IR 05000261/2020011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000261/2020011
ML20356A076
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 12/21/2020
From: James Baptist
NRC/RGN-III/DRS/EB1
To: Kapopoulos E
Duke Energy Progress
References
IR 2020011
Download: ML20356A076 (22)


Text

December 21, 2020

SUBJECT:

H. B. ROBINSON STEAM ELECTRIC PLANT - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000261/2020011

Dear Mr. Kapopoulos,

Jr.:

On December 15, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at H. B. Robinson Steam Electric Plant and discussed the results of this inspection with Ms. Nicole Flippin and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety

Docket No. 05000261 License No. DPR-23

Enclosure:

As stated

Inspection Report

Docket Number:

05000261

License Number:

DPR-23

Report Number:

05000261/2020011

Enterprise Identifier: I-2020-011-0019

Licensee:

Duke Energy Progress, LLC

Facility:

H. B. Robinson Steam Electric Plant

Location:

Hartsville, SC

Inspection Dates:

October 05, 2020 to December 15, 2020

Inspectors:

N. Hansing, Mechanical Engineer

G. Ottenberg, Senior Reactor Inspector

M. Schwieg, Reactor Inspector

S. Sandal, Senior Reactor Analyst

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at H. B.

Robinson Steam Electric Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a. Evaluated whether the sampled POVs are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b. Evaluated whether the sampled POVs are capable of performing their design-basis functions.

c. Evaluated whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d. Evaluated maintenance activities including a walkdown of the sampled POVs (if accessible).

(1) AFW-V2-14B, Steam Driven Auxiliary Feedwater Pump Feedwater Discharge to Steam Generator B
(2) MS-V1-8C, Steam Generator C Steam Supply to Steam Driven Auxiliary Feedwater Pump
(3) FCV-1424, Motor Driven Auxiliary Feedwater Pump A Flow Control Valve
(4) CC-749A, Component Cooling from Residual Heat Removal (RHR) Heat Exchanger A
(5) RHR-744B, RHR Return to Cold Legs
(6) CC-739, Excess Letdown Heat Exchanger Outlet
(7) SI-860B, Containment Sump Recirc Suction
(8) SI-862B, RHR Loop RWST Isolation
(9) FCV-478, Feedwater Regulating Valve "A"

INSPECTION RESULTS

Very Low Safety Significance Issue Resolution Process: Potential Passive Single Failure Design Control Issue 71111.21 N.02 This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.

Description:

The H. B. Robinson Unit 2 emergency core cooling system (ECCS) low head safety injection (LHSI) design is such that there are two independent containment sump suction lines provided from the containment sump strainer to the suction of the residual heat removal (RHR) Pumps. The RHR system is a dual-purpose system and can be operated for the LHSI function following an accident, and the RHR pumps would take suction from the containment sump during what is known as the recirculation phase of the accident. Each train of RHR/LHSI is located in a separate RHR pit. The pits are separated by a wall which, if overtopped due to a flood in one RHR pit, could result in the flooding of the adjacent RHR pit as well. Each RHR pit contains flood level instrumentation which is used to alert operators of the need to isolate a single fluid system passive failure in the room, which according to section 6.3.2.5.1 of the current H. B. Robinson Unit 2 Updated Final Safety Analysis Report (UFSAR), is to be assumed to occur during the ECCS recirculation phase without loss of the protective function. The term "passive failure" was defined in UFSAR reference 6.3.2-2, which is mentioned in UFSAR section 6.3.2.5.1. Reference 6.3.2-2 was GID/R87038/0013, Single Failure, which defines passive failure as:

"The structural failure of a static fluid system component which prevents that component from performing its design function. Specifically, a passive failure is defined as a break in a fluid pressure boundary resulting in abnormal leakage not exceeding 50 gpm. Such leak rates are consistent with limited cracks in pipes, sprung flanges, valve packing leaks or pump seal failures and are credited historically for being the basis of the 50 gpm commitment. This definition applies only to the ECCS portion of the SIS and also does not apply to radiological dose calculations."

Per licensee procedure, if a single fluid system passive failure occurs in the RHR pit during the recirculation phase of the accident, actions would be taken to close the innermost containment sump isolation valve, SI-860A or SI-860B, depending on which train experienced the passive failure in an attempt to stop the leakage into the RHR pit and to prevent the other train of LHSI from being affected.

Mod 792, completed in 1984, added a hole to the upstream discs (the disc facing the containment sump) of the SI-860A and B valves to relieve the pressure locking effect in order to ensure the valves will successfully open upon demand. However, installation of the 3/16 hole in the upstream disc potentially violated Robinsons single passive failure design basis. Both the current version of the UFSAR, section 6.3, and the version in place at the time Mod 792 was implemented stated that:

Two independent and redundant recirculation lines are provided. Each line has two motor-operated valves. Both valves are located adjacent to the containment penetration in the RHR pit such that the line outside the containment can be isolated in the event of a passive failure.

