ML14191B032

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/88-30 on 881011-1110.No Violations Noted. Major Areas Inspected:Operational Safety Verification, Physical Protection,Surveillance Observation,Maint Observation & Onsite Followup of Events
ML14191B032
Person / Time
Site: Robinson 
Issue date: 12/09/1988
From: Fredrickson P, Garner L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14191B031 List:
References
50-261-88-30, NUDOCS 8812200338
Download: ML14191B032 (10)


See also: IR 05000261/1988030

Text

RREG

UNITED STATES

WLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, NAN.

ATLANTA, GEORGIA 30323

Report No.:

50-261/88-30

Licensee:

Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name:

H. B. Robinson

Inspection Conducted: October 11 - November 10, 1988

Inspector:

to

L. W. Garner,

nior

de

Inspector

Date Signed

Approved by:

//q

I 'g

Pr-P. E. Fredrickson, Section Chief

Oate Signed

Reactor Projects Section 1A

Division of Reactor Projects

SUMMARY

Scope:

This routine,

announced inspection was conducted in the areas of

operational safety verification, physical protection, surveillance

observation, maintenance observation, onsite followup of events at

operating power reactors and onsite review committee.

Results: A weakness was identified in the Operation Department's review for

applicable

Technical

Specification

action

statements -upon

determination of inoperable equipment, paragraph 7.a.

Within the areas inspected, no violations or deviations were

identified.

Four unresolved items were identified involving:

Improper setpoints of MCC-5 and MCC-6 feeder breakers,

paragraph 7.a.

-

HVH 1-4 penetration splices being non-EQ, paragraph 7.b.

- Declaration of an Unusual Event when shutdown by TS is determined,

paragraph 7.b.

-

Unreinforced masonry block wall, paragraph 7.c.

FDR

ADOCK 05000261

Q

D

REPORT DETAILS

1. Licensee Employees Contacted

R. Barnett, Maintenance Supervisor, Electrical

R. Chambers, Engineering Supervisor, Performance

  • J. Curley, Director, Regulatory Compliance

C. Dietz, Manager, Robinson Nuclear Project Department

R. Femal, Shift Foreman, Operations

W. Flanagan, Manager, Design Engineering

W. Gainey, Support Supervisor, Operations

R. Johnson, Manager, Control and Administration

D. Knight, Shift Foreman, Operations

E. Lee, Shift Foreman, Operations

D. McCaskill, Shift Foreman, Operations

R. Moore, Shift Foreman, Operations

  • R. Morgan, Plant General Manager

M. Page, Engineering Supervisor, Plant Systems

D. Quick, Manager, Maintenance

  • D. Sayre, Senior Specialist, Regulatory Compliance

D. Seagle, Shift Foreman, Operations

  • J. Sheppard, Manager, Operations

R. Steele, Shift Foreman, Operations

  • H. Young, Director, Quality Assurance/Quality Control

Other licensee employees

contacted included technicians, operators,

mechanics, security force members, and office personnel.

NRC Resident Inspector

  • L. Garner
  • Attended exit interview on November 22, 1988.

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2.

Licensee Action on Previous Enforcement Matters (92702)

Not Inspected.

3.

Operational Safety Verification (71707)

The inspector observed licensee activities to confirm that the facility

was being operated safely and in conformance with regulatory requirements,

and that the licensee management control system was effectively dis

charging its responsibilities for continued

safe operation.

These

activities were confirmed by direct observations, tours of the facility,

interviews and discussions with licensee management and personnel,

2

independent verifications of safety system status and limiting conditions

for operation, and reviews of facility records.

Periodically, the inspector reviewed shift logs, operations records, data.

sheets, instrument traces, and records of equipment malfunctions to verify

operability of safety related equipment and compliance with TS.

Specific

items reviewed include control

room

logs, auxiliary logs,

operating

orders, standing orders, and equipment tagout records.

Through periodic

observations of work in progress and discussions with operations staff

members, the inspector verified that the staff was knowledgeable of plant

conditions;

responding properly to

alarm conditions;

adhering to

procedures and applicable administrative controls; and aware of equipment

out of service,

surveillance testing,

and maintenance activities in

progress. The inspector also observed that access to the control room was

controlled and operations personnel were carrying out their assigned

duties in an attentive and professional manner.

