NOTICE OF VIOLATION Carolina Power and Light Company Docket No. 50-261 Robinson Nuclear Plant License No. DPR-23 EA 98-043 During an NRC.inspection conducted on January 5-9. 1998, a violation of NRC requirements was identified. In accordance with the "General Statement of Policy and Procedures for NRC Enforcement Actions," NUREG-1600, the violation is listed below: CFR 50; Appendix B, Criterion XVI requires that measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and correcte UFSAR Section 8.3.1.3 states that control cables are separated into two basic channels as required for redundant circuits. Cables assigned to these channels for separation are required to be.in their respective channels from the beginning of the cable to the final terminatio Contrary to the above, as of May 25, 1997, the licensee failed to correct conditions adverse to quality, in that, the control cables for the safety injection pumps were not separated into two basic channels as required for redundant circuits. Specifically, safety injection pump C autostart cable C2239C and manual cable C2239D were in the same channel (cable tray) as the SI pump A autostart cable C2237D and the SI pump B (train A line up) autostart cable C2891 This is a Severity Level IV violation (Supplement I)

The NRC has concluded that information regarding the reason for the violation, the corrective actions taken and planned to correct the violation and prevent recurrence and the date when full compliance was achieved is already adequately addressed on the docket in Inspection Report No. 50-261/98-0 dated February 6, 1998 and in your March 6. 1998, letter. However, you are required to submit a written statement or explanation pursuant to 10 CFR 2.201 if the description therein does not accurately reflect your corrective actions or your position. In that case, or if you choose to respond, clearly mark your response as a "Reply to a Notice of Violation." and send it to the Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington. with a copy to the Regional Administrator, Region I and a copy to the NRC Resident Inspector at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation (Notice).

Dated at Atlanta, Georgia this 9th day of June 1998 9806180272 980609 Enclosure PDR ADOCK 05000261 G