If either valve, SI-860A or SI-860B, which are located in the RHR pit experiences an assumed passive failure, such as a packing leak following ECCS suction swap to the containment sump, closing the valve would no longer isolate the line outside containment and leakage from the containment sump would continue into the RHR pit. This is because the 3/16 hole would now result in unisolable drainage of the containment sump into the RHR pit via the hole and the passive failure location. The licensee estimated this could result in leakage rates of approximately 2.4 to 3.9 gpm, if a large passive failure of the type described in GID/R87038/0013, Single Failure, was required to be applied. This amount of leakage would require beyond design basis operator intervention to ensure the other train of ECCS remains operable due to the potential for sump vortexing due to loss of water level in the containment sump, loss of available RHR pump net positive suction head due to loss of water level in the containment sump, and/or flooding of the RHR pit. Additionally, if the leakage could not be isolated, it would exceed the amount of radioactivity released assumed in control room operator and public dose assessments. It is assumed that if the passive failure occurs anywhere downstream of the innermost containment sump isolation valve, closure of the valve would be successful at isolating the leakage due to the passive failure such that this concern is limited to the assumption of a passive failure at the innermost containment sump isolation valve itself.

Without further substantial research, the inspectors are unable to determine if a single fluid system passive failure, such as packing failure in excess of the flow expected through a 3/16" orifice, applied at either the SI-860A or B valve after transition to ECCS recirculation phase following an accident was within the current licensing basis of the facility. This is due mainly to uncertainty regarding the intent of a September 17, 1969, Atomic Energy Commission (AEC) request for information (RFI) [ADAMS ML20058C568] regarding the passive failure design of these valves. Testing and inspection requirements were subsequently incorporated into the original technical specifications (TS) section 4.4.5, Post Accident Recirculation Heat Removal System [ADAMS ML20058C527], evidently as a result of the applicant's RFI response. Additional confusion was encountered regarding the licensees definition of the passive failure in the current UFSAR section 6.3.2.5.1, and the following statement in that section of the UFSAR: This definition applies only to the ECCS portion of the SIS and also does not apply to radiological dose calculations. The inspector noted that the leakage limit of 2 gallons per hour in section 4.4.5 of the original TS corresponded to the assumptions used in the station's radiological dose calculations. An understanding of the required application of the single passive failure criterion specific to these valves is needed to determine if the hole drilled into the discs of the SI-860A/B valves in 1984 was a violation of the design control requirements in Title 10 of the Code of Federal Regulations Part 50 (10 CFR 50), Appendix B.

The inspectors were also concerned that the licensee did not consider the existence of the holes in the valves discs, introduced by Mod 792, when they responded to a March 17, 1989, 10 CFR 50.54(f) demand for information [ADAMS ML14188A655] regarding the H. B.

Robinson Unit 2 facility compliance with the single worst failure requirement of 10 CFR 50.46 and Appendix K on May 7, 1991 [ADAMS ML14174B064]. In their evaluation of the failure modes and effects of a passive failure of the valves resulting in 50 gallons per minute of external leakage, documented in 716M-P-100, RNP ECCS Single Failure Analysis, Revision 12, the licensee incorrectly concluded that the leakage during ECCS recirculation phase would be isolated per procedure and would not affect the opposite ECCS train. Consequently, the licensee did not describe this type of passive failure mode of the SI-860A and B valves as either "not applicable", similar to their description of other single failures the licensee deemed beyond their licensing basis, or as a more damaging single failure than those previously described in the UFSAR. Without an accurate understanding of the design basis requirement, the inspector cannot ascertain if the information provided to the NRC and its materiality to the NRC's decision-making represented a violation of 10 CFR 50.9 requirements.

The design and licensing basis information the inspectors reviewed is detailed in the Licensing Basis section, below.

Following the inspectors identification of the concern, the licensee entered the issue into their corrective action program as nuclear condition report NCR 2354646, and took action to provide means to electrically backseat the valves in the event of a packing failure, considered to be the most likely of the potential passive failures at the valves. The means to electrically backseat, as opposed to local manual backseating is necessary due to the high temperature and dose rates expected from the leaking fluid post-accident. Backseating of a valve that has experienced packing failure is expected by the licensee to limit the leakage from the ECCS fluid system into the RHR pit to acceptable values. These actions taken by the licensee would result in a reduction in the risk of the issue, even below that evaluated in the Significance section below. The licensee also detailed their understanding of the design and licensing basis of the passive failure requirements for the SI-860A and B valves in an evaluation, EC EVAL 418572, (ECCS Passive Failure) CLB & Design Basis Review Evaluation, Revision 1, and provided it to the inspector for their review. The licensee's evaluation concluded that the design change implemented in Mod 792 was implemented as intended by the designer from original construction (with hole drilled in the disc facing the containment sump side), and that it was believed that the periodic leak testing and visual inspection that had been incorporated into the original TS and maintained through the subsequent years would be used to address potential failures that result in leakage.

