ML14181A610

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/94-24 on 940912-16.Violations Noted.Major Areas Inspected:Review of Licensee Status Re Implementation of SBO Rule & Corrective Actions for Previous Inspection Findings in Electrical Area
ML14181A610
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 10/04/1994
From: Moore R, Shymlock M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14181A607 List:
References
50-261-94-24, NUDOCS 9410120091
Download: ML14181A610 (10)


See also: IR 05000261/1994024

Text

  • plf REG&4

UNITED STATES

o

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

.

Report No.: 50-261/94-24

Licensee:

Carolina Power and Light Company

P.O. Box 1551

Raleigh, NC, 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name: H. B. Robinson

Inspection Conducted:

September 12-16, 1994

Inspector:

_4

. Moore

Da e Si

Approved by:

_

_

_

_

_

_

_

_____

M. B. Shymfock, Chief

Date Signed

Plant Systems Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection was conducted to review the licensee's

status on the implementation of the Station Blackout (SBO) Rule and corrective

actions for previous inspection findings in the electrical area.

Results:

In the areas inspected two violations were identified. Violation 50-261/94

24-01 identified inadequate testing to demonstrate the one hour capability of

the Station Blackout (SBO) alternate AC power source (paragraph 2.8).

Non-cited violation 50-261/94-24-02 identified inadequate environmental

qualification documentation of LOCA-submerged safety related instrument cables

(paragraph 3.1).

The licensee's actions to comply with the SBO Rule were essentially complete,

with the exception noted above. The licensee's engineering organization

demonstrated a strong knowledge of electrical design issues in the areas

reviewed.

Enclosure

9410120091 941004

PDR ADOCK 05000261

Q

PDR

1.

Persons Contacted

Licensee Employees

  • B. Barnett, Maintenance Support Manager
  • J. Boska, Electrical, Instrumentation and Control Engineering Manager
  • G. Castleberry, Electrical Design Manager

G. Chapel, Mechanical Design Engineer

  • B. Clark, Maintenance Manager

D. Dyksterhouse, Civil Engineer

  • D. Gudger, Regulatory Programs
  • M. Herrel, Acting Plant General Manager
  • R. Krich, Regulatory Affairs Manager

J. Lewis, Electrical Design Engineer

  • F. Modlin, Electrical Design Engineer

R. Moore, Shift Operations Manager

  • D. Neal, Licensed Operator Requalification Training Manager
  • J. Pennington, Plant Operator

G. Walters, Support Training Manager

Other licensee employees contacted during this inspection included

engineers, technicians, and administrative personnel.

NRC Employees

  • C. Ogle, Resident Inspector
  • W. Orders, Senior Resident Inspector
  • Attended exit interview

Acronyms and abbreviations are listed in paragraph 5 of this report.

2.0

Electrical Maintenance (62705) Station Blackout (SBO) Status

The inspector reviewed the status of Robinson activities to comply with

the SBO rule of 10 CFR 50.63, Loss of All Alternating Current Power.

The initial NRC Safety Evaluation (SE) was transmitted to the licensee

on February 4, 1991.

An NRC Supplemental Safety Evaluation (SSE),

transmitted to the licensee on September 16, 1991, addressed the

licensee's February 11, 1991 response to the SE. The licensee's

response to the SSE, dated October 21, 1991, stated that CP&L would

complete all items necessary to meet 10 CFR 50.63 requirements no later

than February 11, 1993. This inspection reviewed the status of the

10 CFR 50.63 requirements and specific Robinson requirements included in

the SE and SSE.

2.1

Coping Strategy

The SBO coping strategy at Robinson included an eight hour coping

duration to maintain the plant at hot shutdown conditions using the

turbine driven auxiliary feed water pump and the steam generator power

operated relief valves. The unit would operate AC-independent for one

2

hour on the batteries. Power for the remaining seven hours of the

coping duration would be provided by the alternate AC (AAC) source which

was the Appendix R diesel generator. Starting of the AAC source and

alignment of the SBO loads was required to be accomplished within one

hour of determination of the SBO condition due to the limited battery

capacity. The following SBO loads were required to maintain the plant

at hot shutdown:

1.

