| title = Summary of Telephone Conference Call Held on February 12, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Concerning Requests for Additional Information Pertaining to the Callaway Plant, Un
| title = Summary of Telephone Conference Call Held on February 12, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Concerning Requests for Additional Information Pertaining to the Callaway Plant, Un
| author name = Daily J W
| author name = Daily J
| author affiliation = NRC/NRR/DLR/RPB1
| author affiliation = NRC/NRR/DLR/RPB1
| addressee name =  
| addressee name =  
Line 14: Line 14:
| page count = 5
| page count = 5
| project = TAC:ME7708
| project = TAC:ME7708
| stage = RAI
}}
}}


=Text=
=Text=
{{#Wiki_filter: UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 8, 2014   LICENSEE: Union Electric Company (Ameren Missouri)   FACILITY: Callaway Plant, Unit 1 SUBJECT: SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 8, 2014 LICENSEE:       Union Electric Company (Ameren Missouri)
FACILITY:       Callaway Plant, Unit 1
 
==SUBJECT:==
 
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),
CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)
CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri) held a telephone conference call on February 12, 2014, to discuss and clarify Ameren Missouri's responses to the NRC staff's requests for additional information concerning the Callaway Plant, Unit 1, license renewal application. Enclosure 1 provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with Ameren Missouri. A brief description on the status of the items is also included. Ameren Missouri had an opportunity to comment on this summary.
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri) held a telephone conference call on February 12, 2014, to discuss and clarify Ameren Missouris responses to the NRC staffs requests for additional information concerning the Callaway Plant, Unit 1, license renewal application. provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with Ameren Missouri. A brief description on the status of the items is also included.
Sincerely, /RA/ John W. Daily, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483
Ameren Missouri had an opportunity to comment on this summary.
Sincerely,
                                                /RA/
John W. Daily, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483


==Enclosures:==
==Enclosures:==
1. List of Participants 2. List of Requests for Additional     Information cc w/encls: Listserv
: 1. List of Participants
: 2. List of Requests for Additional Information cc w/encls: Listserv
 
ML14177A595                                    *concurred via email OFFICE LA:RPB2:DLR*              PM:RPB1:DLR            BC:RPB1:DLR          PM:RPB1:DLR NAME        IKing                JDaily                YDiaz-Sanabria        JDaily (SCuadrado for)
DATE        6/27/14              7/7/14                7/7/14                7/8/14


July 8, 2014  LICENSEE: Union Electric Company (Ameren Missouri)    FACILITY: Callaway Plant, Unit 1  SUBJECT:  SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),
==SUMMARY==
CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)  The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri or the applicant) held a telephone conference call on February 12, 2014, to discuss and clarify Ameren Missouri's responses to the NRC staff's requests for additional information concerning the Callaway Plant, Unit 1, license renewal application.   
OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS February 12, 2014 PARTICIPANTS                      AFFILIATIONS Samuel Cuadrado de Jesús          U.S. Nuclear Regulatory Commission (NRC)
John Wise                          NRC James (Jim) Gavula                NRC William (Bill) Holston            NRC Dave Shafer                        Callaway (Ameren Missouri)
Andrew Burgess                    Callaway (Ameren Missouri)
Eric Blocher                      STARS ENCLOSURE 1