The control room was

observed to be free of unnecessary distractions.

The inspector performed

channel checks, reviewed component status and safety related parameters to

verify conformance with the TS.

During this reporting interval,

the inspector verified compliance with

selected LCOs. This verification was accomplished by direct observation

of monitoring instrumentation,

valve positions, switch positions,

and

review of completed

logs

and records.

Plant tours were routinely

conducted to verify the operability of standby equipment; assess the

general

condition of plant equipment;

and verify that radiological

controls, fire protection controls, and equipment tag out prodedures were

being properly implemented. These tours verified the absence of unusual

fluid leaks; the lack of visual degradation of pipe, conduit and seismic

supports; the proper positions and indications of important valves and

circuit breakers; the lack of conditions which could invalidate EQ; the

operability of safety related instrumentation; the calibration of safety

related and control instrumentation including area radiation monitors,

friskers and portal monitors; the operability of fire suppression and fire

fighting equipment; and the -operfability of 'emergency lighting equipment.

The inspector also verified that housekeeping wa's adequate and areas were

free of unnecessary fire hazards and combustible materials.

No violations or deviations were identified within the areas inspected.

4.

Physical Protection (71707)

In the course of the monthly activities, the inspector included a review

of the licensee's physical security program. The inspector verified by

general observation and interviews, that measures taken to assure the

physical protection of the facility met current requirements.

The

performance of various shifts of the security force was observed to verify

that daily activities were conducted in accordance with the requirements

of the security plan. Activities inspected included protected and vital

areas; access controls; searching of personnel, packages, and vehicles;

3

badge

issuance and retrieval; patrols; escorting of visitors;

and

compensatory measures.

No violations or deviations were identified within the areas inspected.

5. Monthly Surveillance Observation (61726)

The inspector observed certain surveillance related activities of safety

related systems and components to ascertain that these activities were

conducted in accordance with license requirements.

For the surveillance

test procedures listed below, the inspector determined that precautions

and LCOs were met, the tests were completed at the required frequency, the

tests conformed to TS requirements, the required administrative approvals

were obtained prior to initiating the tests,

and the testing was

accomplished by qualified personnel in accordance with an approved test

procedure. The inspector independently verified that the systems were

properly returned to service.

Specifically, the inspector witnessed/

reviewed portions of the following test activities:

o

OST-010 (revision 9) Power Range Calorimetric During Power Operation

The

test compares the power range neutron indications to. the

calculated thermal

power

as required by TS

Table 4.1-1.

The

inspector verified that the neutron indications were within accepted

tolerances and required no adjustments.

o

RST-001 (revision 29) Radiation Monitor Source Checks

The test is a channel functional test of the Radiation Monitoring

System monitors as required

by

TS Table 4.1-1.

The inspector

verified that for selected monitors the test procedure was performed

properly and the acceptance criteria was met.

No violations or deviations were identified within the areas inspected.

6. Monthly Maintenance Observation (62703)

The inspector observed several maintenance related activities of safety

related systems and components to ascertain that these activities were

conducted in accordance with approved procedures,

TS,

and appropriate

industry codes and standards.

The inspector determined that these

activities were not violating TS

LCOs and- that redundant components were

operable. The inspector also determined that activities were accomplished

by qualified personnel using approved procedures,

QC hold points were

established where required, required administrative approvals and tagouts

were obtained prior to work initiation, proper radiological controls were

adhered to, appropriate ignition and fire prevention controls were

implemented, replacement parts and materials used were properly certified,

and the effected equipment was properly tested before being returned to

service.

In particular, the inspector observed/reviewed the following

maintenance activities:

4

0 W/R 88-ALBM1 Replace HVH 1-4 Cable Splices

o

CM-309 (revision 4) Environmental Sealing Low Voltage Electrical

Splices

The inspector verified that the butt splices were performed in

accordance with the procedure. This included verification of proper

cleaning of the cable jacket, sufficient overlap of sleeve and cable

jacket, removal of rough edges, sealing of the ends as demonstrated

by adhesive flow, and proper inspection of installation by QC as

specified by attachments 8.3 and 8.4.

