IR 05000261/2022010
ML22269A334 | |
Person / Time | |
---|---|
Site: | Robinson |
Issue date: | 09/26/2022 |
From: | James Baptist NRC/RGN-II |
To: | Flippin N Duke Energy Progress |
References | |
IR 2022010 | |
Download: ML22269A334 (13) | |
Text
SUBJECT:
H.B. ROBINSON STEAM ELECTRIC PLANT - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000261/2022010
Dear Ms. Flippin:
On August 12, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at H.B. Robinson Steam Electric Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket No. 05000261 License No. DPR-23
Enclosure:
As stated
Inspection Report
Docket Number: 05000261
License Number: DPR-23
Report Number: 05000261/2022010
Enterprise Identifier: I-2022-010-0049
Licensee: Duke Energy Progress, LLC
Facility: H.B. Robinson Steam Electric Plant
Location: Hartsville, SC
Inspection Dates: July 25, 2022 to August 12, 2022
Inspectors: P. Braxton, Reactor Inspector T. Fanelli, Senior Reactor Inspector R. Fanner, Reactor Inspector C. Franklin, Reactor Inspector W. Sherbin, Contractor T. Su, Reactor Inspector
Approved By: James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at H.B.
Robinson Steam Electric Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Teams)
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (6 Samples)
- (1) Boron Injection Valves SI-870A & SI-870B Design bases documents, system descriptions, and training documents Primary design calculations Normal, Abnormal, and Emergency Operating Procedures Surveillance Test Procedures and Recent Results Material Condition of Valves and Associated Equipment Vendor Instruction Manuals Corrective Action History and System Health Reports Condition reports associated with component Local Leak Rate Test Procedure and Recent Results
- (2) 480V-E1, 480V-E2, MCC-9 Compliance with UFSAR, TS and TS Bases Material Condition and Configuration Design Requirements Environmental Conditions Maintenance and Surveillance Test reviews Protective relay setting and calibration
- (3) 125 VDC (Distribution Panel D-3) (Batteries or Inverters or Chargers)verified adequacy of battery capacity Verified short circuit calculations and protection capacity Verified voltage drop calculations
- (4) Unit Service Water (SW) System, Including SW Pumps, Ultimate Heat Sink (UHS),and Deep Well Pump For SW Pumps:
Normal and Emergency Operating Procedures Surveillance Test Procedures and Recent Results Inservice Test Procedures and Recent Results Basis for Pump Test Acceptance Criteria, Including Instrument Uncertainty System Hydraulic Calculations Indicating Required SW Flow Criteria to Safety Related Heat Exchangers are Met Material Condition of Pumps and Associated Equipment Corrective Action History
For UHS (Lake Robinson):
Calculation for Determining the Volume of Water Available to the SW Pumps for the Licensing Basis Time Requirement (22 Days)
Technical Specification for Lake Level Requirement to Ensure SW Pumps Suction Bell Submergence is Sufficient to Prevent Votexing Discussions With Staff to Ensure Water Quality is Maintained
For Deep Well Pump:
Procedure Used to Align Deep Well Pump in the Event That Lake Robinson Water Level is Lost Pump Surveillance Test Procedures and Recent Results
- (5) Steam Driven Auxiliary Feedwater Pump Normal and Emergency Operating Procedures Surveillance Test Procedures and Recent Results Inservice Test Procedures and Recent Results Basis for Pump Test Acceptance Criteria, Including Instrument Uncertainty CST Level Instrumentation Setpoints Which Actuate Alarms to Notify Operators to Transfer AFW Suction Source from CST to Service Water Vortex Calculation for Pump Suction from CST Seismic Qualification of preferred AFW pump suction water source (CST)
Material Condition of Pump and Associated Equipment Modification Performed to Install CST Bladder Corrective Action History
- (6) Emergency Diesel Generator (EDG) Room Ventilation System Normal and Emergency Operating Procedures Surveillance Test Procedures and Recent Results EDG Room Heat Load Calculation Which Determines Ventilation Air Flow Ventilation Supply and Exhaust Fan Specifications Surveillance Test Procedures and Recent Results Which Verify Fan Operation During EDG Operation
Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===
