Grants Util 850322 Request for Extension of Deadline Until 861231 to Implement Upgraded Emergency Operating Procedures & Submit Dcrdr Summary Rept
ML20134B257
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/06/1985
From: Thompson H
Office of Nuclear Reactor Regulation
To: Beckham J
GEORGIA POWER CO.
References
TAC-57306, TAC-57307, NUDOCS 8508150563
Download: ML20134B257 (3)


Text

'

', August 6, 1985 W B o)L Docket Nos. 50-321 and 50-366 DISTRIBUi!0N 0 ELD (6VRNS) c Docket Fils ) Glainas NRC PDR HThompson Local PDR ACRS (10)

,' ORBf4 Reading BGrimes Mr. J. T. Beckham, Jr. GRivenbark EJordan Vice President - Nuclear Generation JStolz JPartlow Georgia Power Company RIngram Gray File Post Office Box 4545 Atlanta, Georgia 30302

Dear Mr. Beckham:

By letter dated March 22, 1985, Georgia Power Company (GPC) requested an extension to dates contained in the NRC's February 21, 1984 Confinnatory Order for Hatch Units I and 2 as follows:

Requirement Existing Deadlines Extension Request Implement upgraded emergency December 31, 1985 December 31, 1986 operating procedures (EOP)

Submit a detailed control June 30,.1986 December 31, 1986 room design review (DCRDR) sumary report including a proposed schedule for implementation GPC stated that the extension of the E0P implementation date is warranted because an unforeseen remedial training program for Hatch licensed operators has become necessary, and could not be deferred until E0P training is completed. In response to NRC Region II concerns regarding the Hatch licensed operator requalification program, GPC has agreed to conduct a comprehensive training program over a 9 month period for all Hatch licensed operators. This training program and its follow-on tests have preempted the operator and control room simulator time needed for training for the new E0Ps. GPC stated that its DCDR schedule assumed that the E0Ps would be implemented and that an adequate number of E0P trained operators-would be available. It requested schedular relief for the DCDR because of the deferral of E0P training.

We find, based on our evaluation of the information provided by the ,

licensee in requesting this extension, that GPC has adequately justified the delays in meeting the completion dates that the proposed extension is I reasonable, l

I 8508150563 050806 PDR ADOCK 05000321 F PDR

- - - - _ . _ . _ - - - - - - - - - - _ - -- -e

r n Y ,

l l 'J. T. Beckham i Therefore, I have concluded, in accordance with Section III of the Order, good cause has been shown for extending the time for implementation of the upgraded E0Ps from December 31, 1985 to December 31, 1986; and for submittal of the DCRDR Summary Report from June 30, 1986 to December 31, 1986.

Sincerely, Orlynal Signed by litgh L Thompson, Jr, Hugh L. Thompson, Jr., Director Division of Licensing Office of Nuclear Reactor Regulation f

cc:

See next page I -

OR DL 0 DL DELD $ Q AD- DL DIR:Dbf f 0RAB y.ewol.l.h GRivenbark:rc JS m'. G inas HT ompuan -0:el o;,oi.

07////85 07/ /85 / '07/ /85 f///85 0 g/85 $/1/85

Mr. J. T. Beckham, Jr. Edwin I. Hatch Nuclear Plant, Georgia Power Company Units Nos. I and 2 cc:

G. F. Trowbridge, Esq. s Shaw, Pittman, Potts and Trowbridge 1800 M Street, N.W. -

Washington, D.C. 20036 Mr. L. T. Gucwa Engineering Department Georgia Power Company P. O. Box 4545 Atlanta, Georgia 30302 Mr. H. C. Nix, Jr., General Manager

- Edwin I. Hatch Nuclear Plant -

Georgia Power Company P. O. Box 442 Baxley, Georgia 31513

'$ Mr. Louis B. Long Southern Company Services, Inc.

P. O. Box 2625 Birmingham, Alabama 35202 Resident Inspector U.S. Nuclear Regulatory Comission Route 1, P. O. Box 279 Baxley, Georgia 31513 Regional Administrator, Region II U.S. Nuclear Regulatory Comission, 101 Marietta Street, Suite 3100 Atlanta, Georiga 30303 Mr. Charles H. Badger

  • Office of Planning and Budget Room 610 270 Washington Street, S.W.

Atlanta, Georgia 30334 Mr. J. Leonard Ledbetter, Comissioner l Department of Natural Resources l 270 Washington Street, N.W. '

Atlanta, Georgia 30334 Chairman Appling County Comissioners -

County Courthouse Baxley, Georgia 31513

-