==Enclosure==
==SUMMARY==
1 provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with Ameren Missouri. A brief description on the status of the items is also included. Ameren Missouri had an opportunity to comment on this summary.
OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION February 12, 2014 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri) held a telephone conference call on February 12, 2014, to discuss and clarify the responses to requests for additional information (RAIs) concerning the Callaway Plant, Unit 1 (Callaway), license renewal application (LRA).
Sincerely, /RA/ John W. Daily, Sr. Project Manager Projects Branch 1  Division of License Renewal Office of Nuclear Reactor Regulation  Docket No. 50-483  Enclosures:  1. List of Participants 2. List of Requests for Additional    Information  cc w/encls:  Listserv  DISTRIBUTION: See next page ADAMS Accession No.:  ML14177A595    *concurred via email OFFICE LA:RPB2:DLR* PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME IKing JDaily  (SCuadrado for) YDiaz-Sanabria JDaily DATE 6/27/14 7/7/14 7/7/14 7/8/14 OFFICIAL RECORD COPY ENCLOSURE 1 SUMMARY OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION  LIST OF PARTICIPANTS February 12, 2014  PARTICIPANTS AFFILIATIONS Samuel Cuadrado de Jesús U.S. Nuclear Regulatory Commission (NRC) John Wise NRC  James (Jim) Gavula NRC William (Bill) Holston NRC Dave Shafer Callaway (Ameren Missouri) Andrew Burgess Callaway (Ameren Missouri) Eric Blocher STARS ENCLOSURE 2 SUMMARY OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION February 12, 2014 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri) held a telephone conference call on February 12, 2014, to discuss and clarify the responses to requests for additional information (RAIs) concerning the Callaway Plant, Unit 1 (Callaway), license renewal application (LRA). December 20, 2013, Response to RAI Set No. 28 (LRA Amendment No. 28) Discussion: The staff stated that it needed clarification on the "Discussion" column for item 3.3.1.128 on Table 3.3-1. Ameren Missouri understood and stated that clarification will be provided in a future letter to the staff. The staff stated that Table 3.3.2-4 may have an error on the Note 3 assigned to one of the aging management review (AMR) items. Ameren Missouri agreed with the staff and stated that the AMR should have been assigned a Note 5. Ameren Missouri further stated that it will correct this error in a future letter to the staff.
December 20, 2013, Response to RAI Set No. 28 (LRA Amendment No. 28)
The staff stated that several tables in Enclosure 2 include new AMR items that cite Generic Aging Lessons Learned (GALL) Report Items VII.C1.A-408a or VII.C1.A-409a, and it was unclear to the staff what the "a" at the end of these items meant. Ameren Missouri stated that these item numbers appeared to be erroneously duplicated in the staff's LR-ISG-2012-01 and LR-ISG-2012-02, and the "a" designation was Ameren Missouri's method to differentiate the numbers. The staff stated that it will review the two ISGs to confirm the GALL Report Items numbering.
Discussion: The staff stated that it needed clarification on the Discussion column for item 3.3.1.128 on Table 3.3-1. Ameren Missouri understood and stated that clarification will be provided in a future letter to the staff.
The staff stated that on page 57 of Enclosure 2 there are two AMR items that reference GALL Report Item VII.E5.A-41 and Table 1 Item 3.3.1.072. The two AMR items are assigned a Note A. The staff asked Ameren whether the references made are correct. Ameren Missouri stated that the reference to item 3.3.1.072 needs to be revised because that is the incorrect Table 1 Item. Ameren Missouri stated that it will provide the correction in a future letter to the staff. The staff noted that on page 111 of Enclosure 2 an enhancement to the Fire Protection Program has been deleted. A portion of the deleted enhancement stated the following "[p]rocedures will be enhanced to include visual inspections of the external surfaces of Halon fire suppression system components for excessive loss of material due to corrosion.However, Page 2 of the cover letter states the following "[r]evised Commitment 9 to reflect completion of visual inspection of the Halon fire protection system components.It is not clear to the staff whether Ameren Missouri revised the Fire Protection enhancement and Commitment 9 because visual inspections were completed or because Callaway procedures were revised to include the visual inspections consistent with the original proposed enhancement to the Fire Protection Program. Ameren Missouri stated that the changes made to the Fire Protection Program were a result of Callaway's procedure being revised consistent with the original proposed enhancement.
The staff stated that Table 3.3.2-4 may have an error on the Note 3 assigned to one of the aging management review (AMR) items. Ameren Missouri agreed with the staff and stated that the AMR should have been assigned a Note 5. Ameren Missouri further stated that it will correct this error in a future letter to the staff.
Action: Ameren Missouri will provide clarifications in its next letter to the staff. The staff will review LR-ISG-2012-01 and LR-ISG-2012-02 to confirm the adequacy of the GALL Report Item referenced.
The staff stated that several tables in Enclosure 2 include new AMR items that cite Generic Aging Lessons Learned (GALL) Report Items VII.C1.A-408a or VII.C1.A-409a, and it was unclear to the staff what the a at the end of these items meant. Ameren Missouri stated that these item numbers appeared to be erroneously duplicated in the staffs LR-ISG-2012-01 and LR-ISG-2012-02, and the a designation was Ameren Missouris method to differentiate the numbers. The staff stated that it will review the two ISGs to confirm the GALL Report Items numbering.
SUBJECT: SUMMARY OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),
The staff stated that on page 57 of Enclosure 2 there are two AMR items that reference GALL Report Item VII.E5.A-41 and Table 1 Item 3.3.1.072. The two AMR items are assigned a Note A. The staff asked Ameren whether the references made are correct. Ameren Missouri stated that the reference to item 3.3.1.072 needs to be revised because that is the incorrect Table 1 Item. Ameren Missouri stated that it will provide the correction in a future letter to the staff.
CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708) DISTRIBUTION:
The staff noted that on page 111 of Enclosure 2 an enhancement to the Fire Protection Program has been deleted. A portion of the deleted enhancement stated the following [p]rocedures will be enhanced to include visual inspections of the external surfaces of Halon fire suppression system components for excessive loss of material due to corrosion. However, Page 2 of the cover letter states the following [r]evised Commitment 9 to reflect completion of visual inspection of the Halon fire protection system components. It is not clear to the staff whether Ameren Missouri revised the Fire Protection enhancement and Commitment 9 because visual inspections were completed or because Callaway procedures were revised to include the visual inspections consistent with the original proposed enhancement to the Fire Protection Program.
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource --------------------- JDaily                                                                                                                               THartman DMorey BMizuno (OGC) GPick (RIV)  
Ameren Missouri stated that the changes made to the Fire Protection Program were a result of Callaways procedure being revised consistent with the original proposed enhancement.
}}
Action: Ameren Missouri will provide clarifications in its next letter to the staff. The staff will review LR-ISG-2012-01 and LR-ISG-2012-02 to confirm the adequacy of the GALL Report Item referenced.
ENCLOSURE 2
 