No violations or deviations were identified within the areas inspected.

7.

Onsite Followup of Events at Operating Power Reactors (93702)

a.

On October 5, 1988, during reconstitution of the design basis for the

electrical loading of safety related MCCs, the licensee discovered a

potential overload condition could exist under certain postulated

accident conditions.

A LOCA with offsite power available and the

loss of either MCC-5 or MCC-6 would result in the starting of standby

non-vital loads on the other MCC.

This starting of standby loads

would trip the feeder breaker to the operating

MCC,

thereby,

resulting in a loss of all 480 V safety related MCC power.

The

condition would not be expected to exist with the loss of offsite

power because the standby non-vital loads are stripped from the MCCs

under this condition in order to limit the loading on the EDGs.

Anticipated loads on MCC-5

and MCC-6 are 794 and 820 amps,

re

spectively. These loads could cause the feeder breakers to MCC-5 and

MCC-6 to trip, since the feeder breakers' trip setpoints are 800 amps

+/- 10%. In addition, the MCCs' continuous rating of 600 amps would

be exceeded.

While verification of the initial calculations were being performed,

the licensee implemented compensatory actions on October 6, 1988, to

lock out certain non-vital loads on MCC-5 and MCC-6 in order to limit

anticipated loads under the postulated scenario to less than 700

amps.

On October 10,

1988,

the potential setpoint problem was

confirmed and the event reported to the NRC in accordance with

10 CFR 50.72. Pending further review by the NRC of the circumstances

surrounding the event,

this is considered an

UNR:

Investigate

Circumstances Surrounding Improper Setpoints of MCC-5

and

MCC-6

Feeder Breakers (261/88-30-01).

On October

11,

1988, subsequent reviews of limiting components

identified that the feeder cables to MCC-6 from emergency bus E-2

were potentially undersized. In accordance with design standards the

derated cable ampacity for continuous duty was determined to be 474

amps.

A similar problem did not exist with MCC-5 because those

cables had been changed to a larger ampacity due to Appendix R

modifications.

Based

upon

engineering

judgement,

the

licensee

believed that refined calculations, with actual plant configurations

5

taken into account,-would demonstrate the acceptability of the MCC-6

feeder cables.

On

October 13,

1988, preliminary calculations

indicated a continuous duty ampacity of approximately 750

amps.

However, the licensee was informed by a consultant who was performing

similar independent calculations that the value was approximately 450

amps.

Based upon this information the licensee declared MCC-6

inoperable at 9:00 p.m., on October 13, 1988. On October 14, 1988, a

plant shutdown was commenced. The unit was placed in hot shutdown by

1:00 p.m.

that

same day and in cold shutdown at 9:45 a.m.

on

October 15, 1988.

Upon reaching cold shutdown,

MCC-6 was removed from service and the

cables were replaced.

'In addition, critical portions of MCC-5

and

MCC-6,

as well

as other safety related cables were physically

inspected for signs of overheating. None were found. The inspector

witnessed the replacement of the MCC-6 feeder cables and independ

ently inspected parts of MCC-5 and MCC-6.

No conditions effecting

operability were noted.

Subsequent calculations verified that the

continuous duty ampacity of the removed MCC-6 feeder cables had in

fact been adequate to assure MCC-6

operability.

Apparently,

a

miscommunication problem between the licensee and their consultant

had resulted in the consultant utilizing the incorrect plant

configuration. Even though this *was thought to be the case prior to

the shutdown,

plant management determined that it

was prudent to

shutdown and replace the cables.

The licensee issued JCO no.88-010 to address. the potential safety

significance of cable sizing of loads fed from MCC-5

and MCC-6.

Although some cables were determined to be undersized, the licensee

demonstrated that either a failure would not occur or would not

result in a safety problem. The inspector reviewed the JCO and had

no outstanding concerns.

The unit was returned to service at

3:45 p.m. on October 18, 1988.

On October 14, 1988, a review by a licensed operator on rotation into

the regulatory compliance group identified that on October 13,

at

9:00 p.m.,

the plant should have- declared a phase B containment

isolation valve inoperable when MCC-6 was declared inoperable.