Licensing Basis: The NRC staff reviewed many current and historical regulatory requirements and regulatory correspondence related to the single failure criterion. Several other design documents provided by the licensee that were not included on the docket were also reviewed. The main documents reviewed are detailed below. As some of the documents were listed as "non-public" in the NRC's ADAMS system, not all relevant documents are excerpted below. The NRC staff, comprised of both regional inspectors and headquarters technical staff, concluded following a reasonable review of the requirements and documentation that the issue could be closed without immediate enforcement action and treated under the very low safety significance issue resolution process in light of the evaluated risk, the licensee's immediate actions to further reduce the risk, and the lack of clarity regarding the required passive failure assumptions to be applied to the containment sump isolation valves.

Current requirements and design and licensing basis references

  • 10 CFR 50.46 Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors: 50.46(b)(5) "Long-term cooling. After any calculated successful initial operation of the ECCS, the calculated core temperature shall be maintained at an acceptably low value and decay heat shall be removed for the extended period of time required by the long-lived radioactivity remaining in the core."
  • 10 CFR 50, Appendix K, Appendix K to Part 50ECCS Evaluation Models: D. Post-Blowdown Phenomena; Heat Removal by the ECCS 1. Single Failure Criterion. An analysis of possible failure modes of ECCS equipment and of their effects on ECCS performance must be made. In carrying out the accident evaluation the combination of ECCS subsystems assumed to be operative shall be those available after the most damaging single failure of ECCS equipment has taken place.
  • 10 CFR 50, Appendix B, Criterion III, Design Control: Design changes, including field changes, shall be subject to design control measures commensurate with those applied to the original design and be approved by the organization that performed the original design unless the applicant designates another responsible organization.
  • UFSAR Section 6.3 (current version and version in place at the time of Mod 792 development): Two independent and redundant recirculation lines are provided. Each line has two motor-operated valves. Both valves are located adjacent to the containment penetration in the RHR pit such that the line outside the containment can be isolated in the event of a passive failure.
  • UFSAR Section 6.3.2.5.1 Single Failure
Analysis:

During the ECCS recirculation phase, the failure definition is expanded to consider either an active failure or a passive fluid system failure without the loss of the protective function Reference 6.3.2-2 provides a detailed description of the H. B. Robinson Unit 2 single failure criteria. [Ref 6.3.2-2 is GID/R87038/0013, Single Failure]

[not submitted to the NRC but referenced in the UFSAR] GID/R87038/0013, Single Failure, Rev. 0, Section 1.3.8 Passive Failure: The structural failure of a static fluid system component which prevents that component from performing its design function. Specifically, a passive failure is defined as a break in a fluid pressure boundary resulting in abnormal leakage not exceeding 50 gpm. Such leak rates are consistent with limited cracks in pipes, sprung flanges, valve packing leaks or pump seal failures and are credited historically for being the basis of the 50 gpm commitment. This definition applies only to the ECCS portion of the SIS and also does not apply to radiological dose calculations.

[not submitted to the NRC-provided by the licensee] GID/R87038/SD02, SYS DBD-Safety Injection System Rev. 23, Section 4.3.2 ECCS Layout: Each LHSI pump shall be protected against all credible leaks originating within its compartment or in adjacent compartments where a flow path to its compartment exists. Credible leak sources; i.e.,

passive failures, consist of a malfunctioning RHR pump seal, flange gasket, or a valve with blown packing, etc. and "A sump pump can be located in each compartment or a sump and sump pump can be located external to the LHSI pump compartments to receive leakage flows through a system of floor drains and drain pipes. Should the sump pump fail, each compartment should be water tight to the extent which will allow for the accumulation of leakage for a period of 30 minutes without overflow into the other LHSI pump compartment. Thirty minutes is the time assumed that the operator would take to detect and isolate the leak."

Historical requirements and design and licensing basis references

  • Pre-operation Technical Specifications dated May 8, 1970 (non-public): ADAMS ML20058C527
  • Atomic Energy Commission Request for Information dated September 17, 1969, and Applicant Response to the Request (non-public): ADAMS ML20058C568
  • Safety Evaluation Report Regarding Review of the Exxon Nuclear Company Pressurized Water Reactor Generic ECCS Codes and the H. B. Robinson Reactor ECCS Evaluation Model for Conformance to All Requirements of Appendix K to 10 CFR 50 by the Office of Nuclear Reactor Regulation (non-public): ADAMS ML14175A904

and "The failure mode and effects analysis (FMEA) worksheets identified 118 potential single point system vulnerabilities that required further evaluation to determine if the postulated component failures could impact ECCS readiness during pre-accident standby operations or could cause the ECCS not to achieve the required post-accident minimum performance requirements during the short-term ECCS injection phase or during the long-term ECCS recirculation phase. Table 2.1 presents a listing of the 118 potential areas of system vulnerability and the final disposition for each potential area of vulnerability. None of the 118 areas of ECCS single point vulnerability were classified as applicable ECCS single point failures for reasons noted in the table." and "ECCS leakage in the RHR pump pit will ultimately flood the pit, disable both RHR pumps and all ECCS operation during the recirculation phase. A modification installed during Refueling Outage 13 (1990-1991) provides for remotely detecting and isolating RHR pump pit ECCS and support system leaks with equipment qualified to operate in the post-accident environment. After the leak has been isolated, one RHR pump will remain operational."

