IR 05000369/1988015

From kanterella
Jump to navigation Jump to search
Insp Repts 50-369/88-15 & 50-370/88-15 on 880613-17.No Violations or Deviations Noted.Major Areas Inspected:Nde Procedures Review,Observation & Review of in-process NDE Exam & Review of Inservice Insp Exam Data
ML20150B539
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 06/30/1988
From: Blake J, Newsome R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20150B533 List:
References
50-369-88-15, 50-370-88-15, NUDOCS 8807120062
Download: ML20150B539 (12)


Text

' , r ,., jg , > > ,

' * '

.

., g ;W -

'

, t g4 8Uo/- . '

m UNITED STATES 748' ' NUCLEAR REGULATORY COMMISSION

-

, .4 , -1

- ' REGloN il

>

-Q'

y

.o 101 MARIETTA STREET, ,7 j .

't *- t ATLANTA, GEORGI A 30323 h

y*..../

Report Nos.: 50-369/88-15 and 50-370/88-15

'

Licensee: Deke; Power' Company 422 South Church Street Charlotte, NC 28242 Docket Nos.: 50-369 and 50-370 License Nos.* NPF-9 and NPF-17 Facility.Name: McGuire 1 and 2

'Inspectio -o du ted- June 13-17, 1988 Inspecto : '-

4./ d 5 L . me Dhte S'igned Appr e v 6 To &-

J. lake, Chief Date Signed a ials and Processes Section Di ision of Reactor Safety SUMMARY.

i-Scope: This routine, unannounced inspection. was conducted on site in the areas of inservice inspection (ISI) Unit 2, including review of inspection plan for this outage, Nondestructive Examination (NDE.)

o procedures review Units 1 and 2, observation and review of inprocess l

NDE examinations, and review of ISI examination dat Results: In the areas inspect 3d, violations or deviations were not identified.

!

l l

.,

.

!

,

8807120062 880701 PDR ADOCK 05000369 PNU

'

'

O

,

'p

-

, . . ~ . . .. - . - .

-

.

.

. .

.

.

,

REPORT DETAILS ' Persons Contacted Licensee Employees

  • N. Atherton,. Compliance Production. Specialist
  • L. Bost, Engineering Department
  • J. Day, Licensing, Associate Engineer
  • W. Goodman, Quality Assurance (QA) Technical Support Supervisor
  • B. Hamilton, Superintendent, Technical Services
  • S. LeRoy, Licensing
  • R. Sharpe, Compliance Engineer
  • G. Underwood, QA, ISI, Operations Other licensee employees contacted during this inspection included craf tsmen, engineers, mechanics, security force members, technicians, and administrative personne Other. Organization Babcock & Wilcox R. Patterson, ISI Supervisor NRC Resident Inspector
  • Orders, Senior Resident Inspector
  • Attended exit interview Inservice Inspection (ISI)

The inspector examined documents, activities, and records as indicated below to determine- whether ISI was being conducted in accordance with applicable procedures, regulatory requirements and licensee commitment The applicable code for ISI is American Society of Mechanical Engineers Boiler and Pressure Vessel (ASME B&PV) Code,Section XI, 1980 edition with addenda through Winter 1980. Duke Power Company (DCP) nondestructive examination personnel are performing the liquid penetrant (PT), magnetic particle (MT), and visual (VT) examinations while Babcock and Wilcox (B&W)

personnel are performing the ultrasonic (UT) and primary eddy current (EC)

examination evaluation for Duke Power. Duke Power personnel are being

.used to collect the EC data and are performing a secondary examination data evaluatio .

.

'

.

'

. .

. . .

,

,

.

.