- (1) Service Water Booster Pump A Compliance with the Update Final Safety Analysis Report and the Technical Specifications Primary design calculations Normal, Abnormal, and Emergency Operating Procedures Material condition and configuration Surveillance test procedures and recent results System health report Normal and emergency operating procedures
Modification Review - Permanent Mods (IP Section 02.03) (4 Samples)
- (2) EC 0000402563 002, Provide Selective Coordination of 125VDC Power Supplies to Support NFPA 805 LAR
- (4) EC 417357/417864, EDG Day Tank Level Switches Design Change
Review of Operating Experience Issues (IP Section 02.06) (3 Samples)
- (1) Information Notice 2021-01 Lessons Learned from NRC Inspections of Design-Basis Capability of Power-Operated Valves at Nuclear Power Plants
- (2) Part 21 2019-11-00, 2021-07-00 and 01, AMETEK Solid state Controls Notification of Potential Defect
- (3) Information Notice 2016-09, Recent Issues Identified When Using Reverse Engineering Techniques in the Procurement of Safety-Related Components
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On August 12, 2022, the inspectors presented the design basis assurance inspection (teams) inspection results to Nicole Flippin and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71111.21M Calculations16-025 NFPA 805 RNP Coordination Study Rev.1
212-C-020 A-46 Relays Requiring System Consequence Review Rev. 0
213-C-066 Atmosphere Storage Tanks-CST Rev. 0
84065-M-06-F New Basis for CST Level Indication for CST Repair and Rev. 0
Restoration - HBR Unit 2
HBR2-11260 Zone Map for Environment Parameters Rev. 5
SH00004 Reactor Aux Bldg. EL. 242`-6" and 246`-0"
RNP-C/FLEX-0052 Seismic Fragility Analysis of the CST Rev. 1
RNP-E-2.009 Overcurrent Protection Emergency Bus E1 and E2 Rev. 3
Emergency Supply
RNP-E-2.010 Overcurrent Protection Emergency Bus E1 and E2-Normal Rev. 3
Supply
RNP-E-5.031 Cable Sizing for Battery Charger A-1 Rev. 0
RNP-E-6.004 Short Circuit Calculation Rev. 9
RNP-E-6.005 Overcurrent Protection and Coordination of the 125 VDC Rev. 4
Distribution System (Trains A and B)
RNP-E-8.002 AC Auxiliary Electrical Distribution System Voltage/Load Rev.10
Flow/Fault Current Study
RNP-I/INST-1015 CST Level Uncertainty Rev. 8
RNP-M/HVAC-A & B EDG Room Steady State Temperature Rev. 1
1064
RNP-M/MECH-Minimum SDAFW Pump Suction Pressure vs. CST Level Rev. 0
1461
RNP-M/MECH-Set Up Calculation for MOV SI-870A Rev. 14
24
RNP-M/MECH-Set Up Calculation for MOV SI-870B Rev. 14
29
RNP-M/MECH-Service Water System Operation with One Pump Rev. 0
1519
RNP-M/MECH-Availability of Lake Robinson to Provide Ultimate Heat Sink Rev. 13
1645 Cooling
RNP-M/MECH-Service Water System Hydraulic Evaluation Rev. 4
Inspection Type Designation Description or Title Revision or
Procedure Date
1653
RNP-M/MECH-AFW ProtoFlow Model Rev. 2
1655
RNP-M/MECH-Deep Well Pump D Thermal Hydraulic Analyses Rev. 4
1769
RNP-M/MECH-Safety Related Pump Minimum Performance Requirements Rev. 12
1802
RNP-M/MECH-EPRI PPM Analysis For SI-869 SI-870A/B Rev. 1
1905
RNP_E-6.020 Load Profile and Battery Sizing Calculation for Battery BRev. 9
Corrective Action AR 02268696 AMETECK Solidstate Controls Inc. (Part 21) - Vendor 04/23/2019
Documents Notification #53993, Part 21 Report - Overheating And
Failure Of Transformers
AR 02391622 Unresolved Items on Battery Chargers 10/26/2021
2340607,
2342647,
2346091,
2401058,
2410961
Corrective Action CAP 02436847 2022 DBAI: Errors in RNP-E/ELEC-1220 and RNP-E-5.031 08/04/2022
Documents CR 02437413 2022 DBAI: Error in Single Line Depiction for Calculation 08/09/2022
Resulting from RNP-E-6.005, R4
Inspection
Drawings 5379-01082 SH 1 - Safety Injection System Flow Diagram Rev. 50
5379-05374 480V One Line Diagram Rev. 32
5379-2762 Diagrams - AUX. Feedwater Pump Start-Up Rev. 15
2-M-2005 CST Details, Bladder Rev. C
G-190197 Feedwater, Condensate, and Air Evacuation System Rev. 75
G-190199 Service and Cooling Water System Rev. 87
G-190199 SH7 Service And Cooling Water System Flow Diagram Rev. 41
G-1902040 Fuel Oil System Rev. 1
G-190304 HVAC-Turbine, Fuel, Aux., Reactor, & Radwaste BuildingsRev. 66
Inspection Type Designation Description or Title Revision or
Procedure Date
G-190626 125 V DC & Vital AC One Line Diagram Rev. 27
G-190626, Sheet 3 125V DC & 120V AC One Line Diagram Rev. 25
HBR2-11260 Zone Map for Environmental Parameters, Reactor Aux Rev. 5