Significance: A detailed risk evaluation was performed by a regional senior reactor analyst using SAPHIRE Version 8.2.2 and NRC SPAR model Version 8.57. The analysis assumed failure of the high-pressure and low-pressure recirculation functions in the event of a passive failure of one of the RHR containment sump suction valves, 860A or 860B. The dominant sequences involved a medium break loss of coolant accident accompanied by the inability to achieve secondary side cooldown with a subsequent failure of the high-pressure recirculation function due to passive failure of the containment sump suction valves. The analysis determined that if a performance deficiency was assumed to have existed, it would have resulted in an increase in core damage frequency of <1E-6/year, representing very low safety significance (Green).

Technical Assistance Request: A technical assistance request (TAR) was not initiated.

Corrective Action Reference: NCR

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On December 15, 2020, the inspectors presented the design basis assurance inspection (programs) inspection results to Ms. Nicole Flippin and other members of the licensee staff.
  • On October 23, 2020, the inspectors presented the onsite debrief inspection results to Ernest J. Kapopoulos Jr. and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.02 Calculations

1619-0002-CALC-

001

Evaluation of Robinson Valves AFW-V2-14A, B, C

(Velan 4 Gate Valves) Using EPRI PPM v3.3 and JOG

MOV PV Methodology

Rev. 0

716M-P-100

RNP ECCS SINGLE FAILURE ANALYSIS

Rev. 12

95134-C-12

SEISMIC WEAK LINK ASSESSMENT MOV(s): CC-

749A,B

Rev. 1

A10243-C-001

THRUST CAPACITY OF REPLACEMENT YOKE FOR

MOVs CC-749A/B

Rev. 0

CSD-EG-DEP-

0101

ELECTRICAL CALCULATION OF MOTOR OUTPUT

TORQUE FOR AC AND DC MOTOR OPERATED

VALVES (MOVs)

Rev. 0

RNP-C/EQ-1329

Weak Link Analysis MOV(s) MS-V1-8A, B, C (Steam

Admission ISOL to SDAFW Turbine)

Rev. 2

RNP-C/EQ-1346

WEAK LINK ANALYSIS MOV(S) RHR-744A RHR-744B

(RHR LOOP TO RCS COLD LEG)

Rev. 4

RNP-C/EQ-1406

Weak Link Analysis MOV(s) AFW-V2-14A, B, C (SDAFW

Pump Discharge)