2 Inservice Inspection, Programmatic Review Unit 2(73051)

The inspector reviewed the below listed documents relating to the licensee's. (ISI) program (Plan) for the current outage in the areas of: program approva); QA program. requirements including organiza-tional structure; audit requirements; general QA , requirements-(examination reports, control of deviations from established program,

. quality _ documentation, and identification of components); work and quality inspection procedures; control of processes; corrective action; document contro'; control of examinations and examination-equipment; quality records; inspection scope; inspection intervals; persannel qualifications; and, NDE records including provisions for storag Document Title

. Procedure NDE-C R1 Calibration / Verification of- NDE Equipment Drocedure QCH-3 R1 Weld Preparation for Inservice Inspections Inservice Inspection Plan R10 Unit 2 Outage 4 Ir:pectica Pian Details

< Procedure QCK-1 R23 Control of Nonconforming items y Review of Procedures Units 1 and 2 (73052)

The inspector reviewed the procedures indicated below to determine whether the procedures were consistent with regulatory requirements

'

and licensee commitments. The procedures were also reviewed in. the i areas of procedure approval, requirements for qualification of NDE t personnel, and compilation of required records; and if applicable, I division of responsibility between the ifcensee and contractor i

'~

~ personnel if contractor personnal are involved in the ISI effor Procedure ID Title NDE-25 R12 Magentic Particle Examination Procedure "

and Techni' ques

NDE-35 R10 Liquid Penetrant Examination

?

Ultrasonic Examination of Vessel Welds

'

ISI-130 R24 and Nozzle Inside Radius Sections r

151-424 R11 Multifrequency Eddy Current Examination of .750-inch OD x .044-inch Wall RSG Tubing for Detection of Tube Wear at Support Plate t

. - _ - _ _ _ _ _ _ _ _ _ _ _ _---

,

,

,

. _ ,

y

- y

-

, o .

.

,

>

All procedures listed above had been reviewed tj NRC during previous outages. During the current inspection, only changes to these documents were reviewe (1) The inspector reviewed ultrasonic procedure ISI-130.to ascertain whether it had been reviewed and approved in accordance with the licensee's established QA procedure The procedure = was -

reviewed = for technical adequacy and conformance with ASME -

Section V Article 5 arid other license commitments / requirements in the below following areas: type of apparatus used; extent of coverage of wekment; - calibration requirements; search units; beam angles; DAC curves; reference level for monitoring discontinuities; method for demonstrating penetration; -limits for. evaluating and recording indications; recording significant indications; and, acceptance limit (2)- The inspector reviewed EC procedure ISI-424 'or technical content relative to: multichannel examination unit, multi-channel examination indication equipment is specified, examination sensitivity, material permeability, method of examination, method of calibration and calibration sequence, and acceptance criteri (3) The inspector reviewed PT procedure NDE-35 to ascertain whether

'

'it ~ had been raviewed and approved in accordance' with the-licensee's established QA procedures. .The procedure was reviewed for technical adequacy and conformance with ASME, Section '/ , Article 6, and other licensee commitments /

requirements in the following listed areas: specified method; penetrant material identification; penetrant materials analyzed for sulfur; penetrant materials analyzed for total halogens; acceptable pre-examination surface; drying tire; method of penetrant application; surface tuperature; solvent removal; surface drying prior to developing; type of developer; examination technique; evaluation techniques; and, procedure requai1.ication.

"

(4) The inspector reviewed MT procedure HDE-25 to ascertain whether

> it had been reviewed and approved in acct.,rdance with the licensee's established QA procedure The procedure was reviewed for technical acequacy "-d for ton, mance with ASME Section V, Article 7, -d other licensee commitments / require-ments in the followins liste6 areas: examination methods; contrast of dry powder particle color witn background; surface tamperature; viewing conditions; examination overlap and directions; pole or prod spacing; current or lifting power (yoke); and, acceptance criteria.

I

_ .--

- -- - ,

-

,

.

. .

-

..