This

automatic isolation valve, CC-735,

is associated with the reactor

coolant pumps' component cooling water return line from containment.

Consequently, it can not be shut when the reactor coolant pumps are

running.

PEP-101,

Initial Emergency- Actions, item 6, Loss of CV

integrity, requires an unusual event be declared if

one or more

automatic isolation valves are inoperable for greater than 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

and are not isolated or repaired. Thus in accordance with PEP-101,

an unusual event was declared at 11:06 a.m.,

on October 14,

1988.

The plant remained in an unusual event status until 9:45 a.m.

on

October 15,

1988,

when the unit was placed in cold shutdown.

Containment integrity is not required per TS when the unit is in cold

shutdown. The failure to identify that a containment isolation valve

6

was effected resulted in the unusual event being declared approxi

mately 11

hours late.

Additionally, TS 3.6.3 LCO was unknowingly

entered when the MCC was declared inoperable, but was not violated

in that the plant was in cold shutdown within 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of the

initial inoperability determination.

As stated above,

after the

fact, it

was proven that MCC-6 had been operable and declaration of

an unusual event had not been required.

Neverthelest,

it

is of

significant concern that all the relevant TS Action Statements and

regulatory requirements were not properly assessed by the operations

department personnel.

This is of significant concern because of the

long period of time that was available for review prior to declaring

MCC-6 inoperable (e.g. from October 5, 1988, when the operability of

MCC-6

came into question,

to October 13,

1988,

when

MCC-6

was

declared inoperable).

b.

Non-EQ Splices on Containment Fan Coolers

On October 27, 1988, while performing field verifications to resolve

documentation discrepancies,

it

was determined that the pigtail

splice to the penetrations for the containment fan coolers HVH 1-4

were not as expected. Engineering review and subsequent review by

the

PNSC determined that the splices were non-EQ and were

not

qualifiable.

The HVH 1-4

units were declared inoperable at

10:20 p.m.

Reactor

shutdown

was

commenced

from

91% power at

11:00 p.m.

Hot shutdown was obtained at 2:03 a.m.,

on October 28,

1988. HVH 1 and 3 were removed from service and the splices upgraded

to be in conformance with a qualified configuration.

The inspector

verified that the repairs were performed in accordance with approved

procedures. These units were returned to service at 1:16 a.m.

on

October 29,

1988.

HVH 2 and 4 were then removed from service,

upgraded, tested, and declared operable at 10:36 a.m.

on the same

day. Reactor startup was commenced at 4:39 p.m.

and the generator

synchronized to the grid at 5:46 p.m., on October 29, 1988.

The reason why the Cruise-Hinds supplied penetration splices on power

cables were

not replaced with an

EQ configuration during the

August 1987 shutdown to upgrade Cruise-Hinds supplied penetration

splices for instrumentation cables in not

known at this time.

Pending further inspection, this item is considered an UNR:

Review

Circumstances Surrounding HVH 1-4 Penetration Splices Being Non-EQ

(261/88-30-02).

During review of the event, the inspector questioned if

an unusual

event should have

been declared

per PEP-101,

Initial Emergency

Actions. Item 1 of Attachment 9.1 to the PEP requires an unusual

event be declared upon "violation of any limiting condition for

operation

requiring

shutdown

....

Preliminary

discussions

with regional specialists in this area indicates that the intent

of these words is that if

a shutdown is required per

TS 3.0

(e.g.,

if

an

LCO cannot be satisfied because of circumstances in

excess of those addressed,

place the unit in hot shutdown within

7

eight hours) then an unusual event is to be declared.

However, the

licensee indicates that it

has always been their position that

violation of a LCO has meant not meeting the time limitation (e.g.,

eight hours to be in hot shutdown).

The licensee also polled other

utilities within Region II and determined that there is no consistent

practice of declaring an unusual event involving shutdowns due to TS 3.0 type statements.

Furthermore, the

licensee provided the

inspector a draft final report,

Methodology

For Development of

Emergency Action Levels,

by the Nuclear Management

and Resource

Council which documents an industry initiative to standardize this

practice in a fashion similar to the licensee's position.