==SUBJECT:==
 
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),
CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource JDaily THartman DMorey BMizuno (OGC)
GPick (RIV)}}

Latest revision as of 20:19, 5 February 2020

Summary of Telephone Conference Call Held on February 12, 2014, Between the U.S. Nuclear Regulatory Commission and Union Electric Company (Ameren Missouri), Concerning Requests for Additional Information Pertaining to the Callaway Plant, Un
ML14177A595
Person / Time
Site: Callaway Ameren icon.png
Issue date: 07/08/2014
From: Daily J
License Renewal Projects Branch 1
To:
Union Electric Co
CuadradoDeJesus S, 415-2946
References
TAC ME7708
Download: ML14177A595 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 8, 2014 LICENSEE: Union Electric Company (Ameren Missouri)

FACILITY: Callaway Plant, Unit 1

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),

CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)

The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri) held a telephone conference call on February 12, 2014, to discuss and clarify Ameren Missouris responses to the NRC staffs requests for additional information concerning the Callaway Plant, Unit 1, license renewal application. provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with Ameren Missouri. A brief description on the status of the items is also included.

Ameren Missouri had an opportunity to comment on this summary.

Sincerely,

/RA/

John W. Daily, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483

Enclosures:

1. List of Participants
2. List of Requests for Additional Information cc w/encls: Listserv

ML14177A595 *concurred via email OFFICE LA:RPB2:DLR* PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME IKing JDaily YDiaz-Sanabria JDaily (SCuadrado for)

DATE 6/27/14 7/7/14 7/7/14 7/8/14

SUMMARY

OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS February 12, 2014 PARTICIPANTS AFFILIATIONS Samuel Cuadrado de Jesús U.S. Nuclear Regulatory Commission (NRC)

John Wise NRC James (Jim) Gavula NRC William (Bill) Holston NRC Dave Shafer Callaway (Ameren Missouri)

Andrew Burgess Callaway (Ameren Missouri)

Eric Blocher STARS ENCLOSURE 1

SUMMARY

OF TELEPHONE CONFERENCE CALL CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION February 12, 2014 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Union Electric Company (Ameren Missouri) held a telephone conference call on February 12, 2014, to discuss and clarify the responses to requests for additional information (RAIs) concerning the Callaway Plant, Unit 1 (Callaway), license renewal application (LRA).

December 20, 2013, Response to RAI Set No. 28 (LRA Amendment No. 28)

Discussion: The staff stated that it needed clarification on the Discussion column for item 3.3.1.128 on Table 3.3-1. Ameren Missouri understood and stated that clarification will be provided in a future letter to the staff.

The staff stated that Table 3.3.2-4 may have an error on the Note 3 assigned to one of the aging management review (AMR) items. Ameren Missouri agreed with the staff and stated that the AMR should have been assigned a Note 5. Ameren Missouri further stated that it will correct this error in a future letter to the staff.

The staff stated that several tables in Enclosure 2 include new AMR items that cite Generic Aging Lessons Learned (GALL) Report Items VII.C1.A-408a or VII.C1.A-409a, and it was unclear to the staff what the a at the end of these items meant. Ameren Missouri stated that these item numbers appeared to be erroneously duplicated in the staffs LR-ISG-2012-01 and LR-ISG-2012-02, and the a designation was Ameren Missouris method to differentiate the numbers. The staff stated that it will review the two ISGs to confirm the GALL Report Items numbering.

The staff stated that on page 57 of Enclosure 2 there are two AMR items that reference GALL Report Item VII.E5.A-41 and Table 1 Item 3.3.1.072. The two AMR items are assigned a Note A. The staff asked Ameren whether the references made are correct. Ameren Missouri stated that the reference to item 3.3.1.072 needs to be revised because that is the incorrect Table 1 Item. Ameren Missouri stated that it will provide the correction in a future letter to the staff.

The staff noted that on page 111 of Enclosure 2 an enhancement to the Fire Protection Program has been deleted. A portion of the deleted enhancement stated the following [p]rocedures will be enhanced to include visual inspections of the external surfaces of Halon fire suppression system components for excessive loss of material due to corrosion. However, Page 2 of the cover letter states the following [r]evised Commitment 9 to reflect completion of visual inspection of the Halon fire protection system components. It is not clear to the staff whether Ameren Missouri revised the Fire Protection enhancement and Commitment 9 because visual inspections were completed or because Callaway procedures were revised to include the visual inspections consistent with the original proposed enhancement to the Fire Protection Program.

Ameren Missouri stated that the changes made to the Fire Protection Program were a result of Callaways procedure being revised consistent with the original proposed enhancement.

Action: Ameren Missouri will provide clarifications in its next letter to the staff. The staff will review LR-ISG-2012-01 and LR-ISG-2012-02 to confirm the adequacy of the GALL Report Item referenced.

ENCLOSURE 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON FEBRUARY 12, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND UNION ELECTRIC COMPANY (AMEREN MISSOURI),

CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE CALLAWAY PLANT, UNIT 1, LICENSE RENEWAL APPLICATION (TAC. NO. ME7708)