4' bservation of York and Work Activities Unit 2(73753)

'The inspector observed work activities and reviewed certification records of equipment, materia'3, and NDE personnel which had been and will be utilized .during the required ISI examinations during this outage. The observations and reviews conducted by the inspector are

, documented belo (1) Ultrasonic (UT) Examination (a) The inspector observed calibration activities and the in process ultrasonic-examinations being conducted on the welds indicated below. The observations were compared with the applicable procedures and the Code in the following areas: availability of ~ and compliance with approved NDE procedure; use of knowledgeable NDE personnel; use of NDE personnel qualified to the proper level; t' pe y of apparatus used; extent of coverage of weldment; calibration requirements; search units; beam angles; DAC curves; reference level for monitoring discontinuities; method of demonstration; recording significant indications; and, acceptance limit Weld ID ISI Item N NI2F-529 B09.011.415 2NI2F-531 B09.011.416 2NI2F-532 B09.011.417 ,

While observing the examination of the above listed welds, '

the NRC inspector became ' concerned with the examinations because the geometric reflectors, that had been reported during the previous UT examination in October 1979, were not being observed during this examination of weld 2NI2F-529 and the geometric reflectors that had been reported on weld 2NI2F-531 were not clearly discernable nor at an amplitude that would warrant there being recorded.

i Also, in both cases, the UT signal from these areas had a very high noise level signal, however, this is not particularly unusual for stainless steel material.

l Following completion of these examinations, the NRC l: inspector expressed his concern to the ISI supervisor. The

'

ISI supervisor indicated that there had been a similar l

problem on an additional weld and that the resson for the L differences in the UT examinations had not yet been resolve The NRC inspertor requested that two sets of UT equipment

! be calibrated. One set was to utilize the transducer used l for the above examinations on a alffer-T.c UT instrument and l

' _ m

._- .__

,

-

.

.

. .

-

.

-3 the other set was to utili7e a different transducer on the UT instrument. that sas used during the examination Following these calibrations, weld 2NI2F-529 was to be re-examined to deteroine if the examination differences could be attributed to a faulty transducer or possible a UT instrument proble During the UT equipment calibrations mentioned above, the UT examiner discovered that he had inadvertently been using a 5.0 MHz transduce; instead of a 2.25 MHz transducer for his examinations which could account for the differences because the 1979 examinations had been made using a 2. 25 MHz transducer. The use of 5.0 MHz transducer is permitted by procedure and code for these examinations, however, the 2.25 MHz transducer has superior penetration power and is used almost exclusively when examining stainless steel material. Discussions with the UT examiner indicated that he had been unaware of his error and had intended to use a 2.25 MHz transducer f ar these examinations in an effort to match the equioment used during the 1979 examination Following the calibration of two sets of equipment with one set utilizing the 5.0 MH7 transducer used during the current examinations and the other set utilizing a 2.25 MHz transducer, the NRC inspector observed portions of the re-exsmination of weld 2NI2F-52 The re-examination indicated no change with the 5.0 MHz transducer, however, with the 2.25 MHz transducer the geometric :sflectors that hau been reported during the 1979 examination were very evident and correlated very closely with the 1979 examination reported result The NRC inspector discussed the above findings with the ISI supervisor and requested that all of the welds that had been examined with a 5.0 MHz transducer be re-examine These re-examinations were accomplished during this L

inspection and the NRC inspector reviewed the re-examination results. The current examination utilizing a 2.25 MHz transducer and the reported 1979 UT results were compared and there did not appear to be any significant discrepancies between the two examination (b) The NRC inspector conducted an ultrasonic verification examination, using B&W equipment, or, portions of the below listed welds. The examinations were performed in order to

! evaluate the technical adequacy af the ultrasonic

! examination procedure being used , the licensee's contractor to perform ultrasonic examinations and to assess i the validity of the information being reported by the l ultrasonic examiners.

l l~

'

'

- <

,

.4

.. .

-

.

,

g -

a

'

Weld ID .ISI Item N ;

2NI2F-531 BC3.011.416 c 2NI2F-532 809.011.417 The verification ultrasonic examinations : conducted by Lthe-inspector ~ indicated that. the procedure being used te conduct - the examinations is adequat .The . information being reported by the ultrasonic ' examiners compared favorably with the verification examination (c) The following listed ultrasonic equipment and materials certification records were reviewed:

Ultrasonic Instruments Manufacturer /Model Serial N <

.T/K-SM100 1343 T/K-SM100 1288 T/K-SM100 1344 The inspector reviewed . spectrum analysis data for ultrasonic transducers with serial rumbers 40241 and '

