
(5) NCR 2529132, 'B' EDG governor speed setting found changed from 13.60 to 13.36 on September 21, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)engineering change (EC) 420743, replace 'B' instrument air compressor dryer

(2) EC 415523, Lake Robinson spillway Tainter gate and hoist replacement (specific to

'B' Tainter gate)

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1) OST-201-1, MDAFW System Component Test - Train A, following preventive maintenance on 'A' MDAFW pump on July 30, 2024
(2) Work Order (WO) 20651495 instructions for blowing down instrument sensing lines for 'A' train service water supply header pressure on July 31, 2024
(3) OST-402, Auxiliary Feedwater System, Section 6.1.3, Testing C AFW Train, following preventive maintenance on the 'C' diesel driven AFW pump on August 20, 2024
(4) OST-101.3, CVCS Component Test Charging Pump 'C', following corrective maintenance to restore oil prime in pump gyrol fluid drive unit on August 20, 2024
(5) OST-551-2, Turbine Trip Functional Test, following corrective maintenance to disassemble and clean turbine trip Quadvoter solenoid operated valve EV-4459D on August 26, 2024
(6) OP-306, Component Cooling Water System, Section 6.2.1, Operating CCW Pumps, following lubrication preventive maintenance on the 'A' CCW pump on September 16, 2024
(7) OP-903, Service Water System, Section 6.2.1 for swapping operating service water booster pump (SWBP) from 'B' pump to 'A' pump following 'A' SWBP lubrication preventive maintenance on September 25, 2024

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) OST-409-1, EDG A Fast Speed Start, on August 1, 2024
(2) OST-202, Steam Driven Auxiliary Feedwater System Component Test, on September 3, 2024

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) OST-207, Comprehensive Flow Test for the MDAFW Pumps, on July 30, 2024

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) A simulator-based licensed operator training scenario on July 24,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 2 (July 1, 2023, through June 30, 2024)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)

(1) Unit 2 (July 1, 2023, through June 30, 2024)

MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)

(1) Unit 2 (July 1, 2023, through June 30, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)fire in the wall penetration insulation surrounding the 'A' EDG exhaust piping (NCR 2520936)

(2) Robinson site clearance and tagging adverse trend identified (NCR 2522397)

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 17, 2024, the inspectors presented the integrated inspection results to Laura Basta and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AD-OP-ALL-0120

Severe Weather Preparations and Considerations

Rev. 0

AD-OP-RNP-

20

Severe Weather Response

Rev. 0

71111.01

Procedures

OP-218

Lake Robinson Spillway Equipment

Rev. 23

OP-301

Chemical and Volume Control Systems Operation and

Alignments

Rev. 128

OP-402

Auxiliary Feedwater System

Rev. 17

71111.04

Procedures

OP-910

Spent Fuel Pit Cooling and Purification System

Rev. 52

CSD-RNP-PFP-

AB2-0226-01

Auxiliary Building Elevation 226 Pre-Fire Plan

Rev. 3

CSD-RNP-PFP-

AB2-0246-001

Auxiliary Building Elevation 246 Pre-Fire Plan

Rev. 1

CSD-RNP-PFP-

FB2-0226-001

Fuel Handling Building Elevation 226 Pre-Fire Plan

Rev. 0

Fire Plans

CSD-RNP-PFP-

TB2-0226-001

Turbine Building Elevation 226 Pre-Fire Plan

Rev. 2

AD-FP-ALL-1520

Transient Combustible Control

Rev. 2

AD-FP-ALL-1551

Fire Protection Impairments

Rev. 2

AD-OP-ALL-0207

Fire Brigade Administrative Controls

Rev. 6

AD-TQ-ALL-0086

Fire Brigade and Hazmat Training

Rev. 6

AOP-041

Response to Fire Event

Rev. 17

CSD-RNP-PFP-

SOGS-001

Fire Brigade Standard Operating Guidance

Rev. 1

FP-012

Fire Protection Systems Minimum Equipment and

Compensatory Actions

Rev. 39

OMM-002

Fire Protection Manual

Rev. 58

71111.05

Procedures

OP-906

Heating, Ventilation, and Air Conditioning

Rev. 100

Engineering

Changes

EC 415523

'B' Tainter Gate Replacement Modification Test Plan

8/21/2024

71111.06

Work Orders

WO 20645894

Inspect M50A and M50B buried cables

7/8/2024

AD-OP-ALL-1000

Conduct of Operations

Rev. 23

71111.11Q

Procedures

AD-TQ-ALL-0420

Conduct of Simulator Training and Evaluation

Rev. 20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-105

Maneuvering the Plant When Greater than 25% Power

Rev. 74

71111.12

Procedures

AD-EG-ALL-1210

Maintenance Rule Program

Rev. 5

AD-WC-ALL-

200

On-Line Work Management

Rev. 22

AD-WC-ALL-

240

On-Line Risk Management Process

Rev. 6

CSD-WC-RNP-

240-00

RNP ERAT Guidance

Rev. 1

71111.13

Procedures

OMM-048

Work Coordination and Risk Assessment

Rev. 71

71111.15

Procedures

AD-OP-ALL-0105

Operability Determinations

Rev. 7

AD-EG-ALL-1110

Design Review Requirements

Rev. 11

AD-EG-ALL-1122

Failure Modes and Effects Analysis and Single Failure

Analysis

Rev. 2

AD-EG-ALL-1132

Preparation and Control of Engineering Changes

Rev. 27

71111.18

Procedures

AD-EG-ALL-1137

Engineering Change Product Selection

Rev. 12

71111.24

Procedures

PLP-033

Post-Maintenance Testing (PMT) Program

Rev. 70

AD-EP-ALL-0101

Emergency Classification

Rev. 5

AD-EP-ALL-0105

Activation and Operation of the Technical Support Center

Rev. 13

AD-EP-ALL-0111

Control Room Activation of the ERO

Rev. 8

AD-EP-ALL-0304

State and County Notifications

Rev. 7

AD-EP-RNP-

0105

RNP Site Specific TSC Support

Rev. 4

71114.06

Procedures

CSD-EP-RNP-

0101-02

EAL Wallchart

Rev. 3

AD-EG-ALL-1217

Mitigating System Performance Index (MSPI)

Rev. 3

71151

Procedures

AD-PI-ALL-0700

Performance Indicators

Rev. 6

AD-PI-ALL-0100

Corrective Action Program

Rev. 30

AD-PI-ALL-0106

Cause Investigation Checklists

Rev. 10

71152A

Procedures

AD-PI-ALL-0200

Performance Trending

Rev. 14