Charging Pump A

2.

Service Water Pump D

3.

Component Cooling Water Pump A

4.

Motor Control Center (MCC)-5, which included Battery

Charger A

5.

Dedicated Shutdown Auxiliary Panel

2.2

AAC Source

The AAC source at Robinson was the Appendix R diesel generator which was

referred to as the dedicated shutdown diesel generator (DSDG). This was

classified in the SE as a minimally capable AAC power source design.

This design is not capable of powering all or any normal train of

safety-related shutdown equipment; but is capable of powering specific

equipment adequate for attaining safe shutdown during an SB0 in

conjunction with extensive operator actions both inside and outside of

the control room. The inspector noted that extensive manual operator

action was required outside the control room to start the AAC diesel

generator and align the necessary SBO equipment loads.

The DSDG was a General Motors Model EMD 20-645E4B, 20 cylinder diesel

engine coupled to a Beloit Type TBGZJ 2600 kW, 4160 VAC generator The

2600 kW capacity exceeded the SBO load requirement of approximately 1968

kW stated in Robinson NUS Report Number 8S19-P-100, AAC Power Criteria,

revision 4. The DSDG was independent of offsite and onsite emergency

power sources. The inspector concluded that the DSDG source met the

10 CFR 50.63 requirements for capacity and independence.

2.3

Modifications

There were two modifications related to SBO equipment. Modification

M-1129, Civil Compliance with SB0 Rule, upgraded SBO equipment and

structures to withstand wind forces based on criteria from the Uniform

Building Code. The upgrades were required on conduit supports,

electrical duct supports, the DSDG battery storage cabinet, and the 4.16

kV switchgear enclosure. Modification M-1081, Nitrogen Supply Backup to

Instrument Air, installed permanent one inch piping to connect the

nitrogen source to the PORVs. The inspector reviewed the modification

package and verified the field installation of these modifications and

concluded that the SBO related modifications had been completed.

2.4

Procedures

The inspector reviewed the licensee's operating procedures which

required revision to comply with the SBO rule. The following procedures

were revised to address operator actions during an SBO event:

  • End Path Procedure EPP-1, Loss of All AC Power, revision 11
  • EPP-22, Energizing Plant Equipment Using the DSDG, revision 7
  • Abnormal Operating Procedure, AOP-017, Loss of Instrument Air,

revision 12

revision 36

  • PEP-355, Station Blackout Containment Isolation, revision 7

The procedures were appropriately revised to address SBO operator

actions.

Additionally, the inspector accompanied a non-licensed operator on a

walk-through of two SBO evolutions to verify the location and

accessibility of equipment and determine the operator's familiarity with

the evolutions. The evolutions were for PORV control with the nitrogen

backup supply for instrument air using AOP-017, and cross-connection of

the service water system to supply auxiliary feedwater using procedure

OP-402. The inspector concluded that the equipment was accessible and

that necessary tools and ladders were appropriately located to support

these evolutions. The operator was familiar with the procedures and the

evolutions.

2.5

Training

The inspector reviewed operator training documentation to determine if

SBO training had been accomplished. The following training plans and

simululator exercise guides were reviewed:

  • Reactor Operator (RO) Lesson EOP-LP-5, Emergency Operating

Procedures, EPP-1, EPP-21, EPP-22, dated December 13, 1993

  • RO Lesson Plant EOP-LP-6, Emergency Operating Procedures, EPP-2,

EPP-23, Recovery From Loss of All AC, Restoration of Cooling Water

to Reactor Coolant Pumps, dated February 22, 1994

  • RO/SRO Lesson Plant MDTA-LP-3, Mitigating Core Damage Loss of All

AC Power, dated July 27, 1988

  • RO Simulator Exercise Guide, RO-SE-059, Loss of All AC Power,

dated June 10, 1994

4

  • SRO Simulator Exercise Guide, SR-SE-009, Loss of All AC Power,

dated April 11, 1994

  • SRO Simulator Exercise Guide, SR-SE-025, Loss of All AC with LOCA,

date April 25, 1994

Additionally, the inspector reviewed the training rosters for 1993 and

1994, to determine if the operating shift crews had received the SBO

training. The inspector concluded that the SBO rule issues had been

incorporated into the operator training program and the operating shift

crews had been trained.