Pending

further review by the NRC, this item is considered an UNR:

Determine

If a Shutdown per TS 3.0 Requires Declaration of an Unusual Event

(261/88-30-03).

c. AFW Hanger Attached to An Unreinforced Block Wall

On November 2, 1988, while drilling into a wall for pre-outage work,

the licensee determined that wall penetration no. P4 in the AFW pump

room had been filled with unreinforced masonry block.

One brace of

AFW hanger no.

FW-2-136 was determined to be attached to this wall.

This is the first seismic support from the B MDAFW pump discharge

nozzle. Subsequent analysis indicated that this block wall could

fail. under lateral compressive loads during a seismic event. Such a

failure could potentially render the support inoperable. A design

change notice was issued to existing modification no.

937 to add

additional support members and remove the effected brace from the

hanger. Upon notification of the inoperable hanger, the B MDAFW pump

was declared inoperable in accordance with TS 3.4.4.6 at 5:29 p.m.,

on November 3, 1988.

The system was returned to service at

9:35 p.m.,

on November 5, 1988,

after final QC inspection of the

modified support.

The inspector verified that the redundant AFW

pumps were operable in accordance with TS during this period.

The

licensee is submitting a special report to the NRC concerning this

event. Pending further review by the NRC, this item is considered an

UNR:

Review special report and related corrective actions regarding

unreinforced..masonry block wall (261/88-30-04).

No violations or deviations were identified within the areas inspected.

8. Onsite Review Committee (40700)

The inspector evaluated certain activities of the PNSC to determine

whether the onsite review functions were conducted in accordance with TS

and other regulatory requirements. In particular, the inspector attended

a PNSC meeting on October 27,

1988, concerning non-qualified splices to

containment cooling fans HVH 1-4. It was ascertained that provisions of

the TS dealing with membership,

review process, frequency, and qualifi

cations were satisfied. Previous meeting minutes were reviewed to confirm

that decisions and recommendations

were accurately reflected in the

minutes.

8

No violations or deviations were identified within the areas inspected.

9. Exit Interview (30703)

The inspection scope and findings were summarized on November 22,

1988,

with those persons indicated'in paragraph 1. The inspector described the

areas inspected and discussed in detatl the inspection findings listed

below, as well as the NRC concern over the exhibited weakness in identi

fying the applicable TS action statement upon declaring MCC -6 inoperable.

In addition, the identification of UNR 261/88-30-04 was discussed with the

licensee on December 9, 1988. Dissenting comments were not received from

the licensee. Proprietary information is not contained in this report.

No written material was given to the licensee by the Resident Inspector

during this report period.

Items Numbers

Status

Description/Reference Paragraph

88-30-01

Open

UNR -

Investigate Circumstances

Surrounding Improper Setpoints of MCC-5

and -6 Feeder Breakers. Paragraph 7.a.

88-30-02

Open

UNR -

Review Circumstances Surrounding

HVH 1-4

Penetration

Splices

Being

Non-EQ. Paragraph 7.b.

88-30-03

Open

UNR -

Determine

If

a Shutdown

per

TS 3.0

Requires Declaration

of an

Unusual Event. Paragraph 7.b.

88-30-04

Open

UNR -

Review

Special

Report and

Related Corrective Actions Regarding

Unreinforced

Masonry

Block

Wall.

Pararaph 7.c.

10.

List of Abbreviations

AFW

Auxiliary Feedwater

CFR

Code of Federal Regulations

CM

Corrective Maintenance

CP&L

Carolina Power & Light

CV

Containment Vessel

EDG

Emergency Diesel Generator

EQ

Environmental Qualifications

FW

Feedwater

HVH

Heating Ventilation Handling

JCO

Justification For Continued Operation

LCO

Limiting Condition for Operation

LOCA

Loss of Coolant Accident

MCC

Motor Control Center

MDAFW

Motor Driven Auxiliary Feed Water

NRC

Nuclear Regulatory Commission

9

OMM

Operations Management Manual

OST

Operations Surveillance Test

PEP

Plant Emergency Procedure

PNSC

Plant Nuclear Safety Committee

QC

Quality Control

TS

Technical Specification

  • UNR

Unresolved Item

W/R

Work Request

  • Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve violations or deviations.