Rev. 0

RNP-E-8.042

AC MOV Protection Evaluation Based on Computer

Program Motorguard

Rev. 8

RNP-F/NFSA-0267

RADIOLOGICAL CONSEQUENCE ANALYSIS OF THE

AST LOSS OF COOLANT ACCIDENT

Rev. 4

RNP-M/MECH-

288

Air Operated Valve Required Thrust and Actuator

Capabilities for FCV-478, FCV-488, and FCV-498

Rev. 0

RNP-M/MECH-

1409

SET-UP CALCULATION FOR MOV CC-749A

Rev. 13

RNP-M/MECH-

1438

SET UP CALCULATION FOR MOV RHR-744B

Rev. 11

RNP-M/MECH-

1472

Evaluation of Static and Dynamic Test Data for RHR-

744B

Rev. 3

RNP-M/MECH-

21

Set Up Calculation for AFW-V2-14B

Rev. 10

RNP-M/MECH-

Set Up Calculation For MOV MS-V1-8C

Rev. 12

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

23

RNP-M/MECH-

1789

DETERMINATION OF MOV VALVE FACTORS

Rev. 5

RNP-M/MECH-

1790

DETERMINATION OF MOV STEM FACTORS

Rev. 1

RNP-M/MECH-

1892

SYSTEM MISSION TIMES

Rev. 2

RNP/M-MECH-

1651

Containment Analysis Inputs

Rev. 16

Corrective Action

Documents

AR 250367250367 AR

267179, AR

058275, AR

00505330-21, NCR

353470, NCR

565200

Corrective Action

Documents

Resulting from

Inspection

NCR 02351725

20 NRC DBAI Cancelled EC should be removed from

EQDP 2200

NCR 02351964

20 RNP NRC POV DBAI EQ EDB Update

NCR 02352010

20 RNP NRC POV DBAI RHR-744B Pre-OP valve

leakage testing

NCR 02352029

20 RNP NRC POV DBAI CC-749A/B JOG modules

NCR 02352251

20 RNP NRC POV DBAI Plant Licensing Documents

NCR 02352471

20 RNP NRC POV DBAI Exceeded MOV TEST FREQ

+ GRACE

NCR 02353305

20 RNP NRC POV DBAI Revise MOV Stem Factor

Calculation

NCR 02353397

20 RNP NRC POV DBAI Dimension inspection not

performed

NCR 02353421

20 RNP NRC POV DBAI Revise V1-8C Set-Up Calc

Test Frequency

NCR 02353837

20 RNP NRC POV DBAI Demonstrate CC-739 is

Adequately Sized

NCR 02353845

20 RNP NRC POV DBAI MS-V1-8C has rust

NCR 02354122

20 RNP NRC POV DBAI MOV Set Up Calculations

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Need Revision

NCR 02354143

20 RNP NRC POV DBAI: RNP-E-8.042 Time

correction

NCR 02354646

DBAI SI-860A/B, CV SUMP RECIRC SUCTION

PASSIVE FAILURES

NCR 02361021

20 RNP NRC POV DBAI Commitment Change not

Recognized

PRR 02352945

TMM-009 Rev. for ASME OM Code Reference to

Section ISTC-3310

Drawings

5379-01484

RESIDUAL HEAT REMOVAL SYSTEM FLOW

DIAGRAM

Rev. 49

5379-01882

SERIES 300 14"-S70WDD WELD ENDS O.S. AND Y.

DOUBLE DISC GATE VALVE WITH SMB-0

LIMITORQUE VALVE CONTROL

Rev. 5

5379-04375

Model D100-100 Operator 3" 150lb USA Std. Valve

Assembly

Rev. 3

B-190628

SH00627

Steam Driven FWP Back-Up Controls

Rev. 18

B-190628

SH00631E

Steam Driven FWP Valves V1-8A, V1-8B and V1-8C

Computer Input

Rev. 11

B-190628

SH00633A

V1-8C, SDAFW Pump Steam Isolation

Rev. 14

B-190628

SH00648

V2-14B, SDAFW Pump Discharge to S/G B

Rev. 16

B-190628

SH00657

Control Wiring Diagram

Rev. 5

CWD B-190628

CC-749A, RHR Heat Exchanger A Cooling Water Outlet

Rev. 11

CWD B-190628,

SH 221

RHR 744B, RHR Loop to RCS Cold Leg

Rev. 19

FDW-2

FDW-2 Field Inspection Isometric

dated

2/27/1984

G-190188

Reactor Building Sections

Rev. 16

HBR2-08436

4-900# - V510 Globe Valve Schedule 80 Butt Weld

Ends With M1 Manual HWhl Act

Rev. 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HBR2-08709

Limitorque Wiring Diagram

Rev. 1

HBR2-08717

2900 Socket Ends Carbon Steel Double Disc Gate

Valve with SMB-000-2 Limitorque Actuator

Rev. 5

HBR2-10982

16" FIG 47 1/2 x C W.E.O.S Gate Valve with SMB-1

Limit Unit

Rev. 3

HBR2-12712

SH00001

Forged Bolted Bonnet Primary Nuclear Motor Operated

Gate Valve

Rev. 0

HBR2-14189

Sheets 1-3

900# Gate Valve With Limitorque Operator

Rev. 0

Engineering

Changes

EC 279457

C,EE,Q2, Various, Grease, MOV Long Life,

Forsythe/Cromptom,JT/JB MOVLL Grade 1

dated

08/26/2015

EC 299154

MS-V1-8A/B/C Actuator Gear Ratio Change

Rev. 0

EC 400486

Hot Short Failure Protection for MOVs AFW-V2-14A/B/C

Rev. 5

M-1017

RHR modification

Rev. 1

M-792

Modification of valves SI-860 A+B; SI-862A; SI-863A+B;

SI-865C; SI-891C+D; and RHR-759A+B

Rev. 0

Mod M-1017

Plant Modification

Field Rev.

No. 1

Engineering

Evaluations

730.1.140

ITT General Controls Post Seismic Functional Test

Engineering Report

dated

05/17/1983

EC 418513

EVALUATION OF ACCUMULATED LEAKAGE IN THE

RHR PUMP PIT RESULTING FROM PACKING

FAILURE IN SI-860B DURING LOCA LONG TERM

RECIRCULATION

Rev. 0

EC 47656

ESR 97-00328 Rev. 006 Determination of MOV Rate-of-

Loading Factors

Rev. 6

EC EVAL 418572

(ECCS PASSIVE FAILURE) CLB & DESIGN BASIS

REVIEW EVALUATION

Rev. 0

MOV Post-Test

Data Review

Worksheet for

Work Order 20035512-06

MOV Post-Test Data Review Worksheet for Work Order 20035512-06, Valve AFW-V2-14B

dated

10/16/2018

MOV Post-Test

MOV Post-Test Data Review Worksheet for Work Order

dated

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Data Review

Worksheet for

Work Order 232689-11

232689-11, Valve MS-V1-8C

06/16/2015

RNP-TR-003

MPR 1862, Part 3, Evaluation of Stem Thrust

Requirements for RHR-744A & RHR-7448 Using the

EPRI PPM

Rev. 0

Miscellaneous

Design Criteria for Internal Overpressurization Protection

for Double Disc Gate Valves

dated

03/30/1970

SAFETY EVALUATION BY THE DIVISION OF

REACTOR LICENSING U.S. ATOMIC ENERGY

COMMISSION IN THE MATTER OF

CAROLINA POWER AND LIGHT COMPANY H. B.