2.6

EDG Reliability Program

The licensee's Emergency Diesel Generator (EDG) reliability program was

implemented by Technical Management Manual Procedure, TMM-034, EDG

Reliability Program, revision 0. This procedure incorporated the

required elements specified in Regulatory Guide (RG) 1.155, Station

Blackout, dated August, 1988. The Robinson SBO EDG reliability of 0.95

and the appropriate failure trigger values were included in this

procedure. The current EDG reliability values exceeded the minimum 0.95

target value. The inspector concluded that the licensee had implemented

an EDG reliability program consistent with the RG 1.155 requirements.

2.7

Quality Assurance (QA) Program

The licensee's Plant Program Procedure PLP-018, QA Program for Non

Safety Related Systems and Equipment Used to Meet SBO Rule, revision 1,

implemented the QA program for the SBO equipment. The inspector

verified that the program elements specified in RG 1.155, Appendix A,

were incorporated into the licensee's QA program for SB0 equipment.

2.8

Testing

2.8.1 Test Requirement

The inspector reviewed the licensee's documentation to determine if

adequate testing had been accomplished to demonstrate the capability of

the AAC source. A primary element of the Robinson SBO coping strategy

was that the AAC source would be started and the required SBO equipment

aligned within one hour. The applicable regulation, 10 CFR 50.63,

requires that this capability, the time required for AAC source startup

and alignment to SB0 equipment, be demonstrated by a test. RG 1.155,

Appendix A, requires that a test program be implemented to ensure that

testing is performed to demonstrate conformance with system design and

readiness requirements, and that these tests be performed in accordance

with written test procedures. As discussed in the following paragraphs,

the licensee's test activity did not adequately demonstrate this primary

element of the Robinson SB0 coping strategy nor was the referenced test

activity performed in accordance with written test procedures.

2.8.2 Test Documentation

The licensee's documentation related to the test activity to demonstrate

the one hour capability of the AAC source was a memorandum from

D.B. Blakeney to File, dated February 1, 1993. This memorandum

described the performance of a simulator SBO event scenario in

conjunction with an in-plant walk-through of emergency procedure EPP-22

for energizing and loading of the AAC source. The simulator was manned

with a qualified operations shift crew and the procedure walk-through

was performed by a licensed operator. As described in the memorandum,

the DSDG was not started and the SBO equipment loads were not physically

aligned to the dedicated shutdown (DS) bus.

There was no written test

procedure. The emergency procedures were used for guidance in this

activity.

The memorandum stated that the process was discontinued to correct

procedure problems and the timed walk-through was restarted and

completed. Process milestones and their completion times were listed in

the memorandum and the total time was 49 minutes and 12 seconds.

Additional test documentation included surveillance test procedures,

OST-910, Biweekly Test of the DSDG, dated November 26, 1992, and

OST-911, Dedicated Shutdown Control Panel Test, dated November 27,1993.

The time required from start of the DSDG to closing of the DSDG output

breaker onto the DS bus was demonstrated by OST-910 test document to be

nine minutes. This did not support the 4 minute and 40 second time

period, for energizing the DS bus via the DSDG, stated in the

memorandum. The DSDG loading to 1970 kW during this test demonstrated

the capacity to supply the 1968 kW SBO load referenced in Robinson NUS

Report No. 8S19-P-100 although the SBO loads were not loaded. The DSDG

was loaded in parallel with the grid.