K8608 Ultrasonic Couplant Batch No, 8767, Sonotrace 40 Ultrasonic Calibration Block 50249

,

(2) Magnetic Particle (MT) Examination l (a) The inspector cbserved the magnetic particle examinations indicted below. The observations were compared with the applicable procedures and the Code in the following areas:

examination methods; contrast of dry powder particle color with backgrouno; surface temperature; viewing conditions; ecamination overlap and directions; pole or prod r, pacing; current or lifting power (yoke); and, acceptance criteri ISI Iten No Weld ID C03.044.001 2-MCR-CF-160 i C05.011.150 2KC2F-2762 l

(b) The inspector reviewed documentation indicating that a 10

. pound lift test had been performed on maqnetic particle AC l

yokes 26082, 26034. MCQUA 26035, and MCQA-'.. ,

,

!

.

'

- - . .

.

. .

. .

,

(c) A review of magnetic particle material certification records for batch number 84H046 indicated the sulfur and halogen content of the material was within acceptable content limit (3) Liquid Penetrant (PT) Cxamination (a) The inspector observed the liquid penetrant examination indicated below. The observations was conpared with the applicable procedure and the Code in the following areas:

specified method, penetrant materials identified; penetrant materials analyzed for halogens and sulfur; acceptable pre-examination surface; drying time; method of penetrant application; penetration time; surface temperature; solvent removal; dry surface prior to developing; type of developer; examination technique; evaluation technique; and reporting of examination result ISI Item N Weld ID C05.021.362A 2 NIP 131-1 (b) The inspector reviewed the below listed liquid penetrant materials certification records to ascertain if the sulfur and halogen content of the material was within acceptable content limit Materials Batch Number Liquid Penetrant 87J022 Cleaner / Remover 87J076 Developer 84M029 (4) Steam Generator Tubing Eddy Current (EC) Examination f'

The inspector observed the Eddy Current activities indicated belo The obserations were compared with the applicable procedures and the Code in the following areas: rethod for j maximum sensitive is applied; method of examination has been recorded; e xam i na t.i on equipment has been calibrated in accordance with the applicable perfarmance reference; required coverage of steam generator tubes occurs during tha examination; acceptance crite-ia is specified or referenced and is consistent with the procedure or the ASME Code; and, results are consistent with acceptance criteri In process eddy current inspection data evaluation was observed l

for the following steam generato* tubes:

i

. __

_ _ - --- ---- -- -- -- - - - - - - - - - - - - . - - - -- -

.- .

  • '

.. -:

x+< ; , ,

-

.

.

Tube ID

'

'

Tube ID SG-B SG-D Row Column Data Typ Row- Column Data Type 16 103 Bobbin Coil 10 41 Bobbin Coil l'6 110- Bobbin Coil 2 9 Bobbin Coil-18- 96 Bobbin'. Coil 9 61 Bobbin Coil-18 10 Bobbin C011 17 99 Bobbin Coil 22 96 Bobbin CoiT -5 101 Bobbin Coil 23 92 Bobbin Coil 30 102 Bobbin Coil 46 63 Bobbin Coil 10 5 360 Coil 20 9 360' Coi'

12 16 360 Coil 13 17 :360 Coil 33 18 360 -Coil 17 20 360 Coil 16 21 360* Coil 36 25 360' Coil 16 26 3E0' Coil

,

39 30 360 Coil

' (5) Examiner Qualification The inspector reviewed the qualification documentation for the below listed DPC & B&W examiners in the following areas; employer's name; person certified; activity qualified to perform; effective period of certification; signature of employer's designated representative; basis used. for certifi-cation; and, annual visual acuity, color vision examination; and periodic recertificatio Method-Level Company Examiner UT PT MT EC VT

- - -

DP BB II II

- - - -

DP DB II

- - -

, DP LG II II

- - -

DP BS II II

- - -

DP TC II II

- - - -

DP GF II

- - - -

DP LC II

- - -

DP LA II II

- - -

DP LM II II

- - -

DP RS II II

- - - -

DP LW Il

- - - -

BW RP II

- - - -

BW JW II

.