ROBINSON UNIT NO. 2 DOCKET NO. 50-261

dated

05/18/1970

ORDER FOR MODIFICATION OF LICENSE

dated

2/27/1974

TECHNICAL SPECIFICATIONS FOLLOW-UP REVIEW

SECTION 4.4.3 Post Accident Recirculation Heat

Removal System

dated

11/21/1994

H.B. Robinson TS section 4.4.3 Amendment 163

27-703-32

Manual Steam Valves, Gate-Instruction Manual

Rev. 3

28-034-89

Nuclear Hydromotors NH91 thru NH98

Rev. 7

28-562-71

SMB Valve Controls

Rev. 43

28-812-46

Velan Valve Instruction Manual for Manual Valves

Installation, Operation, and Maintenance

Rev. 12

ADAMS

ML14175A904

SAFETY EVALUATION REPORT REGARDING

REVIEW OF THE EXXON NUCLEAR COMPANY

PRESSURIZED WATER REACTOR GENERIC ECCS

CODES AND THE H. B. ROBINSON REACTOR ECCS

EVALUATION MODEL FOR CONFORMANCE TO ALL

REQUIREMENTS OF APPENDIX K TO 10 CFR 50 BY

THE OFFICE OF NUCLEAR REACTOR REGULATION

dated

09/11/1975

ADAMS

ML14188A654

SUBJECT: ORDER IMPOSING A CIVIL MONETARY

PENALTY

dated

03/17/1989

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ADAMS

ML14191A483

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50-261/LICENSE NO. DPR-23

REQUEST FOR LICENSE AMENDMENT -CONTROL

ROOM HABITABILITY

dated

08/29/1990

ADAMS

ML14192A470

XN-NF-83-72 REVISION 2 SUPPLEMENT 1 H.B.

ROBINSON UNIT 2, CYCLE 10 SAFETY ANALYSIS

REPORT, REVISION 2 DISPOSITION OF CHAPTER 15

EVENTS

dated Jul.

1984

ADAMS

ML14227A342

Chapter 5 UFSAR

dated 1970

ADAMS

ML20058C429

Chapter 6 FSAR

dated 1970

ADAMS

ML20058C527

Technical Specifications

dated

05/08/1970

ADAMS

ML20058C551

ADDITIONAL INFORMATION REQUIRED H. B.

ROBINSON UNIT NO. 2 DOCKET NO. 50-261

dated

11/05/1969

ADAMS

ML20058C568

CAROLINA POWER & LIGHT COMPANY REQUEST

FOR INFORMATION DOCKET NO. 50 261

.

dated

09/17/1969

ADAMS

ML20093J554

XN-NF-84-72 H. B. ROBINSON UNIT 2 LARGE BREAK

LOCA-ECCS ANALYSIS WITH INCREASED

ENTHALPY RISE FACTOR

dated Jul.

1984

CC-749A,

20015786-06, 3-7-

MOV POST-TEST DATA REVIEW WORKSHEET

dated

5/31/2017

CC-749A, WO 1011026-01, 6-1-

Static Post Test Evaluation of GL 89-10 Program Rising

Stem MOVs

dated

7/4/2010

Contingency WO 20430760 01

PROVIDE TEMPORARY POWER TO RHR-SMPPMP-A

(CONTINGENCY)

Contingency

WO20430761 01

PROVIDE TEMPORARY POWER TO RHR-SMPPMP-B

(CONTINGENCY)

CPL-HBR-SPEC-5

CP&L Specification for Carbon Steel Motor Operable

Valves for Non-Radioactive Service

Rev. 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DBD-R87038-

SD25

Design Basis Document Main Steam System

Rev. 8

DBD-R87038-

SD32

Design Basis Document Auxiliary Feedwater System

Rev. 11

DBD/R87038/SD02 SYS DBD - SAFETY INJECTION SYSTEM

Rev. 23

DBD/R87038/SD03 SYS DBD - RESIDUAL HEAT REMOVAL SYSTEM

Rev. 11

DBD/R87038/SD13 COMPONENT COOLING WATER SYSTEM

Rev. 13

DR 80.2

GENERIC QUALIFICATION OF SERIES EA180 LIMIT

SWITCHES WITH AN ELECTRICAL RECEPTACLE

AND CONNECTOR/CABLE ASSEMBLY

Rev. 1

EQDP-2200

NAMCO EA 180 SWITCHES, EC 210 AND 290

CONNECTOR ASSEMBLIES

Rev. 13

ESR 00-00181

FCV Hydramotor supports

dated

05/01/2001

ESR 00-00205

FCV-1424-AO

dated

06/27/2001

GID/90-181/00/RCI

GI DBD - REACTOR CONTAINMENT ISOLATION

Rev. 15

GID/R87038/0013

GENERIC ISSUES DOCUMENT SINGLE FAILURE

Rev. 0

HBR-02562

MS-V1-8C Purchase Order

dated

10/27/1987

HBR-02766

PO for FCV-1424

dated

2/11/1982

L2-M-011

Specification for V1-8A, B, C, D, E, & F Carbon Steel

Gate Valves For Nonradioactive Service in the Auxiliary

Feedwater System

Rev. 0

Letter File: NG-

3514 (R) Serial:

NG-74-1122

H. B. ROBINSON UNIT NO. 2 LICENSE DPR-23,

DOCKET NO. 50-261 CONFORMANCE WITH

10CFR50.46

dated

10/02/1974

LICENSEE EVENT

REPORT (LER)

89-008-00

POTENTIAL FOR LOSS OF RESIDUAL HEAT

REMOVAL CAPABILITY DUE TO PUMP FLOODING

dated

05/04/1989

MOV Stem

Lubricant Aging

Research

INEEL Presentation

dated

01/15/2003

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NGG-PMB-HYD-01 NGG Equipment Reliability Template, Hydramotor

Actuators

Rev. 0

NLS-87-157

RESPONSE TO REQUEST FOR ADDITIONAL

INFORMATION REGARDING 10CFR50, APPENDIX J

TEST PROGRAM EXEMPTION

dated

9/14/1987

NLS-88-152

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 5O-261/LICENSE NO. DPR-23 REPLY

TO NOTICE OF VIOLATION AND ANSWER TO

NOTICE OF VIOLATION ENFORCEMENT ACTION 88-

dated

07/15/1988

NLS-89-106

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50-261/LICENSE NO. DPR-23 REPLY

TO ORDER IMPOSING A CIVIL PENALTY

ENFORCEMENT ACTION 88-88 lOCFR50 APPENDIX

K VIOLATION

dated

04/14/1989

NLS-89-108

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50-261/LICENSE NO. DPR-23

RESPONSE TO APPENDIX K SINGLE FAILURE

lOCFR50.54(f)

dated

04/19/1989

NLS-89-124

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50.261/LICENSE NO. DPR-23

FOLLOW-UP RESPONSE TO APPENDIX K SINGLE

FAILURE lOCFR50.54(f) LETTER

dated

05/19/1989

NLS-89-173

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50-261/LICENSE NO. DPR-23 SINGLE

ELECTRICAL FAILURES

dated

06/14/1989

NLS-90-027

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50-261/LICENSE NO. DPR-23

CONTROL ROOM HABITABILITY TMI ITEM II.D.3.4

dated

05/21/1990

NLS-91-120

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 5O-261/LICENSE NO. DPR-23

EMERGENCY CORE COOLING SYSTEM (ECCS)

FAILURE MODES AND EFFECTS ANALYSIS (FMEA)

SUMMARY INFORMATION

dated

05/07/1991

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NLS-91-120

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

DOCKET NO. 50-261/LICENSE NO. DPR-23

EMERGENCY CORE COOLING SYSTEM (ECCS)

FAILURE MODES AND EFFECTS ANALYSIS (FMEA)

SUMMARY INFORMATION

dated

05/07/1991

NRC-88-017

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.

- REQUEST FOR ADDITIONAL INFORMATION

SAFETY INJECTION PUMP B AUTO TRANSFER

SCHEME

dated

01/14/1988

NRC-88-337

SUBJECT: NOTICE OF VIOLATION AND PROPOSE

IMPOSITION OF CIVIL PENALTY (NRC INSPECTION

REPORT NOS. 50-261/88-03 AND 50-261/88-04)

dated

06/15/1988

NRC-89-190

SUBJECT: ORDER IMPOSING A CIVIL MONETARY

PENALTY

dated

03/17/1989

NRC-91-041

SUBJECT: SINGLE FAILURE CRITERION,

ELECTRICAL SYSTEMS - H. B. ROBINSON STEAM

ELECTRIC PLANT, UNIT No. 2 (TAC No. 72969)

dated

01/31/1991

NUREG-0138

STAFF DISCUSSION OF FIFTEEN TECHNICAL

ISSUES LISTED IN ATTACHMENT TO NOVEMBER 3,

1976 MEMORANDUM FROM DIRECTOR, NRR TO

NRR STAFF

dated Nov.

1976

NUREG-0153

STAFF DISCUSSION OF TWELVE ADDITIONAL

TECHNICAL ISSUES RAISED BY RESPONSES TO

NOVEMBER 3, 1976 MEMORANDUM FROM

DIRECTOR, NRR TO NRR STAFF

dated Dec.