The OST-911 procedure, and modification documents M-445F and M-1004,

demonstrated that each of the SBO equipment loads have been connected to

the DS bus at some time in the past. These documents, however, did not

provide a demonstration that all the SBO loads were loaded onto the DS

bus simultaneously or indicate the time required for manual operator

actions to load any one load or group of loads. Therefore there was no

information to confirm the times stated in the memorandum for manual

operator actions.

2.8.3 Testing Conclusion

Based on the available documentation, the inspector concluded that the

licensee did not meet the requirements of 10 CFR 50.63 related to the

testing demonstration of the one hour capability of the AAC source for

startup and alignment of SBO equipment. The testing performed was

inadequate in that it did not establish the actual SBO configuration for

the AAC source and equipment and the test activity was not accomplished

in accordance with written test procedures. This item is identified as

Violation 50-261/94-24-01, Inadequate Testing of SBO Alternate AC Power

Source.

6

'

3.0

Follow-up on Previously Identified Inspection Findings (92701)

3.1

(Closed) Unresolved Item (URI) 50-261/89-26-02, Environmental

Qualification (EQ) of Submerged Cables

This item addressed the adequacy of the licensee's EQ files in

demonstrating the qualification of certain safety related cables to

withstand submergence conditions during a loss-of-coolant-accident

(LOCA).

The licensee became aware of the suspected unqualified

equipment in November, 1988, when it was identified that the containment

LOCA submergence level was potentially higher than the previously

accepted level.

The potentially unqualified equipment condition was

reported to the NRC in Licensee Event Report (LER) 88-22 in November,

1988. Supplement 1 to this LER was submitted in August, 1989.

The item was addressed in NRC Inspection Report 50-261/89-26 and

identified as unresolved pending the licensee providing documentation of

testing to verify the qualification of the cables. Subsequent

documentation provided to the licensee by the cable vendors was

submitted to the NRC in March 1992. This documentation was not adequate

to verify cable qualification as stated in an NRC safety evaluation

which was transmitted to the licensee on February 10, 1994. This URI is

closed based on the determination that the cables' qualification could

not be verified.

The lack of documentation to qualify these safety related cables is

identified as a violation of 10 CFR 50.49, EQ of Electrical Equipment

Important to Safety for Nuclear Power Plants. Section J of 10 CFR 50.49

requires that qualification documentation be maintained for the period

in which the covered item is installed in the plant. Upon the NRC

February 10, 1994, notification, that the available EQ documentation did

not verify the equipment qualification, the licensee initiated an

Engineering Evaluation (EE) to address operability related to this

equipment. EE 94-032, EQ Equipment Subject to Submergence, revision 0,

identified the 27 specific instrument cables subject to this condition

and determined that the safety function of the equipment could be

accomplished by other qualified equipment as an interim operability

determination until corrective actions were completed.

The licensee initiated corrective action to replace or upgrade the

cables to a tested and qualified configuration. A modification was

being developed during this inspection (Mod-M-1165) to replace or

upgrade the cables identified in EE 94-032. The modification

implementation was tentatively scheduled for the next refueling outage

which would be the first opportunity to perform this outage related

modification.

The inspector reviewed the licensee's identification and corrective

actions for this violation to determine if the NRC Enforcement Policy

criteria of 10 CFR Part 2, Appendix C, Section VII B for non-cited

violations (NCV) had been met. Based on the information discussed above

the inspector concluded that NCV criteria had been met. The violation

7

was identified by the licensee, it was not a violation which could have

been prevented by corrective actions for a finding in the previous two

years, corrective action will be accomplished in a reasonable length of

time, and the violation was not willful.

This item is identified as NCV

50-261/94-24-02, Inadequate EQ Documentation for Submerged Safety

Related Instrument Cables.