--- e =, , , .- . . . . -

.-.....--.7--m- ,.,-,-m--,m,_...,y,

-

_ _ - . _ _ _ - . __. - _ _ _ _ __ . . . __ __ __ -_

'

.- . . .4r .

. 1 d . .

BW CS I - - - -

OP HS - - -

IIA -

DP TG - - -

IIA -

BW JW - - -

IIA -

- - -

BW- .MG -

III BW CP - - --

IIA -

BW VL - - -

IIA -

OP TA - - -

I -

- - - -

DP AG II DP TT - - -

I -

"

d. Inservice. Inspection, Data Review and Evaluation, Unit 2 (72755).

(1) Records of completed nondestructive examinations -were selected and reviewed to ascertain whether: the method (s) technique and extent of the examination complied with the ISI plan and applicable NDE procedures; findings were properly recorded and evaluated by qualified personnel programmatic deviations were recorded as required; personnel, instruments, calibration blocks and NDE materials (penetrants, couplants) were designate Records selected for this review are listed belo ISI Item N Weld N NDE Method B09.011.415A 2NI2F-529 PT B09.011.416A 2NI2F-531 PT B09.011.417A 2NI2F-532 PT B09.011.418A 2NI2F-2747 PT B09.011.422A 2NI2F-557 PT B09.011.423A 2NI2F-559 PT B09.011.424A 2NI2F-563 PT F1.02.944 2MC-SM-H148 VT C05.011.313 2ND2FW2 1 PT C05.011.220 2N02F-71 PT F1.03.071 2MCA-CA-5533 VT C05.011.576 2SM2FW12-27 MT C05.011.577 2SM2FW12-31 MT C05.011.603 2SV2FW2-7 MT C05.011.004 2CA2FW44-1 MT C03.040.016 2-MCA-SM-164 MT C33.040.006 2-MCA-SM-017 MT C03.040.005 2-MCA-SM-015 MT F1.02.479 2-MCA-ND-5615 VT F1.02.953 2-MCA-SM-4184 VT F1.03.066 2-MCA-CA-5527 V1 C05.011.150 2KC2F-2762 MT C03.040.001 2-MCR-CF-160 MT C05.021.365 2NI2F-487 UT C05.021.665 2SM-5A-F UT C05.021.666 2SM-5A-H UT B09.011.061 2NC2Fk53-18 UT 6 , - - - , . - - . _ - , -

m-

...

, .

B09.011.062 2NC2FW53-19 UT C05.021.363 2NI2F-482 UT C05.021.364 2NI2F-484 UT C05.021.366 2NI2F-491 UT B09.011.414 2NI2F-527 UT B09.011.415 2NI2F-529 UT B09.011.416 2NI2F-531 UT B09.011.417 2NI2F-532 UT B09.011.419 2NI2F-543 UT The inspector compared current examination results with rando.mly selected previous examination result No significant discrepancies were note (2) Steam Generator Tubing Eddy Current Examination Data Review (a) The inspector reviewed records of the SG-B eddy current examinations indicated belc 4 The reviews were ccmpared with the applicable procedures and the Code in the following areas: the multichannel eddy current examination equipment has been identified; material permeability has been recorded; method of examination has been recorded; and, results are consistent with ecceptance criteri Row Column 7 90 9 76 20 9 10 46 19 12 18 13 12 14 15 15 27 20 3 24 40 25 16 41 43 47 35 59 30 76 39 97 27 95 8 62 7 64 13 64 3 6

.

. .

,.

(b) At the conclusion of the NRC inspection all examinations had not been complete The inspector discussed the program and status witn the licensee and the preliminary examination status for steam generators B and D are listed below. Examination of steam generators A and C had not yet starte SG-B SG-D i Tubes Scheduled By Code 579 548 Tubes examined 549 548 Tubes with >40% TW indications 15 3 Violations or defiations were not identified in the areas inspecte . Exit Interview The inspection scope and results were summarized on June 17, 1988, with those persons indicated in paragraph 1. The inspector described the areas inspected and discussed in detafl the inspection result Proprietary information is not contained in this repor _