1976

NUREG/CP-0152,

Volume 5

EPRI MOV Stem Lubricant Test Program, Frictional

Performance of Exxon Nebula and MOV Long Life in a

Stem Lubrication Application, John Hosler

NUS-8829-P-100

Design Input Requirements for Auxiliary Feedwater

System Control Modification

Rev. 4

NUS-8829-P-200

Specification for Flow Control Valve and Electro-

Hydraulic Actuators

Rev. 1

PLP-100

Technical Requirements Manual section 3.2.3

Revs. 0 and

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PO 03053015

Rev. 2

PRR 02354707

APP-001 R069 Emergent Initiate Work Orders

dated

10/24/2020

PRR02354708

EPP-24 R010 (Emergent, NCR 2354646)

dated

10/24/2020

Rate of Loading

Flowserve Test

Program

2003 MUG Presentation

dated 2003

RHR-744B,

212497-06, 10-

2-18

MOV POST-TEST DATA REVIEW WORKSHEET

dated

10/24/2018

SD-025

Main Steam System

Rev. 9

TMM-032

MOTOR OPERATED VALVE PROGRAM

Rev. 38

TMM-035

POST-TEST EVALUATION OF MOV PERFORMANCE

Rev. 24

TMM-127

Post Test Evaluation of AOV Performance, CC-739

Rev. 7,

completed

9/30/2018

Procedures

8S19-P-101

Station Blackout Coping Analysis Report

Rev. 11

AD-EG-ALL-1110

Design Review Requirements

Rev. 9

AD-OP-ALL-0110

GENERAL EQUIPMENT OPERATING STANDARDS

Rev. 3

AD-OP-RNP-0205

OPERATOR TIME CRITICAL ACTION PROGRAM

Rev. 1

AD-PI-ALL-0100

Corrective Action Program

Rev. 24

AOP-014

COMPONENT COOLING WATER SYSTEM

MALFUNCTION

Rev. 41

AOP-020

LOSS OF RESIDUAL HEAT REMOVAL (SHUTDOWN

COOLING)

Rev. 50

APP-001

MISCELLANEOUS NSSS

Rev. 68

CSD-EG-DEP-

0359

MOTOR OPERATED VALVE STRUCTURAL

EVALUATION

Rev. 0

EGR-NGGC-0029

MIDAS-PGN MOV DESIGN CALCULATION

IMPLEMENTATION PROCEDURE

Rev. 2

EGR-NGGC-0030

PGNTEST MOV TEST SETUP, EVALUATION AND

TRENDING

Rev. 2

EGR-NGGC-0203

MOTOR OPERATED VALVE PERFORMANCE

Rev. 17

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PREDICTION, ACTUATOR SETTINGS, AND

DIAGNOSTIC TEST DATA RECONCILIATION

EOP-ECA-1.1

LOSS OF EMERGENCY COOLANT RECIRCULATION

Rev. 2

EOP-ES-1.3

TRANSFER TO COLD LEG RECIRCULATION

Rev. 1

EPP-24

ISOLATION OF LEAKAGE IN THE RHR PUMP PIT

Rev. 9

EPP-24-BD

EPP-24 BASIS DOCUMENT

Rev. 9

OP-402

Auxiliary Feedwater System

Rev. 105

OST-201-1

MDAFW System Component Test - Train A

Rev. 38,

completed

08/05/2020

OST-206

Comprehensive Flow Test for the Steam Driven Auxiliary

Feedwater Pump

Rev. 65,

completed

09/08/2020

OST-207

Comprehensive Flow Test for the Motor Driven Auxiliary

Feedwater Pumps

Rev. 60.

completed

11/18/2018

OST-252-1

RHR SYSTEM VALVE TEST - TRAIN A

Rev. 27,

completed

9/14/2020

OST-252-2

RHR SYSTEM VALVE TEST - TRAIN B

Rev. 29,

completed

7/27/2020

OST-254

RESIDUAL HEAT REMOVAL SYSTEM AND RHR

LOOP SAMPLING SYSTEM LEAK TEST (REFUELING)

Rev. 42

OST-258-1

RHR VALVE POSITION INDICATOR VERIFICATION -

TRAIN A

Rev. 11,

completed

2/12/2018

OST-258-2

RIIR VALVE POSITION INDICATOR VERIFICATION -

TRAIN B

Rev. 10,

completed

10/3/2018

OST-701-3

CC-739 INSERVICE VALVE TEST

Rev. 9,

completed

7/3/2020

OST-707-3

INSERVICE VALVE POSITION INDICATOR

Rev. 6,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

VERIFICATION FOR CC-739 AND CC-832

completed

1/6/2020

OST-945

Auxiliary Feedwater Switch/Valve Position Verification

Rev. 5

SP-1610

Flush of AFW-165, Motor Driven Aux Feedwater Pump

Discharge Flex Conn Iso

Rev. 1

SP-837

Steam Driven AFW Pump Low Steam Pressure

Operation

dated

11/13/1988

Work Orders

WO 20035512-27,

1; WO 20035512-

01, M; WO 13386072-01, M;

WO 12332689-01,

M; WO 20035512-

EL;

WO 02232689-06,

EL; WO 20056710-

01, K; WO 212783-05, WO 20015786-06, WO 212497-06;

88ADBI1; WO 13326176-01; WO 20191560-01; WO 20186959