3.2

(Closed) URI 50-261/91-03-01, Evaluate LOCA/Submergence Test Results for

Qualification of Patel Conduit Seals

This item identified that the EQ file documentation for Patel Conduit

Seals did not adequately establish equipment qualification. The item

was unresolved pending additional testing of the Patel seals and

inclusion of the test documentation in the EQ files. This item was

reviewed in NRC Inspection Report No. 50-261/93-21 and a vender EQ test

report was provided. Engineering and Advanced Technology (EGS) report

EGS-TR-841215-08, Final Test Report for Qualification/Submergence

Retesting of Patel/EGS Conduit Seals, dated October 14, 1993, was

reviewed. The item remained open pending evaluation of the test by the

licensee and documentation of the test in the EQ files.

During this inspection the inspector verified that the licensee's retest

evaluation was adequate and the EQ File documentation was completed.

EQ Documentation Package (EQDP) 21.0, Patel Seals, revision 5, dated

February 28, 1994 incorporated the test information into the EQ files

and provided the licensee's test evaluation. This item is closed.

3.3

(Closed) IFI 50-261/91-21-03, E1/E2 Equipment Room Ambient Temperature

Conditions Not Evaluated

This item identified that ambient conditions in the safety-related

electrical equipment room had not been analyzed to determine the

potential impact on equipment if the non-safety ventilation was lost to

this space during a design base accident (DBA).

The licensee had

performed an analysis based on industry reference values for equipment

heat loads which produced results that were not consistent with informal

tested conditions. The licensee stated a formal test would be conducted

in 1992, to determine ambient conditions and the equipment would be

evaluated for these conditions.

The inspector reviewed the test document and the equipment evaluation

report. Special Procedure SP-1142, Area Temperature Measurements of the

E1/E2 Room for Determination of Internal Heat Gain, revision 0,

documented the test performance. The equipment evaluations were

documented in the E1/E2 50*C Equipment Evaluation Report, dated

July 20, 1994. The inspector concluded that the E1/E2 equipment room

ambient temperature DBA condition had been adequately evaluated. This

item is closed.

)

8

4.0

Exit Interview

The inspection scope and results were summarized on September 16, 1994,

with those individuals indicated in paragraph 1. The inspector

described the areas inspected and discussed in detail the inspection

findings listed below.

Licensee management provided a dissenting

comment regarding the SBO violation, stating their opinion that their

commitment to demonstrate the AAC power source capability was limited to

demonstration that the AAC power source could be started and connected

to the DS bus in one hour. They considered this commitment to be met by

the testing performed.

The EQ Cable Submergence finding was not identified as a violation at

the exit meeting. This finding was identified as a violation during

regional management review of inspection findings in the week following

the inspection. The licensee was informed of this violation by

telephone on September 26, 1994.

(Open) Violation 50-261/94-24-01, Inadequate Testing of SBO Alternate AC

Power Source

(Open) NCV 50-261/94-24-02, Inadequate EQ Documentation for Submerged

Safety-Related Instrument Cables,

(Closed) URI 50-261/89-26-02, EQ of Submerged Cables

(Closed) URI 50-261/91-03-01, Evaluate LOCA/Submerged Test Results for

Qualification of Patel Conduit Seals

(Closed) IFI 50-261/91-21-03, E1/E2 Equipment Room Ambient Temperature

Conditions Not Evaluated

5.0

Acronyms and Abbreviations

AC

Alternating current

AAC

Alternate AC (source)

AOP

Abnormal Operating Procedure

DBA

Design Basis Accident

DS

Dedicated Shutdown

DSDG Dedicated Shutdown Diesel Generator

EDG

Emergency Diesel Generator

EE

Engineering Evaluation

EOP

Emergency Operating Procedure

EPP

Emergency Path Procedure

EQ

Environmental Qualification

kV

kiloVolts

kW

kiloWatts

LER

Licensee Event Report

LOCA Loss-of-Coolant-Accident

OP

Operating Procedure

OST

Operations Surveillance Test

mPEP

Plant Procedure

9

PORV

Power Operated Rel i ef Val ve

QA

Quality Assurance

RG

Regulatory Guide

RO

Reactor Operator

SBO

Station blackout

SE

Safety Evaluation

SSE

Supplemental Safety Evaluation

SRO

Senior Reactor Operator