Bldg EL 242'6" and 246'-0", Sheet 4
Engineering EC 277392 Modify SI-869, SI-870A/B to Conform to GL 96-05 and the Rev. 13
Changes JOG
EC 402563 Provide Selective Coordination of 125VDC Power Supplies Rev. 2
EC 417357 Replace EDG Day Tank "B" Level Control Switches Rev. 3
EC 90617 Connect FLEX Diesel to 125 VDC Battery Chargers Rev. 51
ESR # 95-00266 Replace EDG Day Tank "A" Level Control Switches Rev. 1
Mod 680 CST Sealing Bladder 04/08/85
Miscellaneous 727-909-91 Gate and Globe Valve Rev. 11
28-562-71 SMB Valve Controls Rev. 43
28-812-46 Velan Valve Instruction Manual for Manual Valves: Rev. 12
Installation, Operation, and Maintenance
738-523-20 Breakers, 480V, MCC Westinghouse Rev.10
2-209-181 Ametek Solidstate Controls Instruction Technical Manual Rev. 3
300 amp Battery Charger
AR 02377519-01 AMETEK Part 21 Notice for TVA Diodes 04/21/2021
DBD/R87038/SD02 Design Basis Document Safety Injection System Rev. 24
DBD/R87038/SD16 SYS DBD-Electrical Power Distribution System 13
DBD/R87038/SD32 SYS DBD - Auxiliary Feedwater System Rev. 12
LP-027 Feedwater System Rev. 09
ML13252A243 First Six-Month Status Report in Response to March 12, 08/28/2013
2012 Commission Order
Modifying Licenses With Regard to Requirements for
Mitigation Strategies for
Beyond-Design-Basis External Events (Order Number EA-
2-049)
ML14063A238 Second Six-Month Status Report in Response to March 12, 02/24/2014
2012 Commission Order
Modifying Licenses With Regard to Requirements for
Mitigation Strategies for
Inspection Type Designation Description or Title Revision or
Procedure Date
Beyond-Design-Basis External Events (Order Number EA-
2-049)
- H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 03/31/2016
SAFETY
EVALUATION REGARDING IMPLEMENTATION OF
MITIGATING
STRATEGIES AND RELIABLE SPENT FUEL
INSTRUMENTATION RELATED
TO ORDERS EA-12-049 AND EA-12-051 (CAC NOS.
MF0720 AND MF0793)
RNP-E-2.019 MCC 5,6,9, and 10 Protective Devices Rev. 14
RNP-F/PSA-0133 Robinson Operator Action Risk Ranking Rev. 000
RNP2-E-0007 Specification for 125 Volt Battery Charger Rev. 1
RNPD/85-907 H. B. Robinson Region II Inspection Report 05/02/1985
SD-016 480/120VAC Electrical Systems Rev. 12
SD-042 Auxiliary Feedwater System Rev. 11
SP-1609 FUKUSHIMA FLEX 4.2 DIESEL GENERATOR 1A AND 1B Rev. 2
SITE ACCEPTANCE TEST
UFSAR Updated Final Safety Analysis Report Rev. 30
Procedures 728-800-16 Worthington Co. Instructions for Installation & Operation of Rev. 7
Centrifugal Pumps
AD-EG-ALL-1011 Engineering Technical Task Rigor: Pre-Job Brief, Risk Rev. 8
Management and Post-Job Critique
AD-EG-ALL-1202 Preventive Maintenance and Surveillance Testing Rev. 11
Administration
AD-OP-ALL-0204 Plant Status Control Rev. 5
AD-PI-ALL-0100 Corrective Action Program Rev. 27
CSD-EG-DEP-AC and DC Overcurrent Protection and Coordination Rev. 0
0106
EDP-001 4160 VAC Buses Rev 11
EDP-002 480 VAC Buses Rev 19
EDP-003 MCC Buses Rev. 97
EDP-006 Lighting Panels Rev. 92
EGR-NGGC-0106 AC and DC Overcurrent Protection and Coordination Rev. 5
Inspection Type Designation Description or Title Revision or
Procedure Date
EOP E-0 Reactor Trip or Safety Injection Rev. 11
EPP-28 Loss of Ultimate Heat Sink Rev. 22
FSG-004 ELAP DC Load Shed/Management Rev. 1
OP-402 Auxiliary Feedwater System Rev. 112
OST-151-1 Safety Injection System Components Test Pump 'A' Rev. 46
OST-151-2 Safety Injection System Components Test Pump B Rev. 42
OST-151-3 Safety Injection System Components Test Pump C Rev. 43
OST-151-4 Comprehensive Flow Test for Safety Injection Pump 'A' Rev. 30
OST-151-5 Comprehensive Flow Test for Safety Injection Pump 'B' Rev. 28
OST-151-6 Comprehensive Flow Test for Safety Injection Pump 'C' Rev. 26
OST-154 Safety Injection System High Head Check Valve Test Rev. 53
OST-160 Pressure Isolation Check Valve Back Leakage Test Rev. 53
OST-303-1 Service Water Booster Pump A Test Rev. 29
OST-453 Fukushima FLEX 4.2 Diesel Generator 1A and 1B Rev. 9
Surveillance Test
PIC-805 Westinghouse Type CV-7 Undervoltage Relays Rev. 19
Work Orders 20106087,
20327494,
20145768-01,
20152000-01,
20182465-01,
21243-01,
20370563-01,
20371486-01,
20410693-01,
20416978-03,
01800271,
2051481101,
204851145,
011180093
WO 20072906 01 Clean/Inspect MCC-6(10C) (SDAFW Pump Aux Oil Pump) 01/30/2018
WO 20321807 01 Megger Motor From MCC-6(10C) (SDAFW Pump Aux Oil 11/12/